Well Details

Well ID: 42-111-20265
Loading map...
County: Somerset
Municipality: Allegheny Township
Operator Name: SAMSON RES CO
Farm/Lease Name: MOWRY 2
First Permit Date: 2007-09-10
Last Permit Date: 2007-09-10
Spud Date: 2007-11-13
Unconventional: Yes
Horizontal: No
Producing: No
Violations: 1
Latitude: 39.928301
Longitude: -78.775796

Well Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID
1668466 2007-11-15 No Violations Noted WELL SPUDDED ON 11/13/07. PIT/FREEBOARD/E&S CONTROL IN PLACE OK
1781669 2009-04-01 Violation(s) Noted Well completed on 12/4/07/not connected for production/E&S ok. 560009
1887758 2010-05-27 No Violations Noted At the time of inspection well was drilled but not in production. Well initially owned (drilled) by T & F Exploration LP, transferred to Quest Oil and Gas, and now owned by Samson Resources since11/2008 Inactive status approved 5/22/09. Site was properly signed. Access road was in good condition. Brine tanks appeared sound. No accelerated E&S or IW issues were observed. Site was restored with vegetative cover surrounding well and well pad rocked. (Accompanied with, WQS Supervisor, Ed Ritzer at time of inspection).
1963841 2011-04-06 No Violations Noted During inspection, DEP met Samson representative, Marvin Bartlett. Well plug in accordance with 78.92 regulations. Pressure initial on well was 1250 psi. Well was removed of pressure and fluids sent to above ground transfer tank. Marcellus well plugging. Removed all tubing and jack pump from well. Ran wire line on the well and confirmed cementing of well. Top of cement on the 5 ½¿ was 1812 ft. Surface casing (8 5/8¿) was set at 482 ft which was cemented to surface. Samson set mechanical plug at 3440ft. . Process of setting cement plug of 100 ft on top of plug. (13 sks of class A). Top of cement plug was 3300 ft. No pit was completed. Samson using containers for water from well and potable water tanker truck. At the time of inspection, no E&S issues and no IW discharge issues

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
2010-2 0.0 0.0 0.0 0.0 0.0 0.0
2010-3 0.0 0.0 0.0 0.0 0.0 0.0

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE

References