37-129-28137

Well Details

Well ID: 37-129-28137
Loading map...
Operator Name: KRIEBEL MINERALS INC
First Permit Date: 2009-12-15
Last Permit Date: 2009-12-15
Spud Date: 2010-09-14
Unconventional: No
Horizontal: No
Violations: None
Latitude: 40.391433
Longitude: -79.355702

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
2013-0 4633.0 324.0 0.0 0.0 0.0 0.0
2012-0 6427.0 333.0 0.0 0.0 0.0 0.0
2011-0 7586.0 334.0 0.0 0.0 0.0 0.0
2010-0 1663.0 61.0 0.0 0.0 0.0 0.0

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE
2012-0 PRODUCED FLUID 50.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095443 HART RESOURCE TECHNOLOGIES, INC. - CREEKSIDE CREEKSIDE PA
2010-0 PRODUCED FLUID 40.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273 PA BRINE TRT INC - JOSEPHINE PLT, INDIANA COUNTY JOSEPHINE PA
2010-0 DRILLING FLUID WASTE 770.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472 TUNNELTON LIQUIDS COMPANY SALTSBURG PA
2010-0 FRACING FLUID WASTE 1290.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0091472 TUNNELTON LIQUIDS COMPANY SALTSBURG PA
2011-0 PRODUCED FLUID 40.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273 PA BRINE TRT INC - JOSEPHINE PLT, INDIANA COUNTY JOSEPHINE PA
2012-0 PRODUCED FLUID 50.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095443 HART RESOURCE TECHNOLOGIES, INC. - CREEKSIDE CREEKSIDE PA

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID
1914305 2010-09-21 No Violations Noted Drilling was ongoing at the time of the inspection. Belolw grade pit onsite and it had more than the required two feet of lined freeboard. E&S controls had been implemented properly. Access road had been rocked with clean durable rock for stabilization purposes. Minimal site erosion controls neccesary due to the topography of the site. Silt fencing had been installed properly. Noted that the E&S plan was not specific as to what manner the drill cuttings will be disposed. Specifically the plan stated that the drill cuttings "will be disposed of onsite as per DEP regulations." The plan should state specifically whether the drill cuttings are to be encapsulated or land farmed
1915252 2010-09-23 No Violations Noted Site inspection was conducted just after drilling. Site ID sign in place and E&S plan reviewed. Water level in drill pit meets minimum 2¿ freeboard. Site is relatively level but perimeter E&S BMP¿s in place and functioning adequately (silt fence). Access road is clean durable rock and no issues noted. *Site must be restored within 9 months of drill completion.