37-129-28844

Well Details

Well ID: 37-129-28844
Loading map...
Operator Name: WPX ENERGY APPALACHIA LLC
Well Pad ID: 145495
First Permit Date: 2013-05-02
Last Permit Date: 2013-05-02
Spud Date: 2013-05-07
Unconventional: Yes
Horizontal: No
Violations: None
Latitude: 40.363744
Longitude: -79.299688

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
2013-2 27296.59 9.0 0.0 0.0 0.0 0.0
2013-1 0.0 0.0 0.0 0.0 0.0 0.0

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE
2013-2 FRACING FLUID WASTE 213.33 Bbl STORAGE PENDING DISPOSAL OR REUSE HUNTER DISPOSAL - NEW MATAMORAS NEW MATAMORAS OH
2013-2 DRILL CUTTINGS 1548.45 Tons RESIDUAL WASTE TRANSFER FACILITY PAD004835146 MAX ENVIRONMENTAL TECHNOLOGIES INC YUKON FACILITY YUKON PA

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID
2167530 2013-05-17 Westmoreland Derry Twp No Violations Noted
2182343 2013-05-30 Westmoreland Derry Twp No Violations Noted
2182408 2013-06-06 Westmoreland Derry Twp No Violations Noted
2188043 2013-07-25 Westmoreland Derry Twp No Violations Noted
2195657 2013-08-12 Westmoreland Derry Twp No Violations Noted
2200901 2013-09-03 Westmoreland Derry Twp No Violations Noted
2211058 2013-09-23 Westmoreland Derry Twp No Violations Noted
2217768 2013-10-03 Westmoreland Derry Twp No Violations Noted
2219586 2013-10-16 Westmoreland Derry Twp No Violations Noted
2222844 2013-11-05 Westmoreland Derry Twp No Violations Noted
2237669 2014-01-16 No Violations Noted At the time of inspection the well appeared to drilled and stimulated. The Operator indicated that they are actively working to equip the well for production. The Erosion and Sedimentation Plan was onsite and appeared to implemented and maintained. No observation of accelerated erosion in relation to the well pad or access road. The Department suggests the Operator continue to monitor the site weekly and after significant precipitation event to ensure the stability of the site in maintained.