Well ID: 37-033-26819 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":41.161315,"lon":-78.465834,"icon":""}]} |
County: Clearfield | |
Municipality: Lawrence Township | |
Operator Name: EOG RESOURCES INC | |
Well Pad ID: 149110 | |
Farm/Lease Name: PUNXSUTAWNEY HUNTING CLUB 26H | |
First Permit Date: 2009-06-25 | |
Last Permit Date: 2009-06-25 | |
Spud Date: 2009-07-17 | |
Unconventional: Yes | |
Horizontal: Yes | |
Producing: Yes | |
Violations: None | |
Latitude: 41.161315 | |
Longitude: -78.465834 |
INSPECTION ID | DATE | DESCRIPTION | COMMENT | VIOLATION ID |
---|---|---|---|---|
1814837 | 2009-07-21 | No Violations Noted | The following items were noted during the inspection:
-Met with Mr. Dan Lindsey, EOG Consultant. -Drilling contractor, Coda Rathole drilling conductor hole. -Site sign and E & S plan were on site. -E&S BMPs were in place and working adequately. Site was muddy, but flat & contained. -Reserve pit met regulatory standards, 20 mil liner w/ padding. |
|
1822523 | 2009-08-13 | No Violations Noted | The following items were noted during the inspection:
-Drilling contractor, Dalls Morris Rig #8 drilled to 6,225¿. Breaking down rig and moving off location. -Site sign and E & S plan were on site. -E&S BMPs were in place and working adequately. -Reserve pits met regulatory standards. |
|
1822599 | 2009-08-13 | No Violations Noted | Site inspected with OGI Bruce Jankura. Well pad also contains well #5H, which currently does not have any activity associated with it. Well was spud for setting conductor pipe on July 20, 2009 and drilling of top hole that began on August 5, 2009 was completed by this inspection. Top hole drilling rig was in the final stages of being moved to well #4H. One tank containing approximately 34bbls of fresh water was being discharged in an appropriate manner on site. This discharge was not creating any erosional issues nor was it leaving the site. There were also two tanks of brine, amount unknown, on-site. They were being prepared to be hauled to off-site disposal. Pit was constructed with sound liner and more than 2ft of freeboard was being maintained. E&S controls were installed properly and being maintained. Exposed areas were seeded and mulched. About 50% vegetation has regrown in these areas. There are no E&S issues at this time | |
1833467 | 2009-09-30 | No Violations Noted | Site inspected with OGI Supervisor, Bruce Jankura. Met Pete Comeau, Drilling Consultant, on site. Drilling and casing is complete for PHC #5H and rig is setting idle until drilling begins on PHC #26H.
-pit has been backfilled and all earth disturbance that occurred during the backfilling was being limed, seeded and mulched at time of inspection -Rig scheduled to move onto 26H Thursday, October 1, 2009 and pitless drilling will be used -all E&S controls remain in place and working adequately -There are no issues on site at this time |
|
1834898 | 2009-09-30 | No Violations Noted | The following items were noted during the inspection:
-Drilling contractor, Precision #823, moving in and rigging up to drill.. -Old drill pits reclaimed and seeding in process. -met w/ Pete Comeau , Drilling Consultant, reviewed pitless drilling plan for site. -Site sign and E & S plan were on site. -E&S BMPs were in place and working adequately. |
|
1954510 | 2011-03-03 | No Violations Noted |
PERIOD | GAS QUANTITY | GAS PRODUCTION DAYS | CONDENSATE QUANTITY | CONDENSATE PRODUCTION DAYS | OIL QUANTITY | OIL PRODUCTION DAYS |
---|---|---|---|---|---|---|
2012-2 | 139179.0 | 172.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2012-1 | 191638.0 | 182.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2011-2 | 257364.0 | 184.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2011-1 | 421791.0 | 181.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2010-2 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2010-3 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2009-0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 |
PERIOD | TYPE | QUANTITY | UNITS | DISPOSAL METHOD | WASTE FACILITY PERMIT ID | WASTE FACILITY NAME | FACILITY CITY | FACILITY STATE |
---|---|---|---|---|---|---|---|---|
2012-2 | PRODUCED FLUID | 200.0 | Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | 525-1 | BLAZEK PUMP AND WELL | HIRAM | OH |
2012-2 | PRODUCED FLUID | 194.0 | Bbl | INJECTION DISPOSAL WELL | 34-155-21438 | KLEESE #1 (SWIW #18) - KLEESE DEVELOPMENT ASSOCS | VIENNA | OH |
2012-2 | PRODUCED FLUID | 385.0 | Bbl | INJECTION DISPOSAL WELL | 34-155-21447 | KLEESE #2 (SWIW #19) - KLEESE DEVELOPMENT ASSOCS | VIENNA | OH |
2012-2 | PRODUCED FLUID | 105.0 | Bbl | INJECTION DISPOSAL WELL | 34-155-23584 | KOONTZ #1 DISPOSAL WELL | WARREN | OH |
2012-2 | PRODUCED FLUID | 417.0 | Bbl | INJECTION DISPOSAL WELL | 34-155-23795 | PANDER #1 (SWIW #15) | NEWTON FALLS | OH |
2012-2 | PRODUCED FLUID | 95.0 | Bbl | INJECTION DISPOSAL WELL | 34-007-22038 | PAROBEK #2 (SWIW #12) | OH | |
2012-2 | PRODUCED FLUID | 455.0 | Bbl | REUSE OTHER THAN ROAD SPREADING | REUSE FOR HYDRAULIC FRACTURING | |||
2012-2 | PRODUCED FLUID | 538.0 | Bbl | INJECTION DISPOSAL WELL | 34-133-20114 | SALTY'S DISPOSAL - WILCOX #1 | ROOTSTOWN | OH |
2012-2 | PRODUCED FLUID | 105.0 | Bbl | INJECTION DISPOSAL WELL | 34-133-24096 | SALTYS DISPOSAL - GROSELLE INECTION WELL # 2 | GARRETTSVILLE | OH |
2012-2 | PRODUCED FLUID | 1103.0 | Bbl | STORAGE PENDING DISPOSAL OR REUSE | STORAGE PENDING DISPOSAL OR REUSE | PA | ||
2011-1 | PRODUCED FLUID | 105.0 | Bbl | INJECTION DISPOSAL WELL | 34-133-24096 | GROSELLE #2 - SALTYS DISPOSAL WELLS LP | GARRETTSVILLE | OH |
2011-1 | PRODUCED FLUID | 660.0 | Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | 34-099-23127 | NORTH STAR BRINE DISPOSAL | YOUNGSTOWN | OH |
2011-1 | PRODUCED FLUID | 6355.0 | Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0101508 | PA BRINE TRT INC - FRANKLIN PLT - VENANGO CO | FRANKLIN | PA |
2011-1 | PRODUCED FLUID | 10932.0 | Bbl | REUSE OTHER THAN ROAD SPREADING | REUSE OF BRINE TO FRAC A WELL | |||
2011-1 | PRODUCED FLUID | 441.0 | Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0023213 | RIDGWAY BOROUGH SEWAGE TREATMENT PLANT | RIDGWAY | PA |
2011-1 | PRODUCED FLUID | 380.0 | Bbl | CENTRALIZED TREATMENT PLANT FOR RECYCLE | PA0027057 | WILLIAMSPORT SAN AUTH - CENTRAL STP | WILLIAMSPORT | PA |
2011-2 | PRODUCED FLUID | 2894.0 | Bbl | INJECTION DISPOSAL WELL | 34-133-24096 | GROSELLE #2 - SALTYS DISPOSAL WELLS LP | GARRETTSVILLE | OH |
2011-2 | PRODUCED FLUID | 4956.0 | Bbl | INJECTION DISPOSAL WELL | 34-049-23127 | NORTH STAR | YOUNGSTOWN | OH |
2011-2 | PRODUCED FLUID | 2405.0 | Bbl | REUSE OTHER THAN ROAD SPREADING | REUSE OF BRINE TO FRAC A WELL | |||
2012-1 | PRODUCED FLUID | 201.0 | Bbl | INJECTION DISPOSAL WELL | 34-099-23127 | NORTH STAR BRINE DISPOSAL | YOUNGSTOWN | OH |
2012-1 | PRODUCED FLUID | 1145.0 | Bbl | INJECTION DISPOSAL WELL | 34-155-23795 | PANDER #1 (SWIW #15) | NEWTON FALLS | OH |
2012-1 | PRODUCED FLUID | 4274.0 | Bbl | REUSE OTHER THAN ROAD SPREADING | REUSE FOR HYDRAULIC FRACTURING |