X

Track changes made to this page

If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.



Privacy policy
Close this window

powered by ChangeDetection

Difference between revisions of "34-059-24067"

m
 
m
Line 3: Line 3:
 
{| class="wikitable welldetails" width="95%"
 
{| class="wikitable welldetails" width="95%"
 
| Well ID: 34-059-24067
 
| Well ID: 34-059-24067
| style="height=100%; align=center" rowspan="15" | {{#display_map: 39.9413567701, -81.6736407761 | width=100% | height=100% }}
+
| style="height=100%; align=center" rowspan="15" | {{#display_map: 39.94127763, -81.67398116 | width=100% | height=100% }}  
 
|-
 
|-
| County:
+
| County: [[Guernsey County, Ohio|Guernsey]]
 
|-
 
|-
| Municipality:
+
| Municipality:  
 
|-
 
|-
| Operator Name:
+
| Operator Name: [[HILL DAVID R INC]]
 
|-
 
|-
| Well Pad ID:
+
| Well Pad ID:  
 
|-
 
|-
| Farm/Lease Name:
+
| Farm/Lease Name:  
 
|-
 
|-
| First Permit Date:
+
| First Permit Date:  
 
|-
 
|-
| Last Permit Date:
+
| Last Permit Date:  
 
|-
 
|-
 
| Spud Date: 2008-02-26
 
| Spud Date: 2008-02-26
 
|-
 
|-
| Unconventional:
+
| Unconventional: No
 
|-
 
|-
| Horizontal:
+
| Configuration: Vertical
 
|-
 
|-
| Producing: No
+
| Well Status: Active Injection
 
|-
 
|-
 
| Violations: 0
 
| Violations: 0
 
|-
 
|-
| Latitude: 39.9413567701
+
| Latitude: 39.94127763
 
|-
 
|-
| Longitude: -81.6736407761
+
| Longitude: -81.67398116
 
|-
 
|-
|}
 
== Production Data ==
 
{| class="wikitable sortable" width="95%"
 
!scope="col" | PERIOD
 
!scope="col" | GAS QUANTITY
 
!scope="col" | GAS PRODUCTION DAYS
 
!scope="col" | CONDENSATE QUANTITY
 
!scope="col" | CONDENSATE PRODUCTION DAYS
 
!scope="col" | OIL QUANTITY
 
!scope="col" | OIL PRODUCTION DAYS
 
|}
 
== Waste Data ==
 
{| class="wikitable sortable" width="95%"
 
!scope="col" | PERIOD
 
!scope="col" | TYPE
 
!scope="col" | QUANTITY
 
!scope="col" | UNITS
 
!scope="col" | DISPOSAL METHOD
 
!scope="col" | WASTE FACILITY PERMIT ID
 
!scope="col" | WASTE FACILITY NAME
 
!scope="col" | FACILITY CITY
 
!scope="col" | FACILITY STATE
 
 
|}
 
|}
 
== Inspection Data ==
 
== Inspection Data ==
Line 64: Line 42:
 
!scope="col" | VIOLATION ID
 
!scope="col" | VIOLATION ID
 
!scope="col" | VIOLATION CODE
 
!scope="col" | VIOLATION CODE
!scope="col" | VIOLATION_COMMENT
+
!scope="col" | VIOLATION COMMENT
 
|-
 
|-
 
| -1028964582
 
| -1028964582
 
| 2012-11-09
 
| 2012-11-09
|
+
|  
 
| Inspection revealed that Sweeny Well Service on site to apply pressure to annulus of tubing, they applied 425 psi and we monitored pressure for 15 minutes with no decline in pressure TEST PASSED, injection pump was not in operation during my inspection.
 
| Inspection revealed that Sweeny Well Service on site to apply pressure to annulus of tubing, they applied 425 psi and we monitored pressure for 15 minutes with no decline in pressure TEST PASSED, injection pump was not in operation during my inspection.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| 1031046280
 +
| 2014-03-07
 +
|
 +
| Inspection revealed that injection pump was in operation and it was noted that three Buckeye Water Service vacuum trucks were unloading at facility during my inspection.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| -1047151489
 
| -1047151489
 
| 2008-04-22
 
| 2008-04-22
|
+
|  
 
| CHIPCO DRILLING OUT DV TOOLS IN BOTTOM HOLE 7138'
 
| CHIPCO DRILLING OUT DV TOOLS IN BOTTOM HOLE 7138'
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| 1048507788
 +
| 2008-08-07
 +
|
 +
| SWIW STARTING TO CONSTRUCT DIKE WALLS. PILING UP AND COMPACTING DIRT AS CONTRACTOR GOES UP WITH DIKE WALL.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| -1090017095
 
| -1090017095
 
| 2010-06-25
 
| 2010-06-25
|
+
|  
 
| Inspection revealed that injection pump not in operation today due to fact of Sweeny Well Service performing mini test on annulus of tubing 350psi was applied to annulus and pressure monitored for 15 min with no decline in pressure.
 
| Inspection revealed that injection pump not in operation today due to fact of Sweeny Well Service performing mini test on annulus of tubing 350psi was applied to annulus and pressure monitored for 15 min with no decline in pressure.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| -1106162492
 
| -1106162492
 
| 2008-03-06
 
| 2008-03-06
|
+
|  
 
| KILBARGER DRILLING RIG#17 DRILLING BOTTOM RR 7683. NOTHING DRILLING AHEAD.
 
| KILBARGER DRILLING RIG#17 DRILLING BOTTOM RR 7683. NOTHING DRILLING AHEAD.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| -1108372922
 
| -1108372922
 
| 2013-04-08
 
| 2013-04-08
|
+
|  
 
| Inspection revealed that injection pump was not in operation during my inspection and I walked flow line area to monitor area for leaks, none were found.
 
| Inspection revealed that injection pump was not in operation during my inspection and I walked flow line area to monitor area for leaks, none were found.
|
+
|  
|
+
|  
|
+
|  
|-
 
|-
 
| -1173282118
 
| 2009-01-30
 
|
 
| WELL IN OPERATION TODAY. WELL IS STILL ON VACUUM. LARGE AMOUNT OF PIT WATER INJECTED DOWN HOLE FOR THE LAST SEVERAL WEEKS AND INJECTION PRESSURE WENT TO 1000#. AFTER PIT WATER WAS INJECTED DOWN, PRESSURE DROPPED OFF TO 640# AND WENT ON VACUUM AGAIN.
 
|
 
|
 
|
 
|-
 
|-
 
| -1227475767
 
| 2014-01-17
 
|
 
| Inspection revealed that injection pump was in operation today and it was noted that one Buckeye  Water Service vacuum truck was unloading at facility during my inspection.
 
|
 
|
 
|
 
|-
 
|-
 
| -1478919296
 
| 2009-02-24
 
|
 
| SWIW INSPECTED. UNLOADING PAD AND FACILITY IN GOOD REPAIR. NO VIOLATIONS NOTED.
 
|
 
|
 
|
 
|-
 
|-
 
| -1491684624
 
| 2010-03-01
 
|
 
| On site to witness mini test on annulas of tubing Sweeny Well Service pressured up to 360 psi and we monitored pressure for 15 min with no decline in pressure(TEST PASSED) and injection pump was in operation during my inspection.
 
Note: 390,595 bbl of water has been injected since well went into operation.
 
|
 
|
 
|
 
|-
 
|-
 
| -1493195847
 
| 2010-11-24
 
|
 
| Inspection revealed that well was not in operation during my inspection,well operator was in process of changing filters in pumphouse and was planning on placing well into operation after mainitence work was completed.
 
Note: 613,574 bbl disposed of since well went into service.
 
|
 
|
 
|
 
|-
 
|-
 
| -150070169
 
| 2008-08-19
 
|
 
| SWIW TOP SOIL BEING SPREAD ON BOTTOM OF LINER ON OUTSIDE OF DIKE AREA. PLUMBING STILL BEING HOOKED UP TO OVERFLOW VAULT ON OUTSIDE OF UNLOADING PAD.
 
|
 
|
 
|
 
|-
 
|-
 
| -155224430
 
| 2008-08-18
 
|
 
| SETTING IN 2400 GAL CEMENT VAULT FOR PAD DRAIN. PLUMB IN VAULT.
 
|
 
|
 
|
 
|-
 
|-
 
| -1559212810
 
| 2010-01-20
 
|
 
| Inspection revealed that injection pump was in operation during my inspection.
 
Note: Dow Cameron vac truck unloading at site during my inspection,370,656 bbl water put away since well went into operation.
 
|
 
|
 
|
 
|-
 
|-
 
| -1559431971
 
| 2012-02-02
 
|
 
| On site to witness Baker Oil Tool employee unhook tubing from packer and pull tubing trying to find hole in it we located hole and decision was made to get new string of tubing and run it back in hole tomorrow.
 
|
 
|
 
|
 
|-
 
|-
 
| -1560256822
 
| 2008-05-05
 
|
 
| APPALACHIAN WELL SURVEY'S RUN CEMENT BOND LOG ON HOLE.
 
|
 
|
 
|
 
|-
 
|-
 
| -1683725546
 
| 2012-02-04
 
|
 
| On site to witness Chipco Well Services run tubing back into well and latch onto packer and perform pretesting of annulus we pressured up to 1800 psi and monitored pressure for 15 min. with no decline, will perform official test on Monday with Producers Services pump truck.
 
|
 
|
 
|
 
|-
 
|-
 
| -1690178081
 
| 2014-07-15
 
|
 
| Inspection revealed that injection pump was in operation today and it was noted that one Buckeye Water Service vacuum truck was unloading at facility during my inspection.
 
|
 
|
 
|
 
|-
 
|-
 
| -1748823651
 
| 2008-08-12
 
|
 
| LAYING IN OF 2-20 MIL LINERS ON INSIDE OF DIKE.
 
|
 
|
 
|
 
|-
 
|-
 
| -1849592333
 
| 2009-04-29
 
|
 
| Restoration work at site satisfactory,pit has been filled in and site restored and vegetation has been established site is currently being used for a active Salt Water Injection Facility.
 
|
 
|
 
|
 
|-
 
|-
 
| -197109858
 
| 2012-08-21
 
|
 
| On site with UIC Director and group from Central Office to inspect well site and surface facility and discuss any issues with well operator concerning facility.
 
|
 
|
 
|
 
|-
 
|-
 
| -1999546532
 
| 2008-04-28
 
|
 
| CHIPCO DRILLING OUT FORMATION PACKER
 
|
 
|
 
|
 
|-
 
|-
 
| -200516364
 
| 2012-04-25
 
|
 
| Inspection revealed that well was in operation on this day, well caretaker was changing filters during my inspection and it was noted that Buckeye Water Services was unloading tanker truck at site.
 
|
 
|
 
|
 
|-
 
|-
 
| -2039009496
 
| 2011-09-07
 
|
 
| Inspection revealed that injection pump was in operation during my inspection and there was three vacuum trucks unloading at facility also, walked flow line area to monitor for potential leaks(none found) facility was in good repair this inspection.
 
Note: 941,746 bbl of water has been disposed of since well went into operation.
 
|
 
|
 
|
 
|-
 
|-
 
| -2068245965
 
| 2008-04-17
 
|
 
| DRILLED TO 8500' FOR PURPOSE OF INJECTION WELL. DRILLING OUT DV TOOLS IN 5.5"
 
|
 
|
 
|
 
|-
 
|-
 
| -2076879871
 
| 2008-10-02
 
|
 
| SALT WATER INJECTION WELL
 
|
 
|
 
|
 
|-
 
|-
 
| -2090380607
 
| 2008-11-03
 
|
 
| WELL IS IN OPERATION. NO VIOLATIONS NOTED.
 
|
 
|
 
|
 
|-
 
|-
 
| -223578216
 
| 2013-01-17
 
|
 
| On site with company personnel Don Krieger and John Suhar to review injection well monitoring charts to try and determine if there is a possibility of leakage in tubing or packer after reviewing data it was determined that annulus pressure increase was due to thermal expansion to down hole fluid when well is not in operation.
 
|
 
|
 
|
 
|-
 
|-
 
| -225951818
 
| 2008-04-21
 
|
 
| CHIPCO DRILLING OUT DV TOOL. WILL HAVE TO TRIP FOR BIT. JOHN SUHAR WILL TAKE PERMIT APPLICATION TO COLUMBUS TODAY.
 
|
 
|
 
|
 
|-
 
|-
 
| -284590190
 
| 2014-06-03
 
|
 
| Inspection revealed that injection pump was in operation today and it was noted that one H&L Water Service vacuum truck was unloading at this facility on the day of my inspection.
 
|
 
|
 
|
 
|-
 
|-
 
| -341072783
 
| 2014-04-15
 
|
 
| Inspection revealed that injection pump was in operation during my inspection and it was noted that two H&L Water vacuum trucks were unloading at facility during my inspection.
 
|
 
|
 
|
 
|-
 
|-
 
| -364566513
 
| 2012-04-17
 
|
 
| Inspection revealed that injection pump was not in operation during my inspection and facility appeared to be in satisfactory condition this inspection.
 
Note: 1,218,997 bbl of brine disposed of since well went into operation.
 
|
 
|
 
|
 
|-
 
|-
 
| -538164671
 
| 2013-06-27
 
|
 
| Inspection revealed that injection pump was in operation today and it was noted that two Buckeye Water Services vacuum trucks were unloading at site during my inspection.
 
|
 
|
 
|
 
|-
 
|-
 
| -577842201
 
| 2008-03-10
 
|
 
| KILBARGER DRILLING#17. DRILLING ON MUD. LOST CIRCULATION 2 TIMES IN 24 HRS. DRILLING AT 8157'
 
|
 
|
 
|
 
|-
 
|-
 
| -593575519
 
| 2012-09-24
 
|
 
| BOS Fluids system on site to clean out storage tanks at facility will monitor progress on getting tanks cleaned and wells back into operation.
 
|
 
|
 
|
 
|-
 
|-
 
| -645681029
 
| 2014-04-01
 
|
 
| Inspection revealed that injection pump was in operation today and it was noted that one Buckeye Water Service vacuum truck was unloading at facility during  my inspection.
 
|
 
|
 
|
 
|-
 
|-
 
| -683119350
 
| 2009-11-16
 
|
 
| Inspection revealed that injection pump ws not in operation during my inspection,noted that seed and mulch has been applied to area around wellhead to help bind soil and prevent erosion issues at site.
 
|
 
|
 
|
 
|-
 
|-
 
| -721787425
 
| 2011-08-09
 
|
 
| Inspection revealed that pump was in operation during my inspection and there was two vac trucks unloading at site during my inspection.
 
Noted that dirt has been put in place around vault area and seed and mulch has been applied to area.
 
|
 
|
 
|
 
|-
 
|-
 
| -738690761
 
| 2011-11-22
 
|
 
| Inspection revealed that pump was in operation and there ws several vaccum trucks waiting to unload at facility.  Note: 1,063,645 bbl of water has been disposed of since well went into operation.
 
|
 
|
 
|
 
|-
 
|-
 
| -804412253
 
| 2012-12-06
 
|
 
| Restoration work at site satisfactory pit has been filled and site has vegetation established.
 
|
 
|
 
|
 
|-
 
|-
 
| -819557891
 
| 2010-05-25
 
|
 
| On site to witness mini test on annulus of tubing,Swenny Well Service pressured up to 350 psi and well monitored pressure for 15 min. with no decline in pressure, injection pump was not in operation during my inspection.
 
|
 
|
 
|
 
|-
 
|-
 
| -822745846
 
| 2010-09-09
 
|
 
| Inspection revealed that injection pump was in operation during my inspection.
 
Note: 567574 bbl of water disposed of since well went into operation.
 
|
 
|
 
|
 
|-
 
|-
 
| 1031046280
 
| 2014-03-07
 
|
 
| Inspection revealed that injection pump was in operation and it was noted that three Buckeye Water Service vacuum trucks were unloading at facility during my inspection.
 
|
 
|
 
|
 
|-
 
|-
 
| 1048507788
 
| 2008-08-07
 
|
 
| SWIW STARTING TO CONSTRUCT DIKE WALLS. PILING UP AND COMPACTING DIRT AS CONTRACTOR GOES UP WITH DIKE WALL.
 
|
 
|
 
|
 
 
|-
 
|-
 
|-
 
|-
 
| 1130921095
 
| 1130921095
 
| 2014-04-01
 
| 2014-04-01
|
+
|  
 
| I am accompanying inspector Dave Ball.  My inspection finds the well is operating at a tubing pressure of 1300 psi and an annular pressure of 375 psi.
 
| I am accompanying inspector Dave Ball.  My inspection finds the well is operating at a tubing pressure of 1300 psi and an annular pressure of 375 psi.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1163408779
 
| 1163408779
 
| 2012-09-26
 
| 2012-09-26
|
+
|  
 
| On site to witness cleaning of storage tanks by BOS Fluid Systems and Zemba Brothers had super sucker truck on site to remove solids from storage tanks.
 
| On site to witness cleaning of storage tanks by BOS Fluid Systems and Zemba Brothers had super sucker truck on site to remove solids from storage tanks.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -1173282118
 +
| 2009-01-30
 +
|
 +
| WELL IN OPERATION TODAY. WELL IS STILL ON VACUUM. LARGE AMOUNT OF PIT WATER INJECTED DOWN HOLE FOR THE LAST SEVERAL WEEKS AND INJECTION PRESSURE WENT TO 1000#. AFTER PIT WATER WAS INJECTED DOWN, PRESSURE DROPPED OFF TO 640# AND WENT ON VACUUM AGAIN.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 1192305701
 
| 1192305701
 
| 2013-03-27
 
| 2013-03-27
|
+
|  
 
| Inspection revealed that injection pump was not in operation during my inspection and it was noted that three Buckeye Water Services vacuum trucks were unloading at facility during my inspection.
 
| Inspection revealed that injection pump was not in operation during my inspection and it was noted that three Buckeye Water Services vacuum trucks were unloading at facility during my inspection.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1204047975
 
| 1204047975
 
| 2008-02-26
 
| 2008-02-26
|
+
|  
 
| KILBARGER RIG#17. MOVING ON RIGGING UP.
 
| KILBARGER RIG#17. MOVING ON RIGGING UP.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1204149418
 
| 1204149418
 
| 2008-02-27
 
| 2008-02-27
|
+
|  
 
| KILBARGER RIG#17. DRILLING AT 500'
 
| KILBARGER RIG#17. DRILLING AT 500'
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1204296794
 
| 1204296794
 
| 2008-02-29
 
| 2008-02-29
|
+
|  
 
| KILBARGER DRILLING RIG #17. DRILLING AT 2117'. SHALE
 
| KILBARGER DRILLING RIG #17. DRILLING AT 2117'. SHALE
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1204646406
 
| 1204646406
 
| 2008-03-03
 
| 2008-03-03
|
+
|  
 
| KILBARGER DRILLING #17. DRILLING AT 5252'
 
| KILBARGER DRILLING #17. DRILLING AT 5252'
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1204753145
 
| 1204753145
 
| 2008-03-05
 
| 2008-03-05
|
+
|  
 
| KILBARGER DRILLING #17. DRILLING AT 7057'. SHOULD DRILL IN LATER ON TONOTE.
 
| KILBARGER DRILLING #17. DRILLING AT 7057'. SHOULD DRILL IN LATER ON TONOTE.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1204754321
 
| 1204754321
 
| 2008-03-04
 
| 2008-03-04
|
+
|  
 
| KILBARGER DRILLING#17, DRILING AT 6133'
 
| KILBARGER DRILLING#17, DRILING AT 6133'
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1204831407
 
| 1204831407
 
| 2008-03-05
 
| 2008-03-05
|
+
|  
 
| KILBARGER DRILLING. DRILL IN BEEKMANTOWN 7326' 236U NO FLARE. DRILLING AHEAD
 
| KILBARGER DRILLING. DRILL IN BEEKMANTOWN 7326' 236U NO FLARE. DRILLING AHEAD
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1205930001
 
| 1205930001
 
| 2008-03-17
 
| 2008-03-17
|
+
|  
 
| KILBARGER DRILLING#17,SCHLUMBERGER SIDEWALL CORES BEING CUT. TD WELL AT 8934'
 
| KILBARGER DRILLING#17,SCHLUMBERGER SIDEWALL CORES BEING CUT. TD WELL AT 8934'
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1209676502
 
| 1209676502
 
| 2008-05-01
 
| 2008-05-01
|
+
|  
 
| CHIPCO RIG ON HOLE. GOT TO BOTTOM 8900' CIRCULATING HOLE TO SURFACE. TO SPOT ACID TOMORROW.
 
| CHIPCO RIG ON HOLE. GOT TO BOTTOM 8900' CIRCULATING HOLE TO SURFACE. TO SPOT ACID TOMORROW.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1209989261
 
| 1209989261
 
| 2008-05-02
 
| 2008-05-02
|
+
|  
 
| PSC SPOT 2000 GAL. ACID ACROSS LOWER ZONES. WELL WENT ON VACUUM IMMEDIATELY
 
| PSC SPOT 2000 GAL. ACID ACROSS LOWER ZONES. WELL WENT ON VACUUM IMMEDIATELY
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1215329563
 
| 1215329563
 
| 2013-03-01
 
| 2013-03-01
|
+
|  
 
| Inspection revealed that injection pump was not in operation today, and it was noted that tank area was free of water and unloading pad was fairly clean and neat.
 
| Inspection revealed that injection pump was not in operation today, and it was noted that tank area was free of water and unloading pad was fairly clean and neat.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1217518288
 
| 1217518288
 
| 2008-07-31
 
| 2008-07-31
|
+
|  
 
| SWIW CONSTRUCTION HAS STARTED. ESI IS THE CONTRACTOR DOING THE WORK. LEVELING GROUD OUT FOR DIKE AREA AND COMPACTING SOIL AS LEVELING PROCESS IS TAKING PLACE. JEFF KRAEGER IS CONTACT PERSON.
 
| SWIW CONSTRUCTION HAS STARTED. ESI IS THE CONTRACTOR DOING THE WORK. LEVELING GROUD OUT FOR DIKE AREA AND COMPACTING SOIL AS LEVELING PROCESS IS TAKING PLACE. JEFF KRAEGER IS CONTACT PERSON.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1217965392
 
| 1217965392
 
| 2008-08-05
 
| 2008-08-05
|
+
|  
| CONSTRUCTION CONTINUES ON DIKE AREA OF SWIW. LINER LAID DOWN. 8" SCEENINGS LAID OUT ON LINER. 500T OF #2 STONE BEING SPREAD ON TOP OF SCREENINGS. WORK TO CONTINUE EVERY DAY ON THIS PROJECR UNTIL COMPLETED.
+
| CONSTRUCTION CONTINUES ON DIKE AREA OF SWIW. LINER LAID DOWN. 8 SCEENINGS LAID OUT ON LINER. 500T OF #2 STONE BEING SPREAD ON TOP OF SCREENINGS. WORK TO CONTINUE EVERY DAY ON THIS PROJECR UNTIL COMPLETED.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1218549132
 
| 1218549132
 
| 2008-08-11
 
| 2008-08-11
|
+
|  
| SWIW CONSTRUCTION. BLOWING 7" SAND ON INSIDE OF DIKE WITH SAND SLINGER. DISCUSSED WITH JEFF KRAEGETHE LAYING IN OF THE LINERS. 2-20 MIL.
+
| SWIW CONSTRUCTION. BLOWING 7 SAND ON INSIDE OF DIKE WITH SAND SLINGER. DISCUSSED WITH JEFF KRAEGETHE LAYING IN OF THE LINERS. 2-20 MIL.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1219991800
 
| 1219991800
 
| 2009-11-30
 
| 2009-11-30
|
+
|  
 
| On site to witness testing of annulas of casing,Sweeny Well Service pressured up to 350 psi and monitored pressure no decline in pressure,noted that pump was in operation during my inspection.
 
| On site to witness testing of annulas of casing,Sweeny Well Service pressured up to 350 psi and monitored pressure no decline in pressure,noted that pump was in operation during my inspection.
 
Note: 344,611 bbl of water disposed of as of this date.
 
Note: 344,611 bbl of water disposed of as of this date.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1223312286
 
| 1223312286
 
| 2008-10-06
 
| 2008-10-06
|
+
|  
 
| STILL WORKING ON FACILITY. LOADING WATER INTO TANKS. WORKING ON PUMP AND FILTER SYSTEM.
 
| STILL WORKING ON FACILITY. LOADING WATER INTO TANKS. WORKING ON PUMP AND FILTER SYSTEM.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1223400995
 
| 1223400995
 
| 2008-10-07
 
| 2008-10-07
|
+
|  
 
| LOADING WATER INTO TANKS. WORKING ON DIRT OUTSIDE DIKE AREA. WORKING ON PUMP,FILTER SYSTEM.
 
| LOADING WATER INTO TANKS. WORKING ON DIRT OUTSIDE DIKE AREA. WORKING ON PUMP,FILTER SYSTEM.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1223565811
 
| 1223565811
 
| 2008-10-09
 
| 2008-10-09
|
+
|  
 
| WELL IS UP AND RUNNING. 1658 BBLS. PUT AWAY SO FAR.
 
| WELL IS UP AND RUNNING. 1658 BBLS. PUT AWAY SO FAR.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1224160681
 
| 1224160681
 
| 2008-10-15
 
| 2008-10-15
|
+
|  
 
| WELL IS STILLIN OPERATION. INJECTION PRESSURE TODAY WAS 285#. 3 TRUCKS ON UNLOADING PAD. WELL IS GETTING A LOT OF WATER IN. 5387 BBL. OF WATER HAS BEEN PUT AWAY SO FAR.
 
| WELL IS STILLIN OPERATION. INJECTION PRESSURE TODAY WAS 285#. 3 TRUCKS ON UNLOADING PAD. WELL IS GETTING A LOT OF WATER IN. 5387 BBL. OF WATER HAS BEEN PUT AWAY SO FAR.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1225122800
 
| 1225122800
 
| 2008-10-27
 
| 2008-10-27
|
+
|  
 
| WELL IS IN OPERATION. 10,000 BBL. SO FAR TO DATE
 
| WELL IS IN OPERATION. 10,000 BBL. SO FAR TO DATE
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1226685814
 
| 1226685814
 
| 2008-11-14
 
| 2008-11-14
|
+
|  
 
| WELL MIS UP AND RUNNING. JOHN GOMBEDA AND DONALD KREIGER ON LOCATION TO DISCUSS X-TRA STORAGE TANKS COMPANY IS PLANNING TO INSTALL AT FACILITY. NO VIOLATIONS NOTED THIS INSPECTION. 20981 BBLS. PUT AWAY SO FAR.
 
| WELL MIS UP AND RUNNING. JOHN GOMBEDA AND DONALD KREIGER ON LOCATION TO DISCUSS X-TRA STORAGE TANKS COMPANY IS PLANNING TO INSTALL AT FACILITY. NO VIOLATIONS NOTED THIS INSPECTION. 20981 BBLS. PUT AWAY SO FAR.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -1227475767
 +
| 2014-01-17
 +
|
 +
| Inspection revealed that injection pump was in operation today and it was noted that one Buckeye  Water Service vacuum truck was unloading at facility during my inspection.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 1227530733
 
| 1227530733
 
| 2008-09-22
 
| 2008-09-22
|
+
|  
 
| FILLING TANKS WITH BRINE TO TEST FOR LEAKS.
 
| FILLING TANKS WITH BRINE TO TEST FOR LEAKS.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1230731256
 
| 1230731256
 
| 2008-12-31
 
| 2008-12-31
|
+
|  
 
| 51000 BBLS. WATER INJECTED DOWN SO FAR. NO VIOLATIONS NOTED THIS INSPECTION.
 
| 51000 BBLS. WATER INJECTED DOWN SO FAR. NO VIOLATIONS NOTED THIS INSPECTION.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1231526299
 
| 1231526299
 
| 2009-01-09
 
| 2009-01-09
|
+
|  
 
| WELL IS IN OPERATION. GAUGING TANKS FOR FILL UP FROM PIT WATER. PLAN TO CLEAN OUT TANKS. 57071 BBLS. WATER PUT DOWN HOLE.
 
| WELL IS IN OPERATION. GAUGING TANKS FOR FILL UP FROM PIT WATER. PLAN TO CLEAN OUT TANKS. 57071 BBLS. WATER PUT DOWN HOLE.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1237191881
 
| 1237191881
 
| 2011-05-27
 
| 2011-05-27
|
+
|  
 
| Inspection revealed that well is in operation and Sweeny Well Service was on site to perform mini test on annulus of tubing today they pressured up to 300 psi and we monitored pressure for 15 min with no decline in pressure.
 
| Inspection revealed that well is in operation and Sweeny Well Service was on site to perform mini test on annulus of tubing today they pressured up to 300 psi and we monitored pressure for 15 min with no decline in pressure.
 
Note: 788,900 bbl of water disposed of since well went into operation.
 
Note: 788,900 bbl of water disposed of since well went into operation.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1249080080
 
| 1249080080
 
| 2009-07-31
 
| 2009-07-31
|
+
|  
 
| On site to witness mini test of annulus of tubing, Sweeny Well Services  pressured up to 300 psi on annulus and I monitored pressure for 15 min with no decline in pressure(TEST PASSED),injection pump was not in operation during testing procedure.
 
| On site to witness mini test of annulus of tubing, Sweeny Well Services  pressured up to 300 psi on annulus and I monitored pressure for 15 min with no decline in pressure(TEST PASSED),injection pump was not in operation during testing procedure.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1252150772
 
| 1252150772
 
| 2009-09-04
 
| 2009-09-04
|
+
|  
 
| On site to witness mini test on annulus of tubing Sweeny Well Service pressured up to 350 psi and we monitored pressure for 15 min with no decline in pressure(TEST PASSED) injection pump was not in operation during my inspection.
 
| On site to witness mini test on annulus of tubing Sweeny Well Service pressured up to 350 psi and we monitored pressure for 15 min with no decline in pressure(TEST PASSED) injection pump was not in operation during my inspection.
 
Note: Better vegetation needs to be established in area of wellhead.
 
Note: Better vegetation needs to be established in area of wellhead.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1253308247
 
| 1253308247
 
| 2009-09-18
 
| 2009-09-18
|
+
|  
 
| Inspection revealed that well is in operation, pump was running on the day of my inspection.
 
| Inspection revealed that well is in operation, pump was running on the day of my inspection.
 
Talked to well tender about getting vegetation established in area of wellhead and he stated that he would contact supervisor and let them be aware of inspectors concerns.
 
Talked to well tender about getting vegetation established in area of wellhead and he stated that he would contact supervisor and let them be aware of inspectors concerns.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1255186234
 
| 1255186234
 
| 2009-10-10
 
| 2009-10-10
|
+
|  
 
| On site to witness rig crew release packer and pull tubing,unable to do so today due to fact that well is flowing back,owner will attempt swapping out tubing tomorrow if well quits flowing.
 
| On site to witness rig crew release packer and pull tubing,unable to do so today due to fact that well is flowing back,owner will attempt swapping out tubing tomorrow if well quits flowing.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1255511206
 
| 1255511206
 
| 2009-10-13
 
| 2009-10-13
|
+
|  
 
| On site to witness Berry Well Service run new packer assembly and new 2.875 tubing back into well and set packer@7151' and flush annulus of tubing with fresh water and anhibitor  and pressure test,tested at 1700 psi for 15 min with no decline in pressure(TEST PASSED),will check back at later date for compliance of restoration work in area of working pit.
 
| On site to witness Berry Well Service run new packer assembly and new 2.875 tubing back into well and set packer@7151' and flush annulus of tubing with fresh water and anhibitor  and pressure test,tested at 1700 psi for 15 min with no decline in pressure(TEST PASSED),will check back at later date for compliance of restoration work in area of working pit.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1257285422
 
| 1257285422
 
| 2009-11-03
 
| 2009-11-03
|
+
|  
 
| Inspection revealed that well is in operation,pump was running during my inspection.
 
| Inspection revealed that well is in operation,pump was running during my inspection.
 
Note:Area where recent compleation worktook place has been graded and seed and mulch applied waiting on vegatation to be established.  385,485 bbl disposed of since well went into operation.
 
Note:Area where recent compleation worktook place has been graded and seed and mulch applied waiting on vegatation to be established.  385,485 bbl disposed of since well went into operation.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1262205710
 
| 1262205710
 
| 2009-12-30
 
| 2009-12-30
|
+
|  
 
| On site to witness operator apply pressure to annulas of tubing,Sweeny Well Service applied 360 psi. monitored pressure for 15 min with no decline in pressure(TEST PASSED).
 
| On site to witness operator apply pressure to annulas of tubing,Sweeny Well Service applied 360 psi. monitored pressure for 15 min with no decline in pressure(TEST PASSED).
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1264878580
 
| 1264878580
 
| 2010-01-29
 
| 2010-01-29
|
+
|  
 
| On site to witness mini test on annulas of tubing Sweeny Well Service pressured up to 350 psi and I monitored pressure for 15 min with no decline in pressure.Test Passed
 
| On site to witness mini test on annulas of tubing Sweeny Well Service pressured up to 350 psi and I monitored pressure for 15 min with no decline in pressure.Test Passed
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1268494420
 
| 1268494420
 
| 2010-03-13
 
| 2010-03-13
|
+
|  
 
| Inspection revealed Producers Services preformed acid treatment  on well they pumped 2000 gal of acid into injection zone@1.3 bbl per min and displaced it with 50 bbl fresh water and then well was shut in too let acid soak on injection zone,owner will resume operation on 3/15/10.
 
| Inspection revealed Producers Services preformed acid treatment  on well they pumped 2000 gal of acid into injection zone@1.3 bbl per min and displaced it with 50 bbl fresh water and then well was shut in too let acid soak on injection zone,owner will resume operation on 3/15/10.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1273011323
 
| 1273011323
 
| 2010-05-03
 
| 2010-05-03
|
+
|  
 
| Inspection revealed that restoration work at site is satisfactory pit has been filled in and site restored and vegetation has been established.
 
| Inspection revealed that restoration work at site is satisfactory pit has been filled in and site restored and vegetation has been established.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1276720394
 
| 1276720394
 
| 2010-06-15
 
| 2010-06-15
|
+
|  
 
| Inspection revealed that injection pump was not in operation during my inspection.
 
| Inspection revealed that injection pump was not in operation during my inspection.
 
Note 492,274 bbl of water has been put away since well went into operation.
 
Note 492,274 bbl of water has been put away since well went into operation.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -127854275
 +
| 2015-02-11
 +
|
 +
| Inspection revealed that injection pump was in operation today and it was noted  that Buckeye Water Services had one truck on the unloading pad during my inspection.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 1280607690
 
| 1280607690
 
| 2010-07-29
 
| 2010-07-29
|
+
|  
 
| Inspection revealed that well was not in operation during my inspection, on site to witness mini test preformed on annulus of tubing Sweeny Well Service pressured up on backside of tubing too 350 psi and we monitored pressure for 15 min with no decline in pressure(TEST PASSED).
 
| Inspection revealed that well was not in operation during my inspection, on site to witness mini test preformed on annulus of tubing Sweeny Well Service pressured up on backside of tubing too 350 psi and we monitored pressure for 15 min with no decline in pressure(TEST PASSED).
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1283213220
 
| 1283213220
 
| 2010-08-30
 
| 2010-08-30
|
+
|  
 
| On site to witness mini test on annulus of tubing Sweeny Well Service pressured up to 350 psi and we monitored pressure for 15 min with no decline in pressure.
 
| On site to witness mini test on annulus of tubing Sweeny Well Service pressured up to 350 psi and we monitored pressure for 15 min with no decline in pressure.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1285699907
 
| 1285699907
 
| 2010-09-28
 
| 2010-09-28
|
+
|  
 
| On site to witness mini test preformed on annulus of tubing Sweeny Well Service pressured up to 380 psi and we monitored pressure for 15 min with no decline in pressure(TEST PASSED),injection pump was shut down prior too testing and resumed operation following testing.
 
| On site to witness mini test preformed on annulus of tubing Sweeny Well Service pressured up to 380 psi and we monitored pressure for 15 min with no decline in pressure(TEST PASSED),injection pump was shut down prior too testing and resumed operation following testing.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1288381186
 
| 1288381186
 
| 2010-10-29
 
| 2010-10-29
|
+
|  
 
| On site to witness mini test on annulus of tubing Sweeny Well Service pressured up to 370 psi and we monitored pressure for 15 min with no decline in pressure TEST PASSED. Injection pump was in operation during my inspection.
 
| On site to witness mini test on annulus of tubing Sweeny Well Service pressured up to 370 psi and we monitored pressure for 15 min with no decline in pressure TEST PASSED. Injection pump was in operation during my inspection.
 
Note: 600,648 bbl has been disposed of since well went into operation.
 
Note: 600,648 bbl has been disposed of since well went into operation.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1296163532
 
| 1296163532
 
| 2011-01-26
 
| 2011-01-26
|
+
|  
 
| On site to witness mini test on annulus of tubing Sweeny Well Service pressured up to 350 psi and we monitored pressure for 15 min with no decline in pressure.
 
| On site to witness mini test on annulus of tubing Sweeny Well Service pressured up to 350 psi and we monitored pressure for 15 min with no decline in pressure.
 
Note: 652,798 bbl  of water has been disposed of since well went into operation.
 
Note: 652,798 bbl  of water has been disposed of since well went into operation.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1299194767
 
| 1299194767
 
| 2011-02-28
 
| 2011-02-28
|
+
|  
 
| On site to witness mini test of annulus pressure being applied by Sweeny Well Service they applied 350 #pressure and we monitired pressure for 15 min. with no decline in pressure,injection pump was in operation during my inspection.
 
| On site to witness mini test of annulus pressure being applied by Sweeny Well Service they applied 350 #pressure and we monitired pressure for 15 min. with no decline in pressure,injection pump was in operation during my inspection.
 
Note: 676,050 bbl of water disposed of since well went into operation.
 
Note: 676,050 bbl of water disposed of since well went into operation.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1301341808
 
| 1301341808
 
| 2011-03-28
 
| 2011-03-28
|
+
|  
 
| Inspection revealed that pump was in operation today.
 
| Inspection revealed that pump was in operation today.
 
Note: 711,681 bbl disposed of since well went into operation.
 
Note: 711,681 bbl disposed of since well went into operation.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1301690913
 
| 1301690913
 
| 2011-03-31
 
| 2011-03-31
|
+
|  
 
| On site to witness mini test of annulus of tubing Sweeny Well Service pressured up to 370 psi and we monitored pressure for 15 min with no decline in pressure.
 
| On site to witness mini test of annulus of tubing Sweeny Well Service pressured up to 370 psi and we monitored pressure for 15 min with no decline in pressure.
 
Note: Held mini meeting with well operator to discuss better ventilation in pump house area and also discussed possible hazards in unloading area while trucks were unloading water.
 
Note: Held mini meeting with well operator to discuss better ventilation in pump house area and also discussed possible hazards in unloading area while trucks were unloading water.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1303503994
 
| 1303503994
 
| 2011-04-21
 
| 2011-04-21
|
+
|  
 
| Inspection revealed that pump was in operation during my inspection and 3 Buckeye Water Service vac trucks were unloading at facility during my inspection.
 
| Inspection revealed that pump was in operation during my inspection and 3 Buckeye Water Service vac trucks were unloading at facility during my inspection.
 
Note: 742,116 BBL  has been pumped down well since it went into operation.
 
Note: 742,116 BBL  has been pumped down well since it went into operation.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1303854655
 
| 1303854655
 
| 2011-04-26
 
| 2011-04-26
|
+
|  
 
| On site to witness Baker Crane Rental place four new 210 bbl tanks within dike area and company personnel plumbed them up and placed tanks into service.
 
| On site to witness Baker Crane Rental place four new 210 bbl tanks within dike area and company personnel plumbed them up and placed tanks into service.
 
Note: Injection pump was not in operation today due to fact that additional storage tanks were being placed within dike area.
 
Note: Injection pump was not in operation today due to fact that additional storage tanks were being placed within dike area.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1304501446
 
| 1304501446
 
| 2011-05-03
 
| 2011-05-03
|
+
|  
 
| Inspection revealed that injection pump was in operation during my inspection and Corp Well Services vac truck was unloading at facility and H&L Water Services was also unloading at facility.
 
| Inspection revealed that injection pump was in operation during my inspection and Corp Well Services vac truck was unloading at facility and H&L Water Services was also unloading at facility.
 
Note:755,730 bbl of water has been disposed of since well went into operation.
 
Note:755,730 bbl of water has been disposed of since well went into operation.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1305807687
 
| 1305807687
 
| 2011-05-18
 
| 2011-05-18
|
+
|  
 
| Accompanied Dave Ball with Josh Garland on inspection.
 
| Accompanied Dave Ball with Josh Garland on inspection.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1307726668
 
| 1307726668
 
| 2011-05-18
 
| 2011-05-18
|
+
|  
 
| accompanied D. Ball on inspection.
 
| accompanied D. Ball on inspection.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1308608527
 
| 1308608527
 
| 2011-06-20
 
| 2011-06-20
|
+
|  
 
| On site to witness acid job preformed on well Producers Services pumped 2000 gal of 15% acid down tubing and displaced with 2100 gal of fresh water and shut well in and they will resume operations later today.
 
| On site to witness acid job preformed on well Producers Services pumped 2000 gal of 15% acid down tubing and displaced with 2100 gal of fresh water and shut well in and they will resume operations later today.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1309477850
 
| 1309477850
 
| 2011-06-30
 
| 2011-06-30
|
+
|  
 
| On site to witness Sweeny Well Service perform mini test on annulus of tubing they pressured up on tubing to 350# and we monitored pressure for 15 minutes with no decline in pressure and it was noted that Corp Oilfield Services vac truck was unloading at facility during my inspection.
 
| On site to witness Sweeny Well Service perform mini test on annulus of tubing they pressured up on tubing to 350# and we monitored pressure for 15 minutes with no decline in pressure and it was noted that Corp Oilfield Services vac truck was unloading at facility during my inspection.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1309906052
 
| 1309906052
 
| 2011-07-05
 
| 2011-07-05
|
+
|  
 
| Inspection revealed that well is in operation and injection pump was running during my inspection,noted that storage tanks have been repainted since my last inspection and operator pumped 48,554 bbl of water down well last month and total bbl since well went into operation is 844,122.
 
| Inspection revealed that well is in operation and injection pump was running during my inspection,noted that storage tanks have been repainted since my last inspection and operator pumped 48,554 bbl of water down well last month and total bbl since well went into operation is 844,122.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1317415950
 
| 1317415950
 
| 2011-09-30
 
| 2011-09-30
|
+
|  
 
| On site to witness Sweeny Well Service apply pressure to annulus of tubing to check integrity of production casing they applied 350 psi and we monitored it for 15 minutes with no decline in pressure.
 
| On site to witness Sweeny Well Service apply pressure to annulus of tubing to check integrity of production casing they applied 350 psi and we monitored it for 15 minutes with no decline in pressure.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1317936118
 
| 1317936118
|
+
|  
|
+
|  
 
| FLOW LINE TESTED AND PASSED. 1500#
 
| FLOW LINE TESTED AND PASSED. 1500#
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1319490541
 
| 1319490541
 
| 2011-10-24
 
| 2011-10-24
|
+
|  
 
| Inspection revealed that injection pump was in operation today and new building addition has been completed.  Awaiting delivery of new pump, filter housing and 4 additional storage tanks.
 
| Inspection revealed that injection pump was in operation today and new building addition has been completed.  Awaiting delivery of new pump, filter housing and 4 additional storage tanks.
 
Note: 1,017,537 bbls of water have been disposed of in this well since it went into operation.
 
Note: 1,017,537 bbls of water have been disposed of in this well since it went into operation.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1326650773
 
| 1326650773
 
| 2012-01-14
 
| 2012-01-14
|
+
|  
 
| On site to witness acid job being performed on injection well,Producers Services pumped 2000 gallon of 15% acid down well at a average pressure of 1388 psi and ISIP was 1170 psi and and 5 min pressure was noted at 1136 psi.
 
| On site to witness acid job being performed on injection well,Producers Services pumped 2000 gallon of 15% acid down well at a average pressure of 1388 psi and ISIP was 1170 psi and and 5 min pressure was noted at 1136 psi.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1328227950
 
| 1328227950
 
| 2012-01-31
 
| 2012-01-31
|
+
|  
 
| Company rep called and stated that he thought well was equalizing pressure wants inspector to check pressures upon checking it was determined that tubing possibly has hole in it instructed operator to shut well down and acquire service rig to pull tubing.
 
| Company rep called and stated that he thought well was equalizing pressure wants inspector to check pressures upon checking it was determined that tubing possibly has hole in it instructed operator to shut well down and acquire service rig to pull tubing.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1328745064
 
| 1328745064
 
| 2012-02-04
 
| 2012-02-04
|
+
|  
 
| On site to witness running and testing of tubing and annulus of tubing, Producers Services pumped fluid on annulus and we did preliminary testing on integrity will perform official testing on Monday.
 
| On site to witness running and testing of tubing and annulus of tubing, Producers Services pumped fluid on annulus and we did preliminary testing on integrity will perform official testing on Monday.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1333409395
 
| 1333409395
 
| 2012-03-30
 
| 2012-03-30
|
+
|  
 
| Inspected site  and found well in operation and Sweeny Well Service pressure tested annulus of tubing to 300 psi and we monitored pressure for 15 min with no decline in pressure.
 
| Inspected site  and found well in operation and Sweeny Well Service pressure tested annulus of tubing to 300 psi and we monitored pressure for 15 min with no decline in pressure.
 
1,206,439 bbl disposed of since well went into operation.
 
1,206,439 bbl disposed of since well went into operation.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1338420324
 
| 1338420324
 
| 2012-05-30
 
| 2012-05-30
|
+
|  
 
| Inspection revealed that injection pump was not in operation during my inspection and it was noted that there was two Whip stock Vac trucks unloading at facility during my inspection.
 
| Inspection revealed that injection pump was not in operation during my inspection and it was noted that there was two Whip stock Vac trucks unloading at facility during my inspection.
 
Note: 1,250,198  bbls of brine has been disposed of since well went into operation.
 
Note: 1,250,198  bbls of brine has been disposed of since well went into operation.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1344706418
 
| 1344706418
 
| 2012-08-06
 
| 2012-08-06
|
+
|  
 
| Inspection revealed that injection pump was not in operation during my inspection, company rep on site having discussion with contractor concerning cleaning out of storage tanks and hauling off of material to a approved landfill.
 
| Inspection revealed that injection pump was not in operation during my inspection, company rep on site having discussion with contractor concerning cleaning out of storage tanks and hauling off of material to a approved landfill.
 
Note: 1,304,489 bbl has been disposed of since well went into operation.
 
Note: 1,304,489 bbl has been disposed of since well went into operation.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1351807474
 
| 1351807474
 
| 2012-10-31
 
| 2012-10-31
|
+
|  
 
| Inspection revealed that injection pump was in operation during my inspection and it was noted that annulus pressure was at zero and I suggested  to operator that they have pressure applied to annulus as soon as possible.
 
| Inspection revealed that injection pump was in operation during my inspection and it was noted that annulus pressure was at zero and I suggested  to operator that they have pressure applied to annulus as soon as possible.
 
Note: 1,381,345 bbl has been disposed of since well went into operation.
 
Note: 1,381,345 bbl has been disposed of since well went into operation.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1354985066
 
| 1354985066
 
| 2012-12-06
 
| 2012-12-06
|
+
|  
 
| Inspection revealed that injection pump was not in operation during my inspection and it was noted that packing on #2 cylinder was leaking and after talking to operator stating new packing was ordered and once received they would replace it.
 
| Inspection revealed that injection pump was not in operation during my inspection and it was noted that packing on #2 cylinder was leaking and after talking to operator stating new packing was ordered and once received they would replace it.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1356101681
 
| 1356101681
 
| 2012-12-18
 
| 2012-12-18
|
+
|  
 
| Inspection revealed that injection pump was in operation and facility appears to be in satisfactory condition this inspection.
 
| Inspection revealed that injection pump was in operation and facility appears to be in satisfactory condition this inspection.
 
Note: 1,437,612 bbl of water has been disposed of since well went into operation.
 
Note: 1,437,612 bbl of water has been disposed of since well went into operation.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1370041671
 
| 1370041671
 
| 2013-05-30
 
| 2013-05-30
|
+
|  
 
| Inspection revealed that injection pump was in operation during my inspection and it was noted that Huey Trucking was unloading at facility during my inspection.
 
| Inspection revealed that injection pump was in operation during my inspection and it was noted that Huey Trucking was unloading at facility during my inspection.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1374262183
 
| 1374262183
 
| 2013-07-19
 
| 2013-07-19
|
+
|  
 
| Inspection revealed that injection pump was in operation today and it was noted that one H&L Water Haulers tanker was unloading at site during my inspection.
 
| Inspection revealed that injection pump was in operation today and it was noted that one H&L Water Haulers tanker was unloading at site during my inspection.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1378361201
 
| 1378361201
 
| 2012-06-25
 
| 2012-06-25
|
+
|  
 
| Inspection revealed that injection pump was not in operation during my inspection, noted that cameras have been installed at well head to help monitor area and well head in the event of flow line failure and possible vandalizing.
 
| Inspection revealed that injection pump was not in operation during my inspection, noted that cameras have been installed at well head to help monitor area and well head in the event of flow line failure and possible vandalizing.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1385881391
 
| 1385881391
 
| 2010-12-29
 
| 2010-12-29
|
+
|  
 
| On site along with supervisor to witness mini test preformed on annulus of tubing,Swenny Well Service pressured up to 350 psi and we monitored pressure for 15 min with no decline in pressure.
 
| On site along with supervisor to witness mini test preformed on annulus of tubing,Swenny Well Service pressured up to 350 psi and we monitored pressure for 15 min with no decline in pressure.
 
Note: 636,748 bbl of water disposed of since well went into operation.
 
Note: 636,748 bbl of water disposed of since well went into operation.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1386357870
 
| 1386357870
 
| 2013-12-05
 
| 2013-12-05
|
+
|  
 
| Inspection revealed  that injection pump was in operation today and it was noted that one Buckeye Water Services vacuum truck was unloading at site during my inspection.
 
| Inspection revealed  that injection pump was in operation today and it was noted that one Buckeye Water Services vacuum truck was unloading at site during my inspection.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1392248814
 
| 1392248814
 
| 2014-02-11
 
| 2014-02-11
|
+
|  
 
| Inspection revealed that injection pump was in operation during my inspection.
 
| Inspection revealed that injection pump was in operation during my inspection.
 
Note: Walked flow line area to monitor area for any potential leaks none were found  on this day of my inspection.
 
Note: Walked flow line area to monitor area for any potential leaks none were found  on this day of my inspection.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| 1409350368
 +
| 2014-08-29
 +
|
 +
| On site to perform mini test on annulus of tubing after changing out 2 valve on well head,Swenny Well Service pressured up on the annulus of tubing  for well owner.(Test Passed)
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| 1412896037
 +
| 2014-10-07
 +
|
 +
| Inspection revealed that injection pump was in operation during my inspection and it was noted that one Corp Oilfield Services vacuum truck was unloading at the facility during my inspection.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| 1415227673
 +
| 2014-11-04
 +
|
 +
| Inspection revealed that injection pump was just started prior to my inspection and it was noted that two Buckeye Water Service vacuum trucks were unloading at the facility during my inspection.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| 1419032355
 +
| 2014-12-19
 +
|
 +
| Inspection revealed that injection pump was not in operation during my inspection and it was noted that containment area was free of any fluids and proper identification is posted.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| 1428829301
 +
| 2015-04-11
 +
|
 +
| Producers Services on site to perform 2000 gal acid treatment on said well.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 1446820158
 
| 1446820158
 
| 2010-12-06
 
| 2010-12-06
|
+
|  
 
| On site to witness mini test preformed on annulus to tubing Sweeny Well Serviced pressured up to 350 psi and we monitored pressure for 15 min with no decline in pressure,
 
| On site to witness mini test preformed on annulus to tubing Sweeny Well Serviced pressured up to 350 psi and we monitored pressure for 15 min with no decline in pressure,
 
Note: Injection pump was in operation during my inspection and there was one vac truck unloading at facility during inspection(Corp Oilfield Services).
 
Note: Injection pump was in operation during my inspection and there was one vac truck unloading at facility during inspection(Corp Oilfield Services).
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 146897399
 
| 146897399
 
| 2008-10-03
 
| 2008-10-03
|
+
|  
 
| WORKING ON TANK VALVES. CHANGING LEAKING FITTINGS.
 
| WORKING ON TANK VALVES. CHANGING LEAKING FITTINGS.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -1478919296
 +
| 2009-02-24
 +
|
 +
| SWIW INSPECTED. UNLOADING PAD AND FACILITY IN GOOD REPAIR. NO VIOLATIONS NOTED.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -1491684624
 +
| 2010-03-01
 +
|
 +
| On site to witness mini test on annulas of tubing Sweeny Well Service pressured up to 360 psi and we monitored pressure for 15 min with no decline in pressure(TEST PASSED) and injection pump was in operation during my inspection.
 +
Note: 390,595 bbl of water has been injected since well went into operation.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -1493195847
 +
| 2010-11-24
 +
|
 +
| Inspection revealed that well was not in operation during my inspection,well operator was in process of changing filters in pumphouse and was planning on placing well into operation after mainitence work was completed.
 +
Note: 613,574 bbl disposed of since well went into service.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 1498563657
 
| 1498563657
 
| 2012-02-06
 
| 2012-02-06
|
+
|  
 
| On site to conduct official testing of integrity of casing and pump fresh water and inhibitor to annulus of tubing, Producer services arrived on site and Baker Packer hand uncoupled from tubing and we flushed annulus of tubing with inhibitor and then they coupled back on tubing and we pressured tested at 1787 psi and monitored pressure for 15 minutes with no decline in pressures.
 
| On site to conduct official testing of integrity of casing and pump fresh water and inhibitor to annulus of tubing, Producer services arrived on site and Baker Packer hand uncoupled from tubing and we flushed annulus of tubing with inhibitor and then they coupled back on tubing and we pressured tested at 1787 psi and monitored pressure for 15 minutes with no decline in pressures.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -150070169
 +
| 2008-08-19
 +
|
 +
| SWIW TOP SOIL BEING SPREAD ON BOTTOM OF LINER ON OUTSIDE OF DIKE AREA. PLUMBING STILL BEING HOOKED UP TO OVERFLOW VAULT ON OUTSIDE OF UNLOADING PAD.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -1514378127
 +
| 2015-04-08
 +
|
 +
| Inspection revealed that injection pump was in operation during my inspection.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 1519543692
 
| 1519543692
 
| 2012-05-14
 
| 2012-05-14
|
+
|  
 
| Inspection revealed that injection pump was in operation during my inspection.
 
| Inspection revealed that injection pump was in operation during my inspection.
 
Note: Restoration work at site has been completed pits have been closed and site restored and vegetation has been established.
 
Note: Restoration work at site has been completed pits have been closed and site restored and vegetation has been established.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -155224430
 +
| 2008-08-18
 +
|
 +
| SETTING IN 2400 GAL CEMENT VAULT FOR PAD DRAIN. PLUMB IN VAULT.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -1559212810
 +
| 2010-01-20
 +
|
 +
| Inspection revealed that injection pump was in operation during my inspection.
 +
Note: Dow Cameron vac truck unloading at site during my inspection,370,656 bbl water put away since well went into operation.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -1559431971
 +
| 2012-02-02
 +
|
 +
| On site to witness Baker Oil Tool employee unhook tubing from packer and pull tubing trying to find hole in it we located hole and decision was made to get new string of tubing and run it back in hole tomorrow.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -1560256822
 +
| 2008-05-05
 +
|
 +
| APPALACHIAN WELL SURVEY'S RUN CEMENT BOND LOG ON HOLE.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -1563713596
 +
| 2015-01-23
 +
|
 +
| Inspection revealed that injection pump was not in operation during my inspection.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 1572863734
 
| 1572863734
 
| 2012-10-22
 
| 2012-10-22
|
+
|  
 
| Inspection revealed that injection pump was in operation during my inspection and it was noted that annulus pressure has reached zero and it is requested that you have positive pressure applied to annulus of tubing in the near future.
 
| Inspection revealed that injection pump was in operation during my inspection and it was noted that annulus pressure has reached zero and it is requested that you have positive pressure applied to annulus of tubing in the near future.
 
Note: 1,365,368 barrel of water has been disposed of since well went into operation.
 
Note: 1,365,368 barrel of water has been disposed of since well went into operation.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -1618534015
 +
| 2015-03-27
 +
|
 +
| On site along with company rep to witness mini pressure test on annulus of tubing Sweeny Well Service pressured up annulus to 700 psi and we monitored pressure for 15 minutes with no decline in pressure.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 1627477762
 
| 1627477762
 
| 2013-10-15
 
| 2013-10-15
|
+
|  
 
| Inspection revealed that injection pump was in operation during my inspection and it was noted that injection pump gear end is in need of repair.
 
| Inspection revealed that injection pump was in operation during my inspection and it was noted that injection pump gear end is in need of repair.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1629049053
 
| 1629049053
 
| 2009-12-24
 
| 2009-12-24
|
+
|  
 
| Inspection revealed that well is not in operation today,well tender stated that not much water coming in today due to holiday.
 
| Inspection revealed that well is not in operation today,well tender stated that not much water coming in today due to holiday.
 
Note: Stone is needed around facility to help cut down on tracking mud out onto county road.
 
Note: Stone is needed around facility to help cut down on tracking mud out onto county road.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1647132619
 
| 1647132619
 
| 2012-03-05
 
| 2012-03-05
|
+
|  
 
| Inspection revealed that injection pump is down for repair one of the pistons has become in operable and repair personnel were to arrive tomorrow to repair pump.
 
| Inspection revealed that injection pump is down for repair one of the pistons has become in operable and repair personnel were to arrive tomorrow to repair pump.
 
Note: Stone has been applied to driveway and some has been placed in tank area.
 
Note: Stone has been applied to driveway and some has been placed in tank area.
  
 
1,181,072 bbl disposed of since well went into operation.
 
1,181,072 bbl disposed of since well went into operation.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1650684974
 
| 1650684974
 
| 2011-07-28
 
| 2011-07-28
|
+
|  
 
| On site to witness mini test of annulus of tubing Sweeny Well Serviced pressured up on backside of tubing to 340 psi and we monitored pressure for 15min with no pressure loss.
 
| On site to witness mini test of annulus of tubing Sweeny Well Serviced pressured up on backside of tubing to 340 psi and we monitored pressure for 15min with no pressure loss.
 
Note:885,540 bbl of water has went down well since it went into operation.
 
Note:885,540 bbl of water has went down well since it went into operation.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -1683725546
 +
| 2012-02-04
 +
|
 +
| On site to witness Chipco Well Services run tubing back into well and latch onto packer and perform pretesting of annulus we pressured up to 1800 psi and monitored pressure for 15 min. with no decline, will perform official test on Monday with Producers Services pump truck.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 1684276670
 
| 1684276670
 
| 2013-12-09
 
| 2013-12-09
|
+
|  
 
| Sweeny Well Service on site to pressure test annulus of tubing they applied 600# of pressure and we monitored pressure for 15 minutes with no decline in pressure.
 
| Sweeny Well Service on site to pressure test annulus of tubing they applied 600# of pressure and we monitored pressure for 15 minutes with no decline in pressure.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| 1686493466
 +
| 2015-06-01
 +
|
 +
| Inspection revealed that injection pump was not in operation during my inspection and it was noted that two Buckeye Water Services vacuum trucks were unloading at the facility on this day.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 1687005480
 
| 1687005480
 
| 2012-02-29
 
| 2012-02-29
|
+
|  
 
| Inspection revealed that injection pump was in operation during my inspection.
 
| Inspection revealed that injection pump was in operation during my inspection.
 
Note: Area of pit site is in need of restoration work performed as weather permits.
 
Note: Area of pit site is in need of restoration work performed as weather permits.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -1690178081
 +
| 2014-07-15
 +
|
 +
| Inspection revealed that injection pump was in operation today and it was noted that one Buckeye Water Service vacuum truck was unloading at facility during my inspection.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 1728540131
 
| 1728540131
 
| 2008-09-22
 
| 2008-09-22
|
+
|  
 
| G AND L DRILLING AT 3450'
 
| G AND L DRILLING AT 3450'
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1739801852
 
| 1739801852
 
| 2013-11-04
 
| 2013-11-04
|
+
|  
 
| On site to witness Sweeny Well Service apply 350# of pressure to annulus of tubing and we monitored pressure for 15 minutes with no decline in pressure.
 
| On site to witness Sweeny Well Service apply 350# of pressure to annulus of tubing and we monitored pressure for 15 minutes with no decline in pressure.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -1748823651
 +
| 2008-08-12
 +
|
 +
| LAYING IN OF 2-20 MIL LINERS ON INSIDE OF DIKE.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 1781373611
 
| 1781373611
 
| 2009-06-29
 
| 2009-06-29
|
+
|  
 
| Witnessed monthly annular pressure test.  Annulus was pressured up to 300 psig and held for 15minutes.  Test passed.
 
| Witnessed monthly annular pressure test.  Annulus was pressured up to 300 psig and held for 15minutes.  Test passed.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 1824132536
 
| 1824132536
 
| 2009-04-29
 
| 2009-04-29
|
+
|  
 
| Inspection revealed that well was in operation during my inspection, pump was running injection pressure was 950 psi and there was two vac trucks unloading at facility during my inspection(GR-Contracting and Kodiak Water Services) facility is a very well kept !
 
| Inspection revealed that well was in operation during my inspection, pump was running injection pressure was 950 psi and there was two vac trucks unloading at facility during my inspection(GR-Contracting and Kodiak Water Services) facility is a very well kept !
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 18261165
 
| 18261165
 
| 2013-11-12
 
| 2013-11-12
|
+
|  
 
| Inspection revealed that injection pump was in operation today and it was noted that one Buckeye Water Service vacuum truck was unloading at facility during my inspection.
 
| Inspection revealed that injection pump was in operation today and it was noted that one Buckeye Water Service vacuum truck was unloading at facility during my inspection.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -1849592333
 +
| 2009-04-29
 +
|
 +
| Restoration work at site satisfactory,pit has been filled in and site restored and vegetation has been established site is currently being used for a active Salt Water Injection Facility.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 1947254021
 
| 1947254021
 
| 2010-08-27
 
| 2010-08-27
|
+
|  
 
| Inspection revealed that injection pump was in operation during my inspection and operator stated that they were planning on performing mini test on annulus of tubing in the near future.
 
| Inspection revealed that injection pump was in operation during my inspection and operator stated that they were planning on performing mini test on annulus of tubing in the near future.
 
Note: 560,651 bbl of water has been disposed of since well went into operation.
 
Note: 560,651 bbl of water has been disposed of since well went into operation.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -197109858
 +
| 2012-08-21
 +
|
 +
| On site with UIC Director and group from Central Office to inspect well site and surface facility and discuss any issues with well operator concerning facility.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -1999546532
 +
| 2008-04-28
 +
|
 +
| CHIPCO DRILLING OUT FORMATION PACKER
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -200516364
 +
| 2012-04-25
 +
|
 +
| Inspection revealed that well was in operation on this day, well caretaker was changing filters during my inspection and it was noted that Buckeye Water Services was unloading tanker truck at site.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 2025559258
 
| 2025559258
 
| 2010-02-11
 
| 2010-02-11
|
+
|  
 
| Inspection revealed that injection pump was not in operation during my inspection, noted that 2 Buckeye Water Service vac trucks were unloading at facility during my inspection.
 
| Inspection revealed that injection pump was not in operation during my inspection, noted that 2 Buckeye Water Service vac trucks were unloading at facility during my inspection.
 
Note: 381,321 bbl of brine disposed of as of this date according to barrel counter installed at site.
 
Note: 381,321 bbl of brine disposed of as of this date according to barrel counter installed at site.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 2034477575
 
| 2034477575
 
| 2008-09-03
 
| 2008-09-03
|
+
|  
 
| COSTRUCTION STILL CONTINUES ON SURFACE FACILITY
 
| COSTRUCTION STILL CONTINUES ON SURFACE FACILITY
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -2039009496
 +
| 2011-09-07
 +
|
 +
| Inspection revealed that injection pump was in operation during my inspection and there was three vacuum trucks unloading at facility also, walked flow line area to monitor for potential leaks(none found) facility was in good repair this inspection.
 +
Note: 941,746 bbl of water has been disposed of since well went into operation.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 206707138
 
| 206707138
 
| 2011-09-22
 
| 2011-09-22
|
+
|  
 
| Well is in operation with pump running at 85% capacity @1550 PSI.  There were several brine trucks at facility during my inspection.
 
| Well is in operation with pump running at 85% capacity @1550 PSI.  There were several brine trucks at facility during my inspection.
 
Note: Owner is expanding pump house facility to accommodate additional pump once new well is drilled and it passes all required testing for a injection facility.
 
Note: Owner is expanding pump house facility to accommodate additional pump once new well is drilled and it passes all required testing for a injection facility.
 
There has been 966,810 bbl of brine disposed of since this disposal well went into operation.
 
There has been 966,810 bbl of brine disposed of since this disposal well went into operation.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -2068245965
 +
| 2008-04-17
 +
|
 +
| DRILLED TO 8500' FOR PURPOSE OF INJECTION WELL. DRILLING OUT DV TOOLS IN 5.5
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -2076879871
 +
| 2008-10-02
 +
|
 +
| SALT WATER INJECTION WELL
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -2090380607
 +
| 2008-11-03
 +
|
 +
| WELL IS IN OPERATION. NO VIOLATIONS NOTED.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 2120462086
 
| 2120462086
 
| 2012-04-17
 
| 2012-04-17
|
+
|  
 
| RESTORATION WORK AT SITE SATISFACTORY.
 
| RESTORATION WORK AT SITE SATISFACTORY.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -223578216
 +
| 2013-01-17
 +
|
 +
| On site with company personnel Don Krieger and John Suhar to review injection well monitoring charts to try and determine if there is a possibility of leakage in tubing or packer after reviewing data it was determined that annulus pressure increase was due to thermal expansion to down hole fluid when well is not in operation.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -225951818
 +
| 2008-04-21
 +
|
 +
| CHIPCO DRILLING OUT DV TOOL. WILL HAVE TO TRIP FOR BIT. JOHN SUHAR WILL TAKE PERMIT APPLICATION TO COLUMBUS TODAY.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -284590190
 +
| 2014-06-03
 +
|
 +
| Inspection revealed that injection pump was in operation today and it was noted that one H&L Water Service vacuum truck was unloading at this facility on the day of my inspection.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 315114216
 
| 315114216
 
| 2008-09-23
 
| 2008-09-23
|
+
|  
 
| STILL FILLING TANKS TO CHECK FOR LEAKS
 
| STILL FILLING TANKS TO CHECK FOR LEAKS
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 326126134
 
| 326126134
 
| 2013-01-30
 
| 2013-01-30
|
+
|  
 
| Inspection revealed that injection pump was not running during my inspection and it was noted that brine filter skid has one chamber in need of replacement, talked to well operator and he stated that they have one ordered and it should be replaced by the end of the week.
 
| Inspection revealed that injection pump was not running during my inspection and it was noted that brine filter skid has one chamber in need of replacement, talked to well operator and he stated that they have one ordered and it should be replaced by the end of the week.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -341072783
 +
| 2014-04-15
 +
|
 +
| Inspection revealed that injection pump was in operation during my inspection and it was noted that two H&L Water vacuum trucks were unloading at facility during my inspection.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 361163417
 
| 361163417
 
| 2011-12-12
 
| 2011-12-12
|
+
|  
| During my inspection the injection pump was in operation and Buckeye Water Services was unloading.
+
| During my inspection the injection pump was in operation and Buckeye Water Services was unloading.  
 
Note: 1,089,357 bbl of water has been disposed of in this well since it went into operation.
 
Note: 1,089,357 bbl of water has been disposed of in this well since it went into operation.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -364566513
 +
| 2012-04-17
 +
|
 +
| Inspection revealed that injection pump was not in operation during my inspection and facility appeared to be in satisfactory condition this inspection.
 +
Note: 1,218,997 bbl of brine disposed of since well went into operation.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 367888702
 
| 367888702
 
| 2008-03-09
 
| 2008-03-09
|
+
|  
 
| LOST CIRCULATION. MIX MUD. WEIGHT UP TO 9.7#. RE-ESTABLISH CIRCULATION. BACK TO DRILLING.8057'.
 
| LOST CIRCULATION. MIX MUD. WEIGHT UP TO 9.7#. RE-ESTABLISH CIRCULATION. BACK TO DRILLING.8057'.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 449971104
 
| 449971104
 
| 2010-05-03
 
| 2010-05-03
|
+
|  
 
| On site at request of company rep too witness mini test on annulus of tubing Swenney Well Service pressured up on backside of tubing too 380 psi and we monitored pressure for 15 minutes with no decline in pressure .
 
| On site at request of company rep too witness mini test on annulus of tubing Swenney Well Service pressured up on backside of tubing too 380 psi and we monitored pressure for 15 minutes with no decline in pressure .
 
Note: Pump was in operation during my inspection and 446,253 bbl of water has been disposed of as of this date.
 
Note: Pump was in operation during my inspection and 446,253 bbl of water has been disposed of as of this date.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 483461478
 
| 483461478
 
| 2010-04-01
 
| 2010-04-01
|
+
|  
 
| On site to witness mini testing of annulus of tubing Sweeney Well Service preformed testing, and pump was in operation during my inspection.
 
| On site to witness mini testing of annulus of tubing Sweeney Well Service preformed testing, and pump was in operation during my inspection.
 
Note: 417,874 bbl of water disposed of as of this date since well went into operation.
 
Note: 417,874 bbl of water disposed of as of this date since well went into operation.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -538164671
 +
| 2013-06-27
 +
|
 +
| Inspection revealed that injection pump was in operation today and it was noted that two Buckeye Water Services vacuum trucks were unloading at site during my inspection.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 571328866
 
| 571328866
 
| 2014-05-09
 
| 2014-05-09
|
+
|  
 
| Inspection revealed that injection pump was in operation during my inspection and it was noted that one H&L Water Services vacuum truck was unloading at facility during my inspection.
 
| Inspection revealed that injection pump was in operation during my inspection and it was noted that one H&L Water Services vacuum truck was unloading at facility during my inspection.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -575310412
 +
| 2015-03-06
 +
|
 +
| Inspection revealed that injection pump was in operation today and it was noted that one Buckeye Water Services vacuum truck and one H&L Water Services  truck was unloading at the facility during my inspection.
 +
Note: Walked flow line area to monitor area for leaks none were detected.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -577842201
 +
| 2008-03-10
 +
|
 +
| KILBARGER DRILLING#17. DRILLING ON MUD. LOST CIRCULATION 2 TIMES IN 24 HRS. DRILLING AT 8157'
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 586743487
 
| 586743487
 
| 2011-03-15
 
| 2011-03-15
|
+
|  
 
| Inspection revealed that well is in operation and pump was running during my inspection.
 
| Inspection revealed that well is in operation and pump was running during my inspection.
 
Note: 698,485 bbl disposed of since well went into operation, also noted that owner has applied stone around facility since my  last inspection.
 
Note: 698,485 bbl disposed of since well went into operation, also noted that owner has applied stone around facility since my  last inspection.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -593575519
 +
| 2012-09-24
 +
|
 +
| BOS Fluids system on site to clean out storage tanks at facility will monitor progress on getting tanks cleaned and wells back into operation.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 604208533
 
| 604208533
 
| 2014-08-18
 
| 2014-08-18
|
+
|  
 
| Inspection revealed that injection pump was in operation during my inspection.
 
| Inspection revealed that injection pump was in operation during my inspection.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 619212723
 
| 619212723
 
| 2010-07-15
 
| 2010-07-15
|
+
|  
 
| Inspection revealed that pump was not in operation during my inspection,caretaker was cleaning unloading pad during my inspection.
 
| Inspection revealed that pump was not in operation during my inspection,caretaker was cleaning unloading pad during my inspection.
 
Note: 524,666 bbl have been disposed of since well went into operation.
 
Note: 524,666 bbl have been disposed of since well went into operation.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -645681029
 +
| 2014-04-01
 +
|
 +
| Inspection revealed that injection pump was in operation today and it was noted that one Buckeye Water Service vacuum truck was unloading at facility during  my inspection.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 649254192
 
| 649254192
 
| 2013-05-01
 
| 2013-05-01
|
+
|  
 
| Inspection revealed that injection pump was not in operation during my inspection and it was noted that one Buckeye Water Service vacuum truck was unloading at facility during my inspection,
 
| Inspection revealed that injection pump was not in operation during my inspection and it was noted that one Buckeye Water Service vacuum truck was unloading at facility during my inspection,
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 679440780
 
| 679440780
 
| 2008-12-02
 
| 2008-12-02
|
+
|  
 
| INJECTING PIT WATER TODAY. PUMP PRESSURE IS ELEVATED SOME. NO VIOLATIONS NOTED DURING THIS INSPECTION.
 
| INJECTING PIT WATER TODAY. PUMP PRESSURE IS ELEVATED SOME. NO VIOLATIONS NOTED DURING THIS INSPECTION.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -683119350
 +
| 2009-11-16
 +
|
 +
| Inspection revealed that injection pump ws not in operation during my inspection,noted that seed and mulch has been applied to area around wellhead to help bind soil and prevent erosion issues at site.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -721787425
 +
| 2011-08-09
 +
|
 +
| Inspection revealed that pump was in operation during my inspection and there was two vac trucks unloading at site during my inspection.
 +
Noted that dirt has been put in place around vault area and seed and mulch has been applied to area.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 736907431
 
| 736907431
 
| 2008-03-17
 
| 2008-03-17
|
+
|  
| RUN AND CEMENT 5.5" INJECTION WELL.7218' 5.5" 286 SX HALLIBURTON TO 6000'. 2 STAGE TOOL RUN IN. WAIT 6 HRS. PUMP 500SX. 6000'- 3300' 500 SX.
+
| RUN AND CEMENT 5.5 INJECTION WELL.7218' 5.5 286 SX HALLIBURTON TO 6000'. 2 STAGE TOOL RUN IN. WAIT 6 HRS. PUMP 500SX. 6000'- 3300' 500 SX.
|
+
|
|
+
|
|
+
|
 +
|-
 +
|-
 +
| -738690761
 +
| 2011-11-22
 +
|
 +
| Inspection revealed that pump was in operation and there ws several vaccum trucks waiting to unload at facility.  Note: 1,063,645 bbl of water has been disposed of since well went into operation.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -804412253
 +
| 2012-12-06
 +
|
 +
| Restoration work at site satisfactory pit has been filled and site has vegetation established.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -819557891
 +
| 2010-05-25
 +
|
 +
| On site to witness mini test on annulus of tubing,Swenny Well Service pressured up to 350 psi and well monitored pressure for 15 min. with no decline in pressure, injection pump was not in operation during my inspection.
 +
|
 +
|
 +
|
 +
|-
 +
|-
 +
| -822745846
 +
| 2010-09-09
 +
|
 +
| Inspection revealed that injection pump was in operation during my inspection.
 +
Note: 567574 bbl of water disposed of since well went into operation.
 +
|  
 +
|  
 +
|  
 
|-
 
|-
 
|-
 
|-
 
| 861229868
 
| 861229868
 
| 2013-08-19
 
| 2013-08-19
|
+
|  
 
| Inspection revealed that injection pump was in operation during my inspection.
 
| Inspection revealed that injection pump was in operation during my inspection.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|-
 
|-
 
| 956093730
 
| 956093730
 
| 2011-05-19
 
| 2011-05-19
|
+
|  
 
| On site with Tom Tomastik to inspect well site.
 
| On site with Tom Tomastik to inspect well site.
  
 
Note: Dike area needs fresh water pumped out of dike to allow for volume in the event of tank failure.
 
Note: Dike area needs fresh water pumped out of dike to allow for volume in the event of tank failure.
|
+
|  
|
+
|  
|
+
|  
 
|-
 
|-
 
|}
 
|}
 +
For data sources see<ref>{{cite web
 +
| title = Ohio Department of Natural Resources RBDMS
 +
| publisher = [http://oilandgas.ohiodnr.gov/]
 +
| date = 2015-06-19
 +
| url = http://wellwiki.org/wiki/Ohio_Oil_and_Gas_Data_Sources#Inspection
 +
| accessdate = 2015-06-20 }}</ref>
 +
== References ==
 +
{{reflist}}
 
__NOEDITSECTION__
 
__NOEDITSECTION__
 
[[Category:Wells]]
 
[[Category:Wells]]

Revision as of 23:36, 14 July 2015

Well Details

Well ID: 34-059-24067
Loading map...
County: Guernsey
Municipality:
Operator Name: HILL DAVID R INC
Well Pad ID:
Farm/Lease Name:
First Permit Date:
Last Permit Date:
Spud Date: 2008-02-26
Unconventional: No
Configuration: Vertical
Well Status: Active Injection
Violations: 0
Latitude: 39.94127763
Longitude: -81.67398116

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION COMMENT
-1028964582 2012-11-09 Inspection revealed that Sweeny Well Service on site to apply pressure to annulus of tubing, they applied 425 psi and we monitored pressure for 15 minutes with no decline in pressure TEST PASSED, injection pump was not in operation during my inspection.
1031046280 2014-03-07 Inspection revealed that injection pump was in operation and it was noted that three Buckeye Water Service vacuum trucks were unloading at facility during my inspection.
-1047151489 2008-04-22 CHIPCO DRILLING OUT DV TOOLS IN BOTTOM HOLE 7138'
1048507788 2008-08-07 SWIW STARTING TO CONSTRUCT DIKE WALLS. PILING UP AND COMPACTING DIRT AS CONTRACTOR GOES UP WITH DIKE WALL.
-1090017095 2010-06-25 Inspection revealed that injection pump not in operation today due to fact of Sweeny Well Service performing mini test on annulus of tubing 350psi was applied to annulus and pressure monitored for 15 min with no decline in pressure.
-1106162492 2008-03-06 KILBARGER DRILLING RIG#17 DRILLING BOTTOM RR 7683. NOTHING DRILLING AHEAD.
-1108372922 2013-04-08 Inspection revealed that injection pump was not in operation during my inspection and I walked flow line area to monitor area for leaks, none were found.
1130921095 2014-04-01 I am accompanying inspector Dave Ball. My inspection finds the well is operating at a tubing pressure of 1300 psi and an annular pressure of 375 psi.
1163408779 2012-09-26 On site to witness cleaning of storage tanks by BOS Fluid Systems and Zemba Brothers had super sucker truck on site to remove solids from storage tanks.
-1173282118 2009-01-30 WELL IN OPERATION TODAY. WELL IS STILL ON VACUUM. LARGE AMOUNT OF PIT WATER INJECTED DOWN HOLE FOR THE LAST SEVERAL WEEKS AND INJECTION PRESSURE WENT TO 1000#. AFTER PIT WATER WAS INJECTED DOWN, PRESSURE DROPPED OFF TO 640# AND WENT ON VACUUM AGAIN.
1192305701 2013-03-27 Inspection revealed that injection pump was not in operation during my inspection and it was noted that three Buckeye Water Services vacuum trucks were unloading at facility during my inspection.
1204047975 2008-02-26 KILBARGER RIG#17. MOVING ON RIGGING UP.
1204149418 2008-02-27 KILBARGER RIG#17. DRILLING AT 500'
1204296794 2008-02-29 KILBARGER DRILLING RIG #17. DRILLING AT 2117'. SHALE
1204646406 2008-03-03 KILBARGER DRILLING #17. DRILLING AT 5252'
1204753145 2008-03-05 KILBARGER DRILLING #17. DRILLING AT 7057'. SHOULD DRILL IN LATER ON TONOTE.
1204754321 2008-03-04 KILBARGER DRILLING#17, DRILING AT 6133'
1204831407 2008-03-05 KILBARGER DRILLING. DRILL IN BEEKMANTOWN 7326' 236U NO FLARE. DRILLING AHEAD
1205930001 2008-03-17 KILBARGER DRILLING#17,SCHLUMBERGER SIDEWALL CORES BEING CUT. TD WELL AT 8934'
1209676502 2008-05-01 CHIPCO RIG ON HOLE. GOT TO BOTTOM 8900' CIRCULATING HOLE TO SURFACE. TO SPOT ACID TOMORROW.
1209989261 2008-05-02 PSC SPOT 2000 GAL. ACID ACROSS LOWER ZONES. WELL WENT ON VACUUM IMMEDIATELY
1215329563 2013-03-01 Inspection revealed that injection pump was not in operation today, and it was noted that tank area was free of water and unloading pad was fairly clean and neat.
1217518288 2008-07-31 SWIW CONSTRUCTION HAS STARTED. ESI IS THE CONTRACTOR DOING THE WORK. LEVELING GROUD OUT FOR DIKE AREA AND COMPACTING SOIL AS LEVELING PROCESS IS TAKING PLACE. JEFF KRAEGER IS CONTACT PERSON.
1217965392 2008-08-05 CONSTRUCTION CONTINUES ON DIKE AREA OF SWIW. LINER LAID DOWN. 8 SCEENINGS LAID OUT ON LINER. 500T OF #2 STONE BEING SPREAD ON TOP OF SCREENINGS. WORK TO CONTINUE EVERY DAY ON THIS PROJECR UNTIL COMPLETED.
1218549132 2008-08-11 SWIW CONSTRUCTION. BLOWING 7 SAND ON INSIDE OF DIKE WITH SAND SLINGER. DISCUSSED WITH JEFF KRAEGETHE LAYING IN OF THE LINERS. 2-20 MIL.
1219991800 2009-11-30 On site to witness testing of annulas of casing,Sweeny Well Service pressured up to 350 psi and monitored pressure no decline in pressure,noted that pump was in operation during my inspection.

Note: 344,611 bbl of water disposed of as of this date.

1223312286 2008-10-06 STILL WORKING ON FACILITY. LOADING WATER INTO TANKS. WORKING ON PUMP AND FILTER SYSTEM.
1223400995 2008-10-07 LOADING WATER INTO TANKS. WORKING ON DIRT OUTSIDE DIKE AREA. WORKING ON PUMP,FILTER SYSTEM.
1223565811 2008-10-09 WELL IS UP AND RUNNING. 1658 BBLS. PUT AWAY SO FAR.
1224160681 2008-10-15 WELL IS STILLIN OPERATION. INJECTION PRESSURE TODAY WAS 285#. 3 TRUCKS ON UNLOADING PAD. WELL IS GETTING A LOT OF WATER IN. 5387 BBL. OF WATER HAS BEEN PUT AWAY SO FAR.
1225122800 2008-10-27 WELL IS IN OPERATION. 10,000 BBL. SO FAR TO DATE
1226685814 2008-11-14 WELL MIS UP AND RUNNING. JOHN GOMBEDA AND DONALD KREIGER ON LOCATION TO DISCUSS X-TRA STORAGE TANKS COMPANY IS PLANNING TO INSTALL AT FACILITY. NO VIOLATIONS NOTED THIS INSPECTION. 20981 BBLS. PUT AWAY SO FAR.
-1227475767 2014-01-17 Inspection revealed that injection pump was in operation today and it was noted that one Buckeye Water Service vacuum truck was unloading at facility during my inspection.
1227530733 2008-09-22 FILLING TANKS WITH BRINE TO TEST FOR LEAKS.
1230731256 2008-12-31 51000 BBLS. WATER INJECTED DOWN SO FAR. NO VIOLATIONS NOTED THIS INSPECTION.
1231526299 2009-01-09 WELL IS IN OPERATION. GAUGING TANKS FOR FILL UP FROM PIT WATER. PLAN TO CLEAN OUT TANKS. 57071 BBLS. WATER PUT DOWN HOLE.
1237191881 2011-05-27 Inspection revealed that well is in operation and Sweeny Well Service was on site to perform mini test on annulus of tubing today they pressured up to 300 psi and we monitored pressure for 15 min with no decline in pressure.

Note: 788,900 bbl of water disposed of since well went into operation.

1249080080 2009-07-31 On site to witness mini test of annulus of tubing, Sweeny Well Services pressured up to 300 psi on annulus and I monitored pressure for 15 min with no decline in pressure(TEST PASSED),injection pump was not in operation during testing procedure.
1252150772 2009-09-04 On site to witness mini test on annulus of tubing Sweeny Well Service pressured up to 350 psi and we monitored pressure for 15 min with no decline in pressure(TEST PASSED) injection pump was not in operation during my inspection.

Note: Better vegetation needs to be established in area of wellhead.

1253308247 2009-09-18 Inspection revealed that well is in operation, pump was running on the day of my inspection.

Talked to well tender about getting vegetation established in area of wellhead and he stated that he would contact supervisor and let them be aware of inspectors concerns.

1255186234 2009-10-10 On site to witness rig crew release packer and pull tubing,unable to do so today due to fact that well is flowing back,owner will attempt swapping out tubing tomorrow if well quits flowing.
1255511206 2009-10-13 On site to witness Berry Well Service run new packer assembly and new 2.875 tubing back into well and set packer@7151' and flush annulus of tubing with fresh water and anhibitor and pressure test,tested at 1700 psi for 15 min with no decline in pressure(TEST PASSED),will check back at later date for compliance of restoration work in area of working pit.
1257285422 2009-11-03 Inspection revealed that well is in operation,pump was running during my inspection.

Note:Area where recent compleation worktook place has been graded and seed and mulch applied waiting on vegatation to be established. 385,485 bbl disposed of since well went into operation.

1262205710 2009-12-30 On site to witness operator apply pressure to annulas of tubing,Sweeny Well Service applied 360 psi. monitored pressure for 15 min with no decline in pressure(TEST PASSED).
1264878580 2010-01-29 On site to witness mini test on annulas of tubing Sweeny Well Service pressured up to 350 psi and I monitored pressure for 15 min with no decline in pressure.Test Passed
1268494420 2010-03-13 Inspection revealed Producers Services preformed acid treatment on well they pumped 2000 gal of acid into injection zone@1.3 bbl per min and displaced it with 50 bbl fresh water and then well was shut in too let acid soak on injection zone,owner will resume operation on 3/15/10.
1273011323 2010-05-03 Inspection revealed that restoration work at site is satisfactory pit has been filled in and site restored and vegetation has been established.
1276720394 2010-06-15 Inspection revealed that injection pump was not in operation during my inspection.

Note 492,274 bbl of water has been put away since well went into operation.

-127854275 2015-02-11 Inspection revealed that injection pump was in operation today and it was noted that Buckeye Water Services had one truck on the unloading pad during my inspection.
1280607690 2010-07-29 Inspection revealed that well was not in operation during my inspection, on site to witness mini test preformed on annulus of tubing Sweeny Well Service pressured up on backside of tubing too 350 psi and we monitored pressure for 15 min with no decline in pressure(TEST PASSED).
1283213220 2010-08-30 On site to witness mini test on annulus of tubing Sweeny Well Service pressured up to 350 psi and we monitored pressure for 15 min with no decline in pressure.
1285699907 2010-09-28 On site to witness mini test preformed on annulus of tubing Sweeny Well Service pressured up to 380 psi and we monitored pressure for 15 min with no decline in pressure(TEST PASSED),injection pump was shut down prior too testing and resumed operation following testing.
1288381186 2010-10-29 On site to witness mini test on annulus of tubing Sweeny Well Service pressured up to 370 psi and we monitored pressure for 15 min with no decline in pressure TEST PASSED. Injection pump was in operation during my inspection.

Note: 600,648 bbl has been disposed of since well went into operation.

1296163532 2011-01-26 On site to witness mini test on annulus of tubing Sweeny Well Service pressured up to 350 psi and we monitored pressure for 15 min with no decline in pressure.

Note: 652,798 bbl of water has been disposed of since well went into operation.

1299194767 2011-02-28 On site to witness mini test of annulus pressure being applied by Sweeny Well Service they applied 350 #pressure and we monitired pressure for 15 min. with no decline in pressure,injection pump was in operation during my inspection.

Note: 676,050 bbl of water disposed of since well went into operation.

1301341808 2011-03-28 Inspection revealed that pump was in operation today.

Note: 711,681 bbl disposed of since well went into operation.

1301690913 2011-03-31 On site to witness mini test of annulus of tubing Sweeny Well Service pressured up to 370 psi and we monitored pressure for 15 min with no decline in pressure.

Note: Held mini meeting with well operator to discuss better ventilation in pump house area and also discussed possible hazards in unloading area while trucks were unloading water.

1303503994 2011-04-21 Inspection revealed that pump was in operation during my inspection and 3 Buckeye Water Service vac trucks were unloading at facility during my inspection.

Note: 742,116 BBL has been pumped down well since it went into operation.

1303854655 2011-04-26 On site to witness Baker Crane Rental place four new 210 bbl tanks within dike area and company personnel plumbed them up and placed tanks into service.

Note: Injection pump was not in operation today due to fact that additional storage tanks were being placed within dike area.

1304501446 2011-05-03 Inspection revealed that injection pump was in operation during my inspection and Corp Well Services vac truck was unloading at facility and H&L Water Services was also unloading at facility.

Note:755,730 bbl of water has been disposed of since well went into operation.

1305807687 2011-05-18 Accompanied Dave Ball with Josh Garland on inspection.
1307726668 2011-05-18 accompanied D. Ball on inspection.
1308608527 2011-06-20 On site to witness acid job preformed on well Producers Services pumped 2000 gal of 15% acid down tubing and displaced with 2100 gal of fresh water and shut well in and they will resume operations later today.
1309477850 2011-06-30 On site to witness Sweeny Well Service perform mini test on annulus of tubing they pressured up on tubing to 350# and we monitored pressure for 15 minutes with no decline in pressure and it was noted that Corp Oilfield Services vac truck was unloading at facility during my inspection.
1309906052 2011-07-05 Inspection revealed that well is in operation and injection pump was running during my inspection,noted that storage tanks have been repainted since my last inspection and operator pumped 48,554 bbl of water down well last month and total bbl since well went into operation is 844,122.
1317415950 2011-09-30 On site to witness Sweeny Well Service apply pressure to annulus of tubing to check integrity of production casing they applied 350 psi and we monitored it for 15 minutes with no decline in pressure.
1317936118 FLOW LINE TESTED AND PASSED. 1500#
1319490541 2011-10-24 Inspection revealed that injection pump was in operation today and new building addition has been completed. Awaiting delivery of new pump, filter housing and 4 additional storage tanks.

Note: 1,017,537 bbls of water have been disposed of in this well since it went into operation.

1326650773 2012-01-14 On site to witness acid job being performed on injection well,Producers Services pumped 2000 gallon of 15% acid down well at a average pressure of 1388 psi and ISIP was 1170 psi and and 5 min pressure was noted at 1136 psi.
1328227950 2012-01-31 Company rep called and stated that he thought well was equalizing pressure wants inspector to check pressures upon checking it was determined that tubing possibly has hole in it instructed operator to shut well down and acquire service rig to pull tubing.
1328745064 2012-02-04 On site to witness running and testing of tubing and annulus of tubing, Producers Services pumped fluid on annulus and we did preliminary testing on integrity will perform official testing on Monday.
1333409395 2012-03-30 Inspected site and found well in operation and Sweeny Well Service pressure tested annulus of tubing to 300 psi and we monitored pressure for 15 min with no decline in pressure.

1,206,439 bbl disposed of since well went into operation.

1338420324 2012-05-30 Inspection revealed that injection pump was not in operation during my inspection and it was noted that there was two Whip stock Vac trucks unloading at facility during my inspection.

Note: 1,250,198 bbls of brine has been disposed of since well went into operation.

1344706418 2012-08-06 Inspection revealed that injection pump was not in operation during my inspection, company rep on site having discussion with contractor concerning cleaning out of storage tanks and hauling off of material to a approved landfill.

Note: 1,304,489 bbl has been disposed of since well went into operation.

1351807474 2012-10-31 Inspection revealed that injection pump was in operation during my inspection and it was noted that annulus pressure was at zero and I suggested to operator that they have pressure applied to annulus as soon as possible.

Note: 1,381,345 bbl has been disposed of since well went into operation.

1354985066 2012-12-06 Inspection revealed that injection pump was not in operation during my inspection and it was noted that packing on #2 cylinder was leaking and after talking to operator stating new packing was ordered and once received they would replace it.
1356101681 2012-12-18 Inspection revealed that injection pump was in operation and facility appears to be in satisfactory condition this inspection.

Note: 1,437,612 bbl of water has been disposed of since well went into operation.

1370041671 2013-05-30 Inspection revealed that injection pump was in operation during my inspection and it was noted that Huey Trucking was unloading at facility during my inspection.
1374262183 2013-07-19 Inspection revealed that injection pump was in operation today and it was noted that one H&L Water Haulers tanker was unloading at site during my inspection.
1378361201 2012-06-25 Inspection revealed that injection pump was not in operation during my inspection, noted that cameras have been installed at well head to help monitor area and well head in the event of flow line failure and possible vandalizing.
1385881391 2010-12-29 On site along with supervisor to witness mini test preformed on annulus of tubing,Swenny Well Service pressured up to 350 psi and we monitored pressure for 15 min with no decline in pressure.

Note: 636,748 bbl of water disposed of since well went into operation.

1386357870 2013-12-05 Inspection revealed that injection pump was in operation today and it was noted that one Buckeye Water Services vacuum truck was unloading at site during my inspection.
1392248814 2014-02-11 Inspection revealed that injection pump was in operation during my inspection.

Note: Walked flow line area to monitor area for any potential leaks none were found on this day of my inspection.

1409350368 2014-08-29 On site to perform mini test on annulus of tubing after changing out 2 valve on well head,Swenny Well Service pressured up on the annulus of tubing for well owner.(Test Passed)
1412896037 2014-10-07 Inspection revealed that injection pump was in operation during my inspection and it was noted that one Corp Oilfield Services vacuum truck was unloading at the facility during my inspection.
1415227673 2014-11-04 Inspection revealed that injection pump was just started prior to my inspection and it was noted that two Buckeye Water Service vacuum trucks were unloading at the facility during my inspection.
1419032355 2014-12-19 Inspection revealed that injection pump was not in operation during my inspection and it was noted that containment area was free of any fluids and proper identification is posted.
1428829301 2015-04-11 Producers Services on site to perform 2000 gal acid treatment on said well.
1446820158 2010-12-06 On site to witness mini test preformed on annulus to tubing Sweeny Well Serviced pressured up to 350 psi and we monitored pressure for 15 min with no decline in pressure,

Note: Injection pump was in operation during my inspection and there was one vac truck unloading at facility during inspection(Corp Oilfield Services).

146897399 2008-10-03 WORKING ON TANK VALVES. CHANGING LEAKING FITTINGS.
-1478919296 2009-02-24 SWIW INSPECTED. UNLOADING PAD AND FACILITY IN GOOD REPAIR. NO VIOLATIONS NOTED.
-1491684624 2010-03-01 On site to witness mini test on annulas of tubing Sweeny Well Service pressured up to 360 psi and we monitored pressure for 15 min with no decline in pressure(TEST PASSED) and injection pump was in operation during my inspection.

Note: 390,595 bbl of water has been injected since well went into operation.

-1493195847 2010-11-24 Inspection revealed that well was not in operation during my inspection,well operator was in process of changing filters in pumphouse and was planning on placing well into operation after mainitence work was completed.

Note: 613,574 bbl disposed of since well went into service.

1498563657 2012-02-06 On site to conduct official testing of integrity of casing and pump fresh water and inhibitor to annulus of tubing, Producer services arrived on site and Baker Packer hand uncoupled from tubing and we flushed annulus of tubing with inhibitor and then they coupled back on tubing and we pressured tested at 1787 psi and monitored pressure for 15 minutes with no decline in pressures.
-150070169 2008-08-19 SWIW TOP SOIL BEING SPREAD ON BOTTOM OF LINER ON OUTSIDE OF DIKE AREA. PLUMBING STILL BEING HOOKED UP TO OVERFLOW VAULT ON OUTSIDE OF UNLOADING PAD.
-1514378127 2015-04-08 Inspection revealed that injection pump was in operation during my inspection.
1519543692 2012-05-14 Inspection revealed that injection pump was in operation during my inspection.

Note: Restoration work at site has been completed pits have been closed and site restored and vegetation has been established.

-155224430 2008-08-18 SETTING IN 2400 GAL CEMENT VAULT FOR PAD DRAIN. PLUMB IN VAULT.
-1559212810 2010-01-20 Inspection revealed that injection pump was in operation during my inspection.

Note: Dow Cameron vac truck unloading at site during my inspection,370,656 bbl water put away since well went into operation.

-1559431971 2012-02-02 On site to witness Baker Oil Tool employee unhook tubing from packer and pull tubing trying to find hole in it we located hole and decision was made to get new string of tubing and run it back in hole tomorrow.
-1560256822 2008-05-05 APPALACHIAN WELL SURVEY'S RUN CEMENT BOND LOG ON HOLE.
-1563713596 2015-01-23 Inspection revealed that injection pump was not in operation during my inspection.
1572863734 2012-10-22 Inspection revealed that injection pump was in operation during my inspection and it was noted that annulus pressure has reached zero and it is requested that you have positive pressure applied to annulus of tubing in the near future.

Note: 1,365,368 barrel of water has been disposed of since well went into operation.

-1618534015 2015-03-27 On site along with company rep to witness mini pressure test on annulus of tubing Sweeny Well Service pressured up annulus to 700 psi and we monitored pressure for 15 minutes with no decline in pressure.
1627477762 2013-10-15 Inspection revealed that injection pump was in operation during my inspection and it was noted that injection pump gear end is in need of repair.
1629049053 2009-12-24 Inspection revealed that well is not in operation today,well tender stated that not much water coming in today due to holiday.

Note: Stone is needed around facility to help cut down on tracking mud out onto county road.

1647132619 2012-03-05 Inspection revealed that injection pump is down for repair one of the pistons has become in operable and repair personnel were to arrive tomorrow to repair pump.

Note: Stone has been applied to driveway and some has been placed in tank area.

1,181,072 bbl disposed of since well went into operation.

1650684974 2011-07-28 On site to witness mini test of annulus of tubing Sweeny Well Serviced pressured up on backside of tubing to 340 psi and we monitored pressure for 15min with no pressure loss.

Note:885,540 bbl of water has went down well since it went into operation.

-1683725546 2012-02-04 On site to witness Chipco Well Services run tubing back into well and latch onto packer and perform pretesting of annulus we pressured up to 1800 psi and monitored pressure for 15 min. with no decline, will perform official test on Monday with Producers Services pump truck.
1684276670 2013-12-09 Sweeny Well Service on site to pressure test annulus of tubing they applied 600# of pressure and we monitored pressure for 15 minutes with no decline in pressure.
1686493466 2015-06-01 Inspection revealed that injection pump was not in operation during my inspection and it was noted that two Buckeye Water Services vacuum trucks were unloading at the facility on this day.
1687005480 2012-02-29 Inspection revealed that injection pump was in operation during my inspection.

Note: Area of pit site is in need of restoration work performed as weather permits.

-1690178081 2014-07-15 Inspection revealed that injection pump was in operation today and it was noted that one Buckeye Water Service vacuum truck was unloading at facility during my inspection.
1728540131 2008-09-22 G AND L DRILLING AT 3450'
1739801852 2013-11-04 On site to witness Sweeny Well Service apply 350# of pressure to annulus of tubing and we monitored pressure for 15 minutes with no decline in pressure.
-1748823651 2008-08-12 LAYING IN OF 2-20 MIL LINERS ON INSIDE OF DIKE.
1781373611 2009-06-29 Witnessed monthly annular pressure test. Annulus was pressured up to 300 psig and held for 15minutes. Test passed.
1824132536 2009-04-29 Inspection revealed that well was in operation during my inspection, pump was running injection pressure was 950 psi and there was two vac trucks unloading at facility during my inspection(GR-Contracting and Kodiak Water Services) facility is a very well kept !
18261165 2013-11-12 Inspection revealed that injection pump was in operation today and it was noted that one Buckeye Water Service vacuum truck was unloading at facility during my inspection.
-1849592333 2009-04-29 Restoration work at site satisfactory,pit has been filled in and site restored and vegetation has been established site is currently being used for a active Salt Water Injection Facility.
1947254021 2010-08-27 Inspection revealed that injection pump was in operation during my inspection and operator stated that they were planning on performing mini test on annulus of tubing in the near future.

Note: 560,651 bbl of water has been disposed of since well went into operation.

-197109858 2012-08-21 On site with UIC Director and group from Central Office to inspect well site and surface facility and discuss any issues with well operator concerning facility.
-1999546532 2008-04-28 CHIPCO DRILLING OUT FORMATION PACKER
-200516364 2012-04-25 Inspection revealed that well was in operation on this day, well caretaker was changing filters during my inspection and it was noted that Buckeye Water Services was unloading tanker truck at site.
2025559258 2010-02-11 Inspection revealed that injection pump was not in operation during my inspection, noted that 2 Buckeye Water Service vac trucks were unloading at facility during my inspection.

Note: 381,321 bbl of brine disposed of as of this date according to barrel counter installed at site.

2034477575 2008-09-03 COSTRUCTION STILL CONTINUES ON SURFACE FACILITY
-2039009496 2011-09-07 Inspection revealed that injection pump was in operation during my inspection and there was three vacuum trucks unloading at facility also, walked flow line area to monitor for potential leaks(none found) facility was in good repair this inspection.

Note: 941,746 bbl of water has been disposed of since well went into operation.

206707138 2011-09-22 Well is in operation with pump running at 85% capacity @1550 PSI. There were several brine trucks at facility during my inspection.

Note: Owner is expanding pump house facility to accommodate additional pump once new well is drilled and it passes all required testing for a injection facility. There has been 966,810 bbl of brine disposed of since this disposal well went into operation.

-2068245965 2008-04-17 DRILLED TO 8500' FOR PURPOSE OF INJECTION WELL. DRILLING OUT DV TOOLS IN 5.5
-2076879871 2008-10-02 SALT WATER INJECTION WELL
-2090380607 2008-11-03 WELL IS IN OPERATION. NO VIOLATIONS NOTED.
2120462086 2012-04-17 RESTORATION WORK AT SITE SATISFACTORY.
-223578216 2013-01-17 On site with company personnel Don Krieger and John Suhar to review injection well monitoring charts to try and determine if there is a possibility of leakage in tubing or packer after reviewing data it was determined that annulus pressure increase was due to thermal expansion to down hole fluid when well is not in operation.
-225951818 2008-04-21 CHIPCO DRILLING OUT DV TOOL. WILL HAVE TO TRIP FOR BIT. JOHN SUHAR WILL TAKE PERMIT APPLICATION TO COLUMBUS TODAY.
-284590190 2014-06-03 Inspection revealed that injection pump was in operation today and it was noted that one H&L Water Service vacuum truck was unloading at this facility on the day of my inspection.
315114216 2008-09-23 STILL FILLING TANKS TO CHECK FOR LEAKS
326126134 2013-01-30 Inspection revealed that injection pump was not running during my inspection and it was noted that brine filter skid has one chamber in need of replacement, talked to well operator and he stated that they have one ordered and it should be replaced by the end of the week.
-341072783 2014-04-15 Inspection revealed that injection pump was in operation during my inspection and it was noted that two H&L Water vacuum trucks were unloading at facility during my inspection.
361163417 2011-12-12 During my inspection the injection pump was in operation and Buckeye Water Services was unloading.

Note: 1,089,357 bbl of water has been disposed of in this well since it went into operation.

-364566513 2012-04-17 Inspection revealed that injection pump was not in operation during my inspection and facility appeared to be in satisfactory condition this inspection.

Note: 1,218,997 bbl of brine disposed of since well went into operation.

367888702 2008-03-09 LOST CIRCULATION. MIX MUD. WEIGHT UP TO 9.7#. RE-ESTABLISH CIRCULATION. BACK TO DRILLING.8057'.
449971104 2010-05-03 On site at request of company rep too witness mini test on annulus of tubing Swenney Well Service pressured up on backside of tubing too 380 psi and we monitored pressure for 15 minutes with no decline in pressure .

Note: Pump was in operation during my inspection and 446,253 bbl of water has been disposed of as of this date.

483461478 2010-04-01 On site to witness mini testing of annulus of tubing Sweeney Well Service preformed testing, and pump was in operation during my inspection.

Note: 417,874 bbl of water disposed of as of this date since well went into operation.

-538164671 2013-06-27 Inspection revealed that injection pump was in operation today and it was noted that two Buckeye Water Services vacuum trucks were unloading at site during my inspection.
571328866 2014-05-09 Inspection revealed that injection pump was in operation during my inspection and it was noted that one H&L Water Services vacuum truck was unloading at facility during my inspection.
-575310412 2015-03-06 Inspection revealed that injection pump was in operation today and it was noted that one Buckeye Water Services vacuum truck and one H&L Water Services truck was unloading at the facility during my inspection.

Note: Walked flow line area to monitor area for leaks none were detected.

-577842201 2008-03-10 KILBARGER DRILLING#17. DRILLING ON MUD. LOST CIRCULATION 2 TIMES IN 24 HRS. DRILLING AT 8157'
586743487 2011-03-15 Inspection revealed that well is in operation and pump was running during my inspection.

Note: 698,485 bbl disposed of since well went into operation, also noted that owner has applied stone around facility since my last inspection.

-593575519 2012-09-24 BOS Fluids system on site to clean out storage tanks at facility will monitor progress on getting tanks cleaned and wells back into operation.
604208533 2014-08-18 Inspection revealed that injection pump was in operation during my inspection.
619212723 2010-07-15 Inspection revealed that pump was not in operation during my inspection,caretaker was cleaning unloading pad during my inspection.

Note: 524,666 bbl have been disposed of since well went into operation.

-645681029 2014-04-01 Inspection revealed that injection pump was in operation today and it was noted that one Buckeye Water Service vacuum truck was unloading at facility during my inspection.
649254192 2013-05-01 Inspection revealed that injection pump was not in operation during my inspection and it was noted that one Buckeye Water Service vacuum truck was unloading at facility during my inspection,
679440780 2008-12-02 INJECTING PIT WATER TODAY. PUMP PRESSURE IS ELEVATED SOME. NO VIOLATIONS NOTED DURING THIS INSPECTION.
-683119350 2009-11-16 Inspection revealed that injection pump ws not in operation during my inspection,noted that seed and mulch has been applied to area around wellhead to help bind soil and prevent erosion issues at site.
-721787425 2011-08-09 Inspection revealed that pump was in operation during my inspection and there was two vac trucks unloading at site during my inspection.

Noted that dirt has been put in place around vault area and seed and mulch has been applied to area.

736907431 2008-03-17 RUN AND CEMENT 5.5 INJECTION WELL.7218' 5.5 286 SX HALLIBURTON TO 6000'. 2 STAGE TOOL RUN IN. WAIT 6 HRS. PUMP 500SX. 6000'- 3300' 500 SX.
-738690761 2011-11-22 Inspection revealed that pump was in operation and there ws several vaccum trucks waiting to unload at facility. Note: 1,063,645 bbl of water has been disposed of since well went into operation.
-804412253 2012-12-06 Restoration work at site satisfactory pit has been filled and site has vegetation established.
-819557891 2010-05-25 On site to witness mini test on annulus of tubing,Swenny Well Service pressured up to 350 psi and well monitored pressure for 15 min. with no decline in pressure, injection pump was not in operation during my inspection.
-822745846 2010-09-09 Inspection revealed that injection pump was in operation during my inspection.

Note: 567574 bbl of water disposed of since well went into operation.

861229868 2013-08-19 Inspection revealed that injection pump was in operation during my inspection.
956093730 2011-05-19 On site with Tom Tomastik to inspect well site.

Note: Dike area needs fresh water pumped out of dike to allow for volume in the event of tank failure.

For data sources see[1]

References

  1. "Ohio Department of Natural Resources RBDMS". [1]. 2015-06-19. Retrieved 2015-06-20.