Line 11: Line 11:
 
| County: [[Richland_County,_Ohio|Richland]]
 
| County: [[Richland_County,_Ohio|Richland]]
 
|-
 
|-
| Municipality: [[Jefferson_Township,_Richland_County,_Ohio|Jefferson Township]]
+
| Municipality: [[Jefferson Township,_Richland_County,_Ohio|Jefferson Township]]
 
|-
 
|-
 
| Operator Name: [[BI JOE DEVELOPMENT INC]]
 
| Operator Name: [[BI JOE DEVELOPMENT INC]]

Revision as of 12:18, 12 August 2019

Well Details

Well ID: 34-139-20762
Loading map...
Country: United States
State: Ohio
County: Richland
Municipality: Jefferson Township
Operator Name: BI JOE DEVELOPMENT INC
Well Pad ID:
Farm/Lease Name: GINGERICH UNIT
License Status: Producing
License Date: 2013-04-29
Spud Date: 2013-06-13
Spud Drilling Contractor: MARIC DRILLING CO.
Final Drill Date: 2013-06-22
Well Total Depth: 4455 ft
Configuration: Vertical
Latitude: 40.587122540
Longitude: -82.56256008

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2013-04-29 Proposed Formations:CLINTON THROUGH TREMPEALEAU, Issued Date:4/29/2013, Expired Date:4/29/2015 12:00:00 PM, Drilling unit acres:50.523, Proposed Well Type:OG, Proposed Well Class:EW
Reached Total Depth 2013-06-22
Completion Report Received 2013-10-09
Construction Permit Expires 2015-04-29
Record Last Modified 2017-02-15

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2013-10-09 4354 4408 28

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
2013-06-28 ACID 15 3150 Gal 0 Producers Service Corporation The well was treated with Hydrochloric acid. ODNR was notified and the job was witnessed. Fluid was recovered into a portable tank on site. Columbus permitting geologists were also on site to observe the job.

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
0 0 0
2013 BI JOE DEVELOPMENT INC 83 77 153
2014 BI JOE DEVELOPMENT INC 316 155 153
2015 BI JOE DEVELOPMENT INC 126 79 153
2016 BI JOE DEVELOPMENT INC 81 81 365
2017 BI JOE DEVELOPMENT INC 74 0 365
2018 BI JOE DEVELOPMENT INC 65 69 365

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2013 BI JOE DEVELOPMENT INC Brine 70 153
2014 BI JOE DEVELOPMENT INC Brine 240 153
2015 BI JOE DEVELOPMENT INC Brine 140 153
2016 BI JOE DEVELOPMENT INC Brine 200 365
2017 BI JOE DEVELOPMENT INC Brine 180 365
2018 BI JOE DEVELOPMENT INC Brine 155 365

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
0513746705 2013-06-14 Drill / Deepen / Reopen No Violations Inspect drill location. Drill 11 inch surface casing hole to 860 feet, set 798 feet measured from grade of 8.625 inch new 23 pound casing. four centralizers set every 5 to 6 joints, total 19 joints of pipe. Cement with 172 sacks of cement with loss circulation material. Good returns.
0553084684 2019-05-29 Production Wells No Violations Identification is posted and no observed violations at the time of this inspection.
0658163127 2014-07-02 Production Wells No Violations The site is 100% vegetated except for the lease road. The road is stable, no erosion. ID posted at the tanks. The well is equipped with a pump jack, rods and tubing and is in production.
0692241112 2013-06-28 Drill / Deepen / Reopen No Violations Request by the well owner to witness acid treatment job on the well. Producers Service Co. supplied and pumped hydrochloric acid. Bakerwell service rig is on site.
0838086997 2013-06-26 Drill / Deepen / Reopen No Violations Operator advised they would be solidifying and closing pits. Baked lime powder was mixed in to the mud and cuttings in the pits. 2 loads of water were hauled out of pits. Water was pumped down to the level of the mud and an excavator was used to mix in lime. The operator was also grading the site around the well.
0861772080 2013-06-11 Drill / Deepen / Reopen No Violations Maric drilling is grading the site. The rig is expeced in 1 to 2 days.
1371666902 2013-06-19 Drill / Deepen / Reopen No Violations Drilling is at 3070 feet. Drilling on fluid. The driller expects to reach TD on Saturday.
1372886265 2013-07-03 Preliminary Restoration No Violations The site needs to be finish graded. The well has been equipped with a pump jack, rods and tubing. The pumper was on location and the well was being pumped into a portable tank.
1374076613 2013-07-17 Preliminary Restoration No Violations R&B and Bakerwell were on site. Baker was setting tanks and working on the dike area. R&B was grading topsoil on the disturbed area.
1376501911 2013-08-14 Preliminary Restoration No Violations The disturbed area has been seeded and vegetation is established. Tanks are 55 ft from the roadway and 102 feet from the well. Fencing has been placed around the well and tank battery. Gates have been installed on the lease road. ID needs to be posted at the tank battery. Preliminary restoration is approved.
1522345367 2018-03-29 Production Wells No Violations The well is equipped with a pump jack, rods and tubing and is in production. There are 2-100 barrel tanks and a separator in the tank battery. ID is posted at the tanks.
1549996662 2019-02-12 Production Wells No Violations Identification is posted and no observed violations at the time of this inspection
1603847770 2013-06-24 Drill / Deepen / Reopen No Violations Production casing was cemented over the weeekend. Drilling is completed. The rig is being moved out. The pits are going to be solidified and the operator is planning to acidize the well.