Difference between revisions of "37-115-20395"

m
m
Line 3: Line 3:
 
{| class="wikitable welldetails" width="95%"
 
{| class="wikitable welldetails" width="95%"
 
| Well ID: 37-115-20395
 
| Well ID: 37-115-20395
| style="height=100%; align=center" rowspan="15" | {{#display_map: 41.88395, -75.992386 | width=100% | height=100% }}  
+
| style="height=100%; align=center" rowspan="14" | {{#display_map: 41.883950, -75.992386 | width=100% | height=100% }}
 
|-
 
|-
| County: [[Susquehanna County, Pennsylvania|Susquehanna]]
+
| Country: United States
 
|-
 
|-
| Municipality: [[Forest Lake Township, Susquehanna County, Pennsylvania|Forest Lake Township]]
+
| State: Pennsylvania
 +
|-
 +
| County: [[Susquehanna_County,_Pennsylvania|Susquehanna]]
 +
|-
 +
| Municipality: [[Forest Lake Township,_Susquehanna_County,_Pennsylvania|Forest Lake Township]]
 
|-
 
|-
 
| Operator Name: [[CARRIZO (MARCELLUS) LLC]]
 
| Operator Name: [[CARRIZO (MARCELLUS) LLC]]
Line 15: Line 19:
 
| Farm/Lease Name: BAKER 2H
 
| Farm/Lease Name: BAKER 2H
 
|-
 
|-
| First Permit Date: 2010-07-15
+
| License Status:  
|-
 
| Last Permit Date: 2010-07-15
 
 
|-
 
|-
 
| Spud Date:  
 
| Spud Date:  
 
|-
 
|-
| Unconventional: Yes
+
| Permit Date: 7/15/2010
 
|-
 
|-
| Horizontal: Yes
+
| Unconventional Well: Y
 
|-
 
|-
| Well Status: INACTIVE
+
| Configuration: Horizontal Well
 
|-
 
|-
| Violations: 0
+
| Latitude: 41.883950
|-
 
| Latitude: 41.88395
 
 
|-
 
|-
 
| Longitude: -75.992386
 
| Longitude: -75.992386
|-
 
 
|}
 
|}
 +
For data sources see<ref>{{cite web
 +
| title = Permits Issued Detail Report
 +
|publisher = [[Pennsylvania Department of Environmental Protection]]
 +
| date = 2019-05-20
 +
| url = http://wellwiki.org/wiki/Pennsylvania_Oil_and_Gas_Data_Sources
 +
| accessdate = 2019-05-21 }}</ref><ref>{{cite web
 +
| title = Spud Data Report
 +
|publisher = [[Pennsylvania Department of Environmental Protection]]
 +
| date = 2019-04-30
 +
| url = http://wellwiki.org/wiki/Pennsylvania_Oil_and_Gas_Data_Sources
 +
| accessdate = 2019-05-16 }}</ref><ref>{{cite web
 +
| title = Oil and Gas Well Pad Report
 +
|publisher = [[Pennsylvania Department of Environmental Protection]]
 +
| date = 2019-05-20
 +
| url = http://wellwiki.org/wiki/Pennsylvania_Oil_and_Gas_Data_Sources
 +
| accessdate = 2019-05-21 }}</ref>
 
== Production Data ==
 
== Production Data ==
 
{| class="wikitable sortable" width="95%"
 
{| class="wikitable sortable" width="95%"
!scope="col" | PERIOD
+
!scope="col" | Period
!scope="col" | GAS QUANTITY
+
!scope="col" | Operator Name
!scope="col" | GAS PRODUCTION DAYS
+
!scope="col" | Gas Quantity (mcf)
!scope="col" | CONDENSATE QUANTITY
+
!scope="col" | Gas Production Days
!scope="col" | CONDENSATE PRODUCTION DAYS
+
!scope="col" | Oil Quantity (bbl)
!scope="col" | OIL QUANTITY
+
!scope="col" | Oil Production Days
!scope="col" | OIL PRODUCTION DAYS
+
!scope="col" | Water Quantity (bbl)
|-
+
!scope="col" | Water Production Days
| 2010-3
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
|-
 
 
|-
 
|-
| 2010-2
+
| 2010
| style="text-align:right;" | 0.0
+
| [[CARRIZO (MARCELLUS) LLC]]
| style="text-align:right;" | 0.0
+
| style="text-align: right;" | 0.00
| style="text-align:right;" | 0.0
+
| style="text-align: right;" | 0
| style="text-align:right;" | 0.0
+
| style="text-align: right;" | 0.00
| style="text-align:right;" | 0.0
+
| style="text-align: right;" | 0
| style="text-align:right;" | 0.0
+
| style="text-align: right;" | 0.00
 +
| style="text-align: right;" | 0
 
|-
 
|-
|-
+
| 2011
| 2010-2
+
| [[CARRIZO (MARCELLUS) LLC]]
| style="text-align:right;" | 0.0
+
| style="text-align: right;" | 0.00
| style="text-align:right;" | 0.0
+
| style="text-align: right;" | 0
| style="text-align:right;" | 0.0
+
| style="text-align: right;" | 0.00
| style="text-align:right;" | 0.0
+
| style="text-align: right;" | 0
| style="text-align:right;" | 0.0
+
| style="text-align: right;" | 0.00
| style="text-align:right;" | 0.0
+
| style="text-align: right;" | 0
|-
 
|-
 
| 2011-1
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
| style="text-align:right;" | 0.0
 
 
|-
 
|-
 
|}
 
|}
 
For data sources see<ref>{{cite web
 
For data sources see<ref>{{cite web
  | title = Oil and Gas Historical Production Report
+
  | title =Oil and Gas Production Reports
| publisher = [[Pennsylvania Department of Environmental Protection]]
+
|publisher = [[Pennsylvania Department of Environmental Protection]]
| date = 2015-05-26
+
| date = 2019-03-31
  | url = http://wellwiki.org/wiki/Pennsylvania_Oil_and_Gas_Data_Sources#Production
+
  | url = http://wellwiki.org/wiki/Pennsylvania_Oil_and_Gas_Data_Sources
  | accessdate = 2015-05-27 }}</ref>
+
  | accessdate = 2019-05-21 }}</ref>
== Waste Data ==
+
<!--== Waste Data ==
 
{| class="wikitable sortable" width="95%"
 
{| class="wikitable sortable" width="95%"
!scope="col" | PERIOD
+
!scope="col" | Period
!scope="col" | TYPE
+
!scope="col" | Waste Type
!scope="col" | QUANTITY
+
!scope="col" | Quantity
!scope="col" | UNITS
+
!scope="col" | Disposal Method
!scope="col" | DISPOSAL METHOD
+
!scope="col" | Waste Facility ID
!scope="col" | WASTE FACILITY PERMIT ID
+
|-
!scope="col" | WASTE FACILITY NAME
+
|}-->
!scope="col" | FACILITY CITY
+
 
!scope="col" | FACILITY STATE
 
|}
 
For data sources see<ref>{{cite web
 
| title = Oil and Gas Historical Waste Report
 
| publisher = [[Pennsylvania Department of Environmental Protection]]
 
| date = 2015-05-26
 
| url = http://wellwiki.org/wiki/Pennsylvania_Oil_and_Gas_Data_Sources#Waste
 
| accessdate = 2015-05-26 }}</ref>
 
 
== Inspection Data ==
 
== Inspection Data ==
 +
==== Inspections Performed ====
 
{| class="wikitable sortable" width="95%"
 
{| class="wikitable sortable" width="95%"
!scope="col" | INSPECTION ID
+
!scope="col" | Inspection ID
!scope="col" | DATE
+
!scope="col" | Inspection Category
!scope="col" | DESCRIPTION
+
!scope="col" | Inspection Date
!scope="col" | COMMENT
+
!scope="col" | Inspection Type
!scope="col" | VIOLATION ID
+
!scope="col" | Inspection Result
!scope="col" | VIOLATION CODE
+
!scope="col" | Inspection Comments
!scope="col" | VIOLATION_COMMENT
 
 
|-
 
|-
 
| 1928308
 
| 1928308
| 2010-11-17
+
| Primary Facility
 +
| 11/17/2010
 +
| Routine/Complete Inspection
 
| No Violations Noted
 
| No Violations Noted
 
| This site is currently being constructed.  No 7 day notice was received by the Department that construction had begun.  There was no ESCGP on site.  The issues that were noteworthy were the topsoil pile on the North end requires mulching and seeding, the filter sock on the north side is not on the contour, and there is a check dam installed in the sediment trap.  The check dam does not conform with the ESCGP that I had on hand to conduct the inspection.  I spoke with Company Man, Jeff Myers, about the issues.  I have emailed Carrizo Staff regarding the plan and notice but have not received a response.  I will reinspect this site.
 
| This site is currently being constructed.  No 7 day notice was received by the Department that construction had begun.  There was no ESCGP on site.  The issues that were noteworthy were the topsoil pile on the North end requires mulching and seeding, the filter sock on the north side is not on the contour, and there is a check dam installed in the sediment trap.  The check dam does not conform with the ESCGP that I had on hand to conduct the inspection.  I spoke with Company Man, Jeff Myers, about the issues.  I have emailed Carrizo Staff regarding the plan and notice but have not received a response.  I will reinspect this site.
|
 
|
 
|
 
|-
 
 
|-
 
|-
 
| 1949297
 
| 1949297
| 2011-02-12
+
| Primary Facility
 +
| 02/12/2011
 +
| Routine/Complete Inspection
 
| No Violations Noted
 
| No Violations Noted
 
| 165 Gallons of diesel fuel spilled on to containment due to an absent minded fuel handler.  The fuel was vacuumed up.  I did not observe any evidence that the spill left the containment, however, I will reinspect the site when the equipment is removed to attempt to determine if the spill had left containment.
 
| 165 Gallons of diesel fuel spilled on to containment due to an absent minded fuel handler.  The fuel was vacuumed up.  I did not observe any evidence that the spill left the containment, however, I will reinspect the site when the equipment is removed to attempt to determine if the spill had left containment.
|
 
|
 
|
 
|-
 
 
|-
 
|-
 
| 1955399
 
| 1955399
| 2011-03-08
+
| Primary Facility
 +
| 03/08/2011
 +
| Routine/Complete Inspection
 
| No Violations Noted
 
| No Violations Noted
|
 
|
 
|
 
 
|  
 
|  
 
|-
 
|-
 
|}
 
|}
 +
<!--==== Violations Commited ====
 +
{| class="wikitable sortable" width="95%"
 +
!scope="col" | Inspection ID
 +
!scope="col" | Violation ID
 +
!scope="col" | Violation Date
 +
!scope="col" | Date Resolved
 +
!scope="col" | Violation Code
 +
!scope="col" | Violation Type
 +
!scope="col" | Violation Comments
 +
|-
 +
|}-->
 +
<!--==== Penalties Applied ====
 +
{| class="wikitable sortable" width="95%"
 +
!scope="col" | Violation ID
 +
!scope="col" | Penalty ID
 +
!scope="col" | Penalty Code
 +
!scope="col" | Penalty Status
 +
!scope="col" | Penalty Date
 +
!scope="col" | Enforcement Date
 +
!scope="col" | Penalty Amount
 +
!scope="col" | Amount Collected
 +
|-
 +
|}-->
 
For data sources see<ref>{{cite web
 
For data sources see<ref>{{cite web
  | title = Oil and Gas Historical Inspection Report
+
  | title =Oil and Gas Compliance Report
| publisher = [[Pennsylvania Department of Environmental Protection]]
+
|publisher = [[Pennsylvania Department of Environmental Protection]]
| date = 2015-05-26
+
| date = 2019-05-20
  | url = http://wellwiki.org/wiki/Pennsylvania_Oil_and_Gas_Data_Sources#Inspections
+
  | url = http://wellwiki.org/wiki/Pennsylvania_Oil_and_Gas_Data_Sources
  | accessdate = 2015-05-27 }}</ref>
+
  | accessdate = 2019-05-21 }}</ref>
== References ==
+
<!--== Fracking Activities ==
{{reflist}}
+
==== Fracking Jobs ====
 +
{| class="wikitable sortable" width="95%"
 +
!scope="col" | Job Number
 +
!scope="col" | Job Start Date
 +
!scope="col" | Job End Date
 +
!scope="col" | True Vertical Depth (ft)
 +
!scope="col" | Total Water Volume (gal)
 +
!scope="col" | Total Non-Water Volume (gal)
 +
|-
 +
|}-->
 +
<!--==== Fluid Composition Data ====
 +
{| class="wikitable sortable" width="95%"
 +
!scope="col" | Job Number
 +
!scope="col" | Trade Name
 +
!scope="col" | Supplier
 +
!scope="col" | Purpose
 +
!scope="col" | Ingredient Name
 +
!scope="col" | CAS Number
 +
!scope="col" | Additive Percentage by Mass
 +
!scope="col" | Job Percentage by Mass
 +
!scope="col" | Mass Used (lb)
 +
|-
 +
|}-->
 +
 
 +
==References==
 +
<references/>
 
__NOEDITSECTION__
 
__NOEDITSECTION__
[[Category:Wells]]
+
[[Category:Pennsylvania Wells]]

Revision as of 04:19, 15 July 2019

Well Details

Well ID: 37-115-20395
Loading map...
Country: United States
State: Pennsylvania
County: Susquehanna
Municipality: Forest Lake Township
Operator Name: CARRIZO (MARCELLUS) LLC
Well Pad ID:
Farm/Lease Name: BAKER 2H
License Status:
Spud Date:
Permit Date: 7/15/2010
Unconventional Well: Y
Configuration: Horizontal Well
Latitude: 41.883950
Longitude: -75.992386

For data sources see[1][2][3]

Production Data

Period Operator Name Gas Quantity (mcf) Gas Production Days Oil Quantity (bbl) Oil Production Days Water Quantity (bbl) Water Production Days
2010 CARRIZO (MARCELLUS) LLC 0.00 0 0.00 0 0.00 0
2011 CARRIZO (MARCELLUS) LLC 0.00 0 0.00 0 0.00 0

For data sources see[4]

Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
1928308 Primary Facility 11/17/2010 Routine/Complete Inspection No Violations Noted This site is currently being constructed. No 7 day notice was received by the Department that construction had begun. There was no ESCGP on site. The issues that were noteworthy were the topsoil pile on the North end requires mulching and seeding, the filter sock on the north side is not on the contour, and there is a check dam installed in the sediment trap. The check dam does not conform with the ESCGP that I had on hand to conduct the inspection. I spoke with Company Man, Jeff Myers, about the issues. I have emailed Carrizo Staff regarding the plan and notice but have not received a response. I will reinspect this site.
1949297 Primary Facility 02/12/2011 Routine/Complete Inspection No Violations Noted 165 Gallons of diesel fuel spilled on to containment due to an absent minded fuel handler. The fuel was vacuumed up. I did not observe any evidence that the spill left the containment, however, I will reinspect the site when the equipment is removed to attempt to determine if the spill had left containment.
1955399 Primary Facility 03/08/2011 Routine/Complete Inspection No Violations Noted

For data sources see[5]

References