Line 21: Line 21:
 
| License Status: Active Injection
 
| License Status: Active Injection
 
|-
 
|-
| License Date: 2006-09-27
+
| License Date: 2006-03-20
 
|-
 
|-
 
| Spud Date: 2006-08-17
 
| Spud Date: 2006-08-17

Revision as of 14:39, 26 July 2019

Well Details

Well ID: 34-153-22967
Loading map...
Country: United States
State: Ohio
County: Summit
Municipality: Coventry Township
Operator Name: CARGILL INC
Well Pad ID:
Farm/Lease Name: CITY OF AKRON (SMP #4)
License Status: Active Injection
License Date: 2006-03-20
Spud Date: 2006-08-17
Spud Drilling Contractor: UNION DRLG
Final Drill Date: 2006-08-27
Well Total Depth: 3150 ft
Configuration: Vertical
Latitude: 41.018814172
Longitude: -81.55922799

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2005-12-22 Proposed Formations:SALINA, Issued Date:12/22/2005, Expired Date:12/22/2006 6:00:00 AM, Drilling unit acres:15.5, Proposed Well Type:SM, Proposed Well Class:SMP
APP 2006-03-20 Proposed Formations:SALINA, Issued Date:3/20/2006, Expired Date:3/20/2007 6:00:00 AM, Drilling unit acres:120, Proposed Well Type:SM, Proposed Well Class:SMP
Original Spud 2006-08-17
Completed 2006-08-27
Reached Total Depth 2006-08-27
Completion Report Received 2006-09-27
Construction Permit Expires 2007-03-20
Last Compliance Report 2012-11-20
Record Last Modified 2016-08-29

For data sources see[2]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
0141374082 2016-08-15 Solution Mining Project No Violations A water-brine interface mechanical integrity test was performed on the well. City of Akron #77, Summit permit number 3121 was used as a reference well. Calculations indicated a net pressure change less than 0.05 psi./hour, between the well and the reference. The well passed the test.
0574127248 2008-12-31 Solution Mining Project No Violations Annual status check inspection found no violations at this time.
0867810887 2007-05-16 Solution Mining Project No Violations Preliminary restoration is due this month. The site still needs to be finish graded, topsoil spread, seeded and mulched.
0931094782 2014-12-05 Solution Mining Project No Violations An inspection of the well found no violations at the time.
1015282035 2010-08-03 Solution Mining Project No Violations Annual inspection of this solution mining well found no violations at this time.
1154634379 2006-08-01 Solution Mining Project No Violations The location has been built and Union Drilling has started moving equipment on site. Union will be using steel pits.
1221805045 2009-06-18 Solution Mining Project No Violations Columbus requested an annual inspection of the solution mining wells. This inspection found no violations at this time.
1373225773 2013-06-24 Solution Mining Project No Violations The well was properly identified. My inspection was accompanied by Andrew Adgate.
1393124839 2007-07-25 Preliminary Restoration No Violations Preliminary restoration is approved.
1547097761 2006-08-17 Drill / Deepen / Reopen No Violations Union Drilling Rig #24 spudded the well this morning and is drilling conductor hole. They should be ready to cement later today. The sump pit is lined and in good condition.
1705321168 2006-12-08 Solution Mining Project No Violations Successfully completed a MIT on this well.

09:50 525 psi 09:55 525 psi 10:00 525 psi 10:05 525 psi

1920677493 2019-01-04 Solution Mining Project No Violations I found the injection well in good repair. I observed no leaks or spills. A locked chain link fence with barb wire surrounding the injection well. An identification sign is posted.
2073860089 2011-09-29 Solution Mining Project No Violations Completed the required 5 year Class III mechanical integrity test using the water-brine interface method. The reference well is Akron #73 permit 2966. The calculated pressure required to place the interface 50 feet above the bottom of the 7 casing was 239.470 psi. The actual pressure achieved was 214.367 psi. The net pressure difference between the test well and the reference well at the start of the day was 237.227 psi. After eight hours, the net pressure difference between the test and reference point was 237.168 psi for a total loss of 0.059 psi over eight hours or 0.007 psi/hour. THE MIT WAS SUCCESSFUL AND THE WELL PASSED.

For data sources see[3]