INSPECTION ID
|
DATE
|
DESCRIPTION
|
COMMENT
|
VIOLATION ID
|
VIOLATION CODE
|
VIOLATION_COMMENT
|
-1077079683
|
2013-09-19
|
|
We pulled all of the 1" tubing, gas escape packer and 1315' of 2" tubing. The tubing needed to be circulated on to free stuck mud on the tubing. 15k pounds of weight were pulled on the casing to remove it from the hole. The casing was also swabbing the well causing it to gas during the job. Tomorrow the first cement plug will be set on the well.
|
|
|
|
-1560125190
|
2013-09-20
|
|
Rain caused a delay in setting the cement plug. The location needed to be pumped clean and drainage controls put in on the location for the weekend in case of heavy rain that may occur. A 175sk cement plug was set. It will be tagged and the second cement plug will be set Monday.
|
|
|
|
-201184649
|
2013-09-18
|
|
A tree had to be removed in order to get the rig onto location. Currently the crew is pulling the 1" tubing and plan on cementing the first plug tomorrow.
|
|
|
|
1379952594
|
2013-09-23
|
|
We tagged cement from the first cement plug to be at 144'. We set 2 3/8" tubing to 135' and pumped the second plug on the well. Cement returned to surface and the plug was topped off after tubing was pulled. The rig will be moving to the next of 9 wells to be plugged on this location.
|
|
|
|