X

Track changes made to this page

If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.



Privacy policy
Close this window

powered by ChangeDetection

34-167-23019

Well Details

Well ID: 34-167-23019
County:
Municipality:
Operator Name:
Well Pad ID:
Farm/Lease Name:
First Permit Date:
Last Permit Date:
Spud Date:
Unconventional:
Horizontal:
Producing:
Violations:
Latitude:
Longitude:

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION_COMMENT
-1446016682 2013-10-28 Total depth at the time of inspection was 1910 ft. Crew was getting ready to pull the 7" that they ran to shut off water while drilling.
-1487102178 2013-11-15 Received phone call from Mr. Bob Lane. He stated that his rig drilled the well down to 1929 ft with 4 in. tools. He also stated the Berea sandstone was from 1904 ft. to 1909 ft.
-1501047690 2013-10-15 Observed deepening operations in progress. Total depth at the time of inspection was 1671 ft. 1620 ft of 7 in casing was used to shut off the water while drilling. This pipe will be pulled after the total depth has been reached. Spoke with drillers on site.
1244434391 2013-10-30 Crew was running 4.5 in. pipe in the well and getting ready to cement it. 6.25 in hole was drilled to a depth of 1910 ft. 1901 ft of pipe was ran. Pipe was used. Mr Bob Lane provided an invoice showing that the pipe had been tested. Each joint of pipe was marked with a stamp showing that it had been tested. After cement was pumped, and the latch down plug landed, pressure was bumped up to 500 psi and held for 5 minutes. It held. I was accompanied by inspector Mike Mitchell.
2020746067 2013-11-04 Crew was preparing to go in with 4 in. tools and to drill out plug and drill below 4.5 in. casing. Spoke with rig operators on site.
2122501519 2013-09-16 Bob Lane's cable tool rig is rigged up over the hole. The pit has been dug and lined. Spoke with drillers on site. They are ready to begin drilling.