34-153-23066

Well Details

Well ID: 34-153-23066
County:
Municipality:
Operator Name:
Well Pad ID:
Farm/Lease Name:
First Permit Date:
Last Permit Date:
Spud Date:
Unconventional:
Horizontal:
Producing:
Violations:
Latitude:
Longitude:

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION_COMMENT
-1002054984 2008-11-10 Wildcat is on location and spudded the well today. The drilling pits are fenced and lined as required. No violations at this time.
-1711599157 2008-11-14 Wildcat is drilling ahead and should TD the well tomorrow. The pits are in good condition and the location is fenced. No violations at this time.
-440449040 2009-01-23 The well is now in production and the required fencing and identification are in place. Preliminary restoration will be evaluated as soon as weather permits but is not required until this summer.
-554554973 2008-12-10 The site has been graded, the wellhead fenced and the flowline installed.
1227212608 2008-11-18 Wildcat moved off on 11/17. The location is fenced and the pits are lined and in good condition. Everflow plans to solidify the pits on Saturday 11/22.
1245956983 2009-06-17 Left a voice mail on the home phone of the complaintant and asked that she call me with questions. Everflow has contacted North Coast Labs to collect a new water sample to compare with the pre-drilling results. I am waiting for these results.
1266956546 2010-02-18 Preliminary restoration is approved.
594391346 2008-11-12 Wildcat switched over to fluid this afternoon after reaching the top of the Big Lime, as required by permit. The location is fenced and the pits are lined and in good condition. No violations at this time.
707636156 2008-11-24 The pits were solidified with 65 tons of cement dust on 11/22. The pits will be covered today with the frac scheduled for Monday 12/1. No violations at this time.