| INSPECTION ID
|
DATE
|
DESCRIPTION
|
COMMENT
|
VIOLATION ID
|
VIOLATION CODE
|
VIOLATION_COMMENT
|
| -230505757
|
2011-10-24
|
|
Poulson is drilling the surface hole at 490'. They should be ready to set and cement surface casing later today. The pits are lined and in good condition.
|
|
|
|
| -900861324
|
2011-11-09
|
|
RD Wiles has a swab rig on site to work on the well and try to get it to kick off. If successful, a service rig will be brought in to run tubing. The well is being swabbed into a frac tank and a water truck is removing fluid.
|
|
|
|
| 1320682956
|
2011-10-31
|
|
Poulson Drilling has moved off location and the pits are fenced, lined and in good condition.
|
|
|
|
| 1321302837
|
2011-11-03
|
|
Hugh Palmer and Chem Tech were on site to solidify the drilling pits. Two loads were applied and mixed and a third load was being delivered later today. No violations at this time.
|
|
|
|
| 1810628421
|
2011-10-28
|
|
Drilling at 3920'. Should reach total depth (TD) later today and will run 4.5" casing tonight. The pits are fenced, lined and in good condition.
|
|
|
|
| 228458271
|
2011-10-25
|
|
Poulson is drilling ahead at 1400'. The pits are fenced, lined and in good condition.
|
|
|
|
| 362809389
|
2011-12-22
|
|
The well has been fraced and 1.5" tubing is in the hole. The tank battery equipment is on site but is not hooked up. The well is connected to the 140 barrel stock tank to flow back to but not produce into. A minimum effort has been made to initiate preliminary restoration.
|
|
|
|