-2095762228
|
2013-11-19
|
|
I performed a status check on the above location. H&P 225 is drilling at a depth of 10396' with oil base mud. There is a vacuume truck on location vacuuming rain water from inside the containment area around the drilling rig. Permits are posted. No violations were noted at this time.
|
|
|
|
-466460688
|
2014-03-05
|
|
Universal Well Service is fracing the above location. All equipment is setting inside of containment. Safety lanes are marked. All annuals are monitored. No noted violations noted at this time.
|
|
|
|
-523258778
|
2013-09-27
|
|
Falcone Drilling Rig 18 drilled a 12.25" well bore to a total depth of 2500' and ran 2500' of 36# J-55 casing. Baker Hughes pumped 234 barrels of water ahead followed by 35 barrels of Gel with Fed Seal and Cello flake follow by 10 barrels of fresh water spacer. They pumped 873 sacks of A+.05S+2CACL+.5%BA10 cement. Displaced with 190 barrels of fresh water. Bumped plug floats held. There was 40 barrels of cement returned to surface. Good circulation throughout job.
|
|
|
|
-835583192
|
2013-07-20
|
|
I was on location for the cementing of the conductor pipe. The 20" casing was set at 90'. Express Energy was the company on location for drilling the conductor and cementing it. Circulation was established and Class A cement with 2 % calcium and 8 oz. of flake was used. The cement scaled at approximatly 15.6 ppg. 173 sacks of cement was used at approximatly 50% excess. I witnessed cement return to surface and the casing was shut in for the cement to set.
|
|
|
|
1377008220
|
2013-07-20
|
|
Express Energy Service is on location drilling a 30" conductor hole to a depth of 90' and ran 90' of 20" 94# conductor casing. They cemented with 172 sacks of class A cement. They had 13 barrels of cement returned to surface. . Permits are posted. There has been safety meeting. No violations at this time. Kevin Perry covered this job.
|
|
|
|
1380737561
|
2013-09-27
|
|
Falcone Drilling Rig 18 drilled a 17.5" well bore to a total depth of 900' and ran 900' of 13-3/8 61# J-55 casing. Baker Hughes pumped 170 barrels of water ahead followed by 35 barrels of Gel with Fed Seal and Cello flake follow by 10 barrels of fresh water spacer. They pumped 766 sacks of A+.05S+2CACL+.5BA10 cement. Displaced with 132 barrels of fresh water. Bumped plug floats held. There was 50 barrels of cement returned to surface. Good circulation throughout job.
|
|
|
|
1441975737
|
2014-01-31
|
|
Northeast Region Supervisor Tom Hill and myself performed a status check on the above location. They are preparing the location and wellhead for fracing. There has been a 2" welded steel flow line installed and is caped with a blind flanged. No noted violations were noted at this time.
|
|
|
|
1684067283
|
2013-11-25
|
|
I performed a status check on the above location. H&P Drilling Rig 225 drilled 8.625" to a total depth of 17509' and are now running 5.5" casing. They will call when ready to cement casing.
|
|
|
|
523152728
|
2014-02-12
|
|
Universal Well Service is fracing the above location. All equipment is setting inside of containment. Safety lanes are marked. All annuals are monitored. No noted violations noted at this time.
|
|
|
|
968304020
|
2013-10-29
|
|
H&P Rig 225 is preparing to move to the 6-H (3409923192) location. No violations were noted at this time. Vacuum trucks are on location vacuuming all the fresh water as they clean the rig.
|
|
|
|
977952919
|
2013-10-22
|
|
Northeast Region Supervisor Tom Hill and myself performed a status check on the above location. We meet with Bill Mitchell the Drilling Consultant for Hillcorp. At that time Blackhawk was performing the blowout preventor test and casing test. We talked with the personal that was performing the test about the various aspects of the testing
|
|
|
|