Well ID: 34-115-24683 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":39.6092802082,"lon":-81.6669590627,"icon":""}]} |
County: | |
Municipality: | |
Operator Name: | |
Well Pad ID: | |
Farm/Lease Name: | |
First Permit Date: | |
Last Permit Date: | |
Spud Date: 2013-11-27 | |
Unconventional: | |
Horizontal: | |
Producing: No | |
Violations: 0 | |
Latitude: 39.6092802082 | |
Longitude: -81.6669590627 |
PERIOD | GAS QUANTITY | GAS PRODUCTION DAYS | CONDENSATE QUANTITY | CONDENSATE PRODUCTION DAYS | OIL QUANTITY | OIL PRODUCTION DAYS |
---|
PERIOD | TYPE | QUANTITY | UNITS | DISPOSAL METHOD | WASTE FACILITY PERMIT ID | WASTE FACILITY NAME | FACILITY CITY | FACILITY STATE |
---|
INSPECTION ID | DATE | DESCRIPTION | COMMENT | VIOLATION ID | VIOLATION CODE | VIOLATION_COMMENT |
---|---|---|---|---|---|---|
-1193968809 | 2014-07-21 | PDC is currently in on Stage 10 of their completion operation. The average treating pressure has been around 6800 psi at 78-80 bbls/min. They are no longer completing both wells (2H and 3H) at the same time but will finish the 3H first before completing the 2H. | ||||
1050357990 | 2013-11-27 | I am on site to witness the cementing of the conductor casing. Express Energy Services drilled 36" hole to a depth of 100'. Express then cemented 100' of 30" casing in place with 315 sks of class A cement with 2% CaCl. 18 bbl of cement returns to surface. | ||||
1385566018 | 2013-11-27 | I arrived on location to witness PDC set their conductor casing, however they were having hard time getting the casing into the hole. They have pushed the cement job to the early evening. | ||||
1389962172 | 2014-01-17 | I arrived on location to witness Halliburton cement 5786' of 9 5/8 intermediate casing with 1340 sacks of cement. PDC is using the H & P 385 Flex Rig. Upon arrival, operator was circulating the hole and Halliburton was still trying to get their equipment rigged up and running properly at the wellhead. PDC used 21 centralizers. Plug was down at 10:20am and landed at 12:15pm, however the pressure gradually backed off possibly indicating a leak in the plug or loss of cement to formation. There were spacer returns but no cement returns at the surface. The decision was made to leave the head on and wait 8 hours for the cement to set then run a temperature log, collar locator, and gyro in order to determine the condition of the cement. 1/18/2014: Temperature log showed top of cement at 410'. They ran a gyro and then skid the rig to begin drilling the 2H. | ||||
1396440683 | 2014-04-02 | PDC skid the H & P rig to the 3H and ran cement bond log. The top of cement on the 9 5/8" was actually at 2610'. They are currently waiting on perf and cement trucks in order to perf at 2580' and set a retainer at 2270'. | ||||
1397821335 | 2014-04-18 | Day Gray called and stated they were unable to get their build rates great enough to land so they pulled back and set a kick plug down to 6200'. | ||||
1399463346 | 2014-05-07 | I arrived on location for the operation and safety meetings. At this time the well is producing very little gas. If it is bridged off they will know once the pull on the drill pipe by drag weight. During the operation meeting, it was discussed that PDC personnel will attempt to kill the well followed by the cutting and tripping out the drill pipe. They will then install a packer to control the well. They plan on using a radial cutting tool. Wild Well Control will be at the wellhead to determine the area of mechanical integrity failure. | ||||
1399563777 | 2014-05-08 | |||||
1405542737 | 2014-07-16 | I was on location to witness PDC and CalFrac undergo stimulation operations. For the first stage they hydraulically fractured the formation with a breakdown of 5678 psi. The average treating pressure was around 6160 psi with an average rate of 20bbls/minute. | ||||
1880710286 | 2014-04-24 | I stopped by for a rig check. Everything looks good and the H & P flex rig was currently drilling the lateral at a depth of 8795'. | ||||
775787808 | 2014-01-05 | I was on location to witness Allied Oilfield Services cement 378' of 20" the surface casing. PDC is using the H & P Flex rig 385. PDC used 4 centralizers. Plug was down at 9:15pm with good cement returns. |