34-115-23962

Well Details

Well ID: 34-115-23962
Loading map...
County:
Municipality:
Operator Name:
Well Pad ID:
Farm/Lease Name:
First Permit Date:
Last Permit Date:
Spud Date: 1986-12-21
Unconventional:
Horizontal:
Producing: No
Violations: 2
Latitude: 39.6913237516
Longitude: -81.8251966783

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION_COMMENT
-1266256458 2007-01-16 A.D. not hooked up, well is equipped with 4.5" casing ,tubing and rods pump jack has been removed from site no tank found and no I.D. posted last production reported on well was back in 1998. 9-9-05(A)10
-1266256458 2007-01-16 A.D. not hooked up, well is equipped with 4.5" casing ,tubing and rods pump jack has been removed from site no tank found and no I.D. posted last production reported on well was back in 1998. NONE E
-520288505 2007-12-31 Final restoration work at site satisfactory,pit has been filled in and site restored and vegetation established.
1089052802 2007-04-16 No change in status of well it is still idle and awaiting plug permit to be issued and rig to be scheduled.
1269839018 2007-10-08 Well has been plugged resolving previous NOV.
1428173562 2007-10-04 On site to witness setting of bottom hole plug,placed plug through tubing due to fact that tubing was hung suspect anchor jt set to lowin well it was sanded in,set required plug owner will get wireline unit called and shoot off tubing@top of cement plug.
929714146 2007-10-05 On site to witness operator shoot tubing off at top of cement tubing was parted@1357' by Applachian Well Services tubing was pulled then operator ran ripping tool in hole to get telegraph it was received@665' knocked off pipe in preparation for cementing at later date.