Well Details

Well ID: 34-089-26143
Loading map...
County:
Municipality:
Operator Name:
Well Pad ID:
Farm/Lease Name:
First Permit Date:
Last Permit Date:
Spud Date: 2014-03-04
Unconventional:
Horizontal:
Producing: No
Violations: 0
Latitude: 40.0942549947
Longitude: -82.5562945077

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION_COMMENT
-1212488263 2014-03-03 Inspect drilling location. Kilbarger rig #1 rigged up. The pits were dug and lined. The bit and collar were hung in the cellar. The rig was prepared to spud well. No activity during inspection. Weather: 13 degrees F, Sunny and 2 inches of snow
-1502446606 2014-03-05 I witnessed the cementing of the 11.75" surface casing on Kilbarger rig #1. John Suhar was on location for David R. Hill Inc. Universal Well Service was contracted to cement casing. Universal broke circulation and good cement returns were observed. Cement stayed at the surface. A cement basket was not used. Universal pressured up on the casing and the test passed. The cement ticket was received.
-1557124025 2014-03-07 Inspect drilling operations. Kilbarger rig #1 drilling on air with an 11 inch bit during inspection. No violations.
-2004049628 2014-03-04 Inspect drilling operations. Kilbarger rig #1 spudded well during inspection. Kilbarger was drilling on fluid with a 17.5" bit. No violations.
-326691769 2014-03-12 Inspect drilling operations. Kilbarger rig #1 drilling on fluid during inspection. Depth approximately 3,500 feet. No violations.
-436235652 2014-03-08 I witnessed the cementing of the 8.63" casing on Kilbarger rig #1. John Suhar was on location for David R. Hill Inc. Universal Well Services was contracted to cement casing. Universal broke circulation and good cement returns were observed. Cement stayed at surface. The cement ticket was received.
-595399840 2014-02-18 Inspect location. Greg Wycoff with Energy Services Corp. building access road during inspection.
-936470971 2014-02-27 Inspect drilling location. Kilbarger rig #1 has moved in and rigged up. The well has not been spudded. The blow pit was being constructed and a 20 mil liner was installed. Toolpusher Gerald Smith was on location. No violations.
1285505166 2014-02-20 Inspect location. Access road and well location being built. Access road is being built with road matting material with crushed stone and concrete. Orange safety fencing and silt fencing has been installed on east side of drilling location. Weather: 41 degrees F, 2" snow
1392733268 2014-01-30 Jeff Fry accompanied me on this site visit. We met with Dave Hill Inc. at the Klema/Bruce Farms #1 location to discuss drilling operations for the Cannon Unit #1. John Suhar, Don Kreager, and Gary Sitler was on location for Dave Hill Inc. Kilbarger Drilling supervisor Gary Smith was on location and Greg Wycoff with Buckeye Water was present. John Suhar pointed out the access road/entry point that would be used during drilling. We walked the drilling location and the rig and pit orientation was explained. John Suhar informed me that Kilbarger rig #1 would be used to drill the well and that they would begin building the location within a couple weeks. Weather: 6" snow on ground during inspection. Note: This is not an urban area permit
1395755697 2014-03-09 Inspect drilling operations. Kilbarger rig #1 drilling on air with 7.88" PDC bit. The depth during inspection was approximately 2,000 feet. Kilbarger drilled into a reef in the bottom of the Big Lime @ 2,016 feet and mudloggers recorded a 2,000 unit gas show. Gas was being flared into the blow pit during inspection. David R. Hill Inc. contracted Fesco Inc. to sample gas. After the gas was sampled Kilbarger loaded the hole with brine to kill the flare and went to drilling on fluid. No violations.
1402763493 2014-03-24 I witnessed Universal Well Services acidize this well for David R. Hill Inc. John Suhar and David Hill was on location. Refer to stimulation report for details.
1408363696 2014-08-06 This inspection was conducted as a preliminary restoration status check. The well was equipped with a pumping unit and motor. A GPS reading was taken at the wellhead. The area around the well has been restored and landscaped with trees. The tank battery consists of (2) 100 barrel tanks inside an earthen dike. The tanks are within the same dike as a #6118. Identification was posted at the separator. The inspection meets ORC 1509.072 requirements.
2096553196 2014-02-18 Accompanied Inspector Brandon Mitchell for a pre-site drill inspection.
575481046 2014-03-21 This inspection was conducted as a status check. Berry Well Service service rig on well and running tubing during inspection. The 4.5" casing was perforated this morning. The job was not witnessed. No violations.
745544631 2014-04-03 This inspection was conducted as a preliminary restoration status check. The pits have been closed. No activity during inspection. No violations.