34-085-21135

Well Details

Well ID: 34-085-21135
Loading map...
County:
Municipality:
Operator Name:
Well Pad ID:
Farm/Lease Name:
First Permit Date:
Last Permit Date:
Spud Date: 2005-01-13
Unconventional:
Horizontal:
Producing: No
Violations: 0
Latitude: 41.591613306
Longitude: -81.3070978595

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION_COMMENT
-1141464783 2013-07-15 The producing unit consists of a wellhead and mechanical plunger lift unit and an aboveground storage tank (AST) battery with one steel 140-barrel production tank, one steel 20-barrel brine tank, mechanical separator, and metering run. Both the wellhead and battery are within the same chain-link enclosure which is locked. The unit ID is present and meets requirements. 1501:9-9-05E safety equipment is present. The battery secondary containment is good. No evidence of leaks or spills.
2053176808 2012-03-19 My inspection found this well in good repair. This site passed Preliminary Restoration on 08/08/2011. The tank battery is in need of HB-278 equipment and Gary McIntyre was informed of this issue.
553593274 2013-06-19 The producing unit consists of the following elements: A production wellhead and storage tank battery. The production wellhead is fitted with a mechanical plunger lift system and is located 200 feet east of the tank battery. The tank battery system includes 2 100-barrel storage tanks, a 50-barrel poly tank, mechanical separator and associated appurtenances. The tank battery is enclosed in a chain link enclosure. The enclosure is locked and the secondary containment is good. Tank and well spacing is in accordance with 1501:09. HB 278 equipment is present. No problems or violations noted. OK for preliminary restoration.
657860907 2011-08-08 This site passes preliminary restoration.