34-053-60003

Well Details

Well ID: 34-053-60003
Loading map...
County:
Municipality:
Operator Name:
Well Pad ID:
Farm/Lease Name:
First Permit Date:
Last Permit Date:
Spud Date: 1932-07-01
Unconventional:
Horizontal:
Producing: No
Violations: 0
Latitude: 38.9249530879
Longitude: -82.1674166379

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION_COMMENT
-1070888011 2005-04-05 Accompanied Michael Altier; witnessed placement of ID.
-1856271519 2005-02-07 No ID; still producing; belongs to MJA (Michael Altier). Coords need adjusting - off about 300'.
-2013609551 2005-02-07 No ID; still producing; belongs to MJA (Michael Altier). Coords need adjusting - off about 300'.
-534904644 2008-05-13 Tag top of cement plug at 1185' Rig hands refused to check for fluid level. Timco ran casing cutter could only get to 290'. Tried to use collar buster and got to 805' Shot at 805' Casing jumped but rig could not pull casing. 2nd shot at 783' pulled 15,000lbs over string weight before shooting. 783'of 6" casing was pulled out.
-588314355 2008-05-14 Ran 671' of 2" tubing. Cement to surface. Did it in two lifts of 322' each. Cement did not circulate to surface. Cement truck ran out of cement. Will have to tag latter and order more cement.
-801818636 2005-10-05 Need to correct coordinates.
1206031036 2008-03-03 This well is to be plugged by OVEC as part of their FGD Landfill project. A 14" steel conductor has a 6" Od casing in it that is sealed at the surface with cement. The 6" casing has a 2" tubing in it. This 2" tubing has cement around it at the surface also. There are no hangers so the tubing must be on a packer of some sort.
1212585392 2008-05-09 Spot bottom plug by running 1" inside 2" tubing. Ran 1" to 1717.95' . Pulled 4 joints 1" and then circulated to clean out for wire line.
451178481 2008-05-12 Rig has been vandalized. A fire extinguisher from the rig was set off in the cab of the rig. Some wrenches are missing from the rig. Debris was placed down the well. Obstruction hit at 686' wire line cannot get past it. Ran 1" jars could get to 700' then stopped. Ran 1" tubing back down to 1585' 1" pushed the obstruction down hole. Pulled 1" back out. Wire line shot at 1545' (7shots). 2" free set 300' plug through 2" then pulled 400' of 2" tubing and circulated 5 3/16" out. Pulled 1545' of 2" out.
649767427 2008-05-15 Tag top of cement plug at 150' ran 2" tubing down to 150' and cemented to surface. Cement stayed at surface.