Well Details

Well ID: 34-151-25673
Loading map...
County:
Municipality:
Operator Name:
Well Pad ID:
Farm/Lease Name:
First Permit Date:
Last Permit Date:
Spud Date: 2010-05-22
Unconventional:
Horizontal:
Producing: No
Violations: 0
Latitude: 40.7861330521
Longitude: -81.5130489062

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION_COMMENT
-1091674764 2010-05-04 Jay Cheslock received a complaint call from Lucille Parker (330-832-1937) on 5-4-2010 regarding activity at the new drilling location near her home at 929 3rd St. SE in Massillon, OH. I inspected the site and met with John Rose, who was building the access road and pushing topsoil. I also met with Lucille Parker and discussed the future drilling activities at the site.
-1526207800 2010-03-23 I met with Dale Nething (Ohio Valley Energy) and John Howell (Wildcat Drilling) to discuss the future location of the drilling pits. This well will be drilled before July 2010.
1274728736 2010-05-22 Wildcat Drilling is moving onto the location and will spud the well tonight. I met with John Howell and discussed the urban drilling requirements.
1275072788 2010-05-26 Dusting at 4470'. Drilling pits and liners are intact.
1275412521 2010-05-29 The Rose Run was dry. Petroset pumped the Rose Run, Trenton, and thief plugs thru drill pipe. The well was plugged back to the Clinton Sandstone. 4-1/2 dia casing was run thru the Clinton Sandstone and cemented.
1275938009 2010-06-03 The location and the drilling pits are fenced. The drilling pits are 1/2 full. There are 2 - 500 bbl frac tanks on the location.
1277923044 2010-06-29 The well has been completed. The drilling pits are closed. There is 1 - 300 bbl frac tank on the location.
1281030277 2010-05-28 Switched over to fluid drilling at 6593'. Reached T.D. of 6869' Will trip out of the hole to log.
1285462867 2010-09-23 The well is ready to go into production and the reclamation is nearly completed at the site. I called Dale Nething (Ohio Valley) and requested additional seeding at the site. I did not pass the Preliminary Restoration at this time.
1326809656 2012-01-06 On 1/6/2012, I performed a status check on the above well site. The well is in production, the site is reclaimed and identification signs are posted. The Preliminary Restorstion is PASSED.
1526301345 2010-05-23 Petroset cemented 11-3/4 dia conductor casing. The drilling pits are fenced off and the pit liners are intact.
1594307993 2010-07-13 The tank battery is set and the location is graded but not seeded.
177230565 2010-06-08 The drilling pits are being solidified today.
1819843662 2010-05-24 Universal cemented 8-5/8 dia surface casing. The drilling pits are fenced off and the pit liners are intact.
2076440435 2014-03-24 During my inspection I found this well to be plugged back from the Rose Run formation to the Clinton Sandstone and is currently a production well, not plugged and abandoned as listed on RBDMS. I found a fenced tank battery with a 100 bbl production tank, 50 bbl poly brine tank and a horizontal separator. The tank battery and well have proper I.D. signs. The well is a plunger lift well that is fenced. The location has vegetation established and landscaping in place. There are no violations at this time.
298917174 2010-06-01 Wildcat Drilling is rigging down and moving off of the location.