34-105-22795

Well Details

Well ID: 34-105-22795
Loading map...
County:
Municipality:
Operator Name:
Well Pad ID:
Farm/Lease Name:
First Permit Date:
Last Permit Date:
Spud Date: 1983-10-26
Unconventional:
Horizontal:
Producing: No
Violations: 4
Latitude: 39.036559021
Longitude: -82.0597189274

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION_COMMENT
-103825152 2006-11-17 Spoke with a company representative regarding the noncompliance.
-1246179616 2012-03-29 The contaminated soils at the well head has been removed. The leaking union at the well has been replaced. The buried 100 Bbl production tank was removed. The contaminated soils under the buried tank were removed. The dike has been re-worked and is no longer leaking. Contaminated soils outside the dike have been removed. Contaminated soils inside the dike have also been removed and new gravel has been laid down. Produced water is being stored in a 100 Bbl production tank in the dike.
-1694506560 2012-03-21 Production line has leaked roughly 2 gallons of oil near the well head. All oil and contaminated soils shall be removed and disposed of properly. Vegetative cover shall be reestablished in the affected area. The dike had a small amount of water in it. Water shall be removed. The brine transfer pump was leaking water into the dike. Leaking equipment at the well head and the dike shall be repaired or replaced. Water leaking out of the dike drain was found to contain brine and an area roughly 15' feet in length was found to be void of vegetation. Contaminated soils shall be removed and vegetative cover shall be established. 9-1-07
-1694506560 2012-03-21 Production line has leaked roughly 2 gallons of oil near the well head. All oil and contaminated soils shall be removed and disposed of properly. Vegetative cover shall be reestablished in the affected area. The dike had a small amount of water in it. Water shall be removed. The brine transfer pump was leaking water into the dike. Leaking equipment at the well head and the dike shall be repaired or replaced. Water leaking out of the dike drain was found to contain brine and an area roughly 15' feet in length was found to be void of vegetation. Contaminated soils shall be removed and vegetative cover shall be established. 9-9-05(A)1
-1694506560 2012-03-21 Production line has leaked roughly 2 gallons of oil near the well head. All oil and contaminated soils shall be removed and disposed of properly. Vegetative cover shall be reestablished in the affected area. The dike had a small amount of water in it. Water shall be removed. The brine transfer pump was leaking water into the dike. Leaking equipment at the well head and the dike shall be repaired or replaced. Water leaking out of the dike drain was found to contain brine and an area roughly 15' feet in length was found to be void of vegetation. Contaminated soils shall be removed and vegetative cover shall be established. 9-9-05(A)9
-559225083 2012-03-22 A buried 100 bbl production tank was found to be the source for the large bare area outside of the dike. It was removed. All oil, brine, and contaminated soils below the tank were removed and disposed or properly before the hole was filled back in.
-591722095 2006-06-14 The well was not equipped for annular disposal. The tank battery dike was found inadequate in size and full of brine. The area between the tanks and the creek was bare of vegetation. 9-1-07
-961361426 2007-04-04 No action has been taken since last inspection. The dike remains inadequate in size and full of water. Remediation of the kill area remains incomplete.
1067307503 2007-05-11 Spoke with Frank Herald, regarding the condition of the tank battery. The NOV requirements were explained to Mr. Herald.
1332340507 2012-03-21 Well not hooked up for annular disposal.
1659089650 2007-07-31 The tank battery was cleaned up and the dike was rebuilt.
1784037242 2006-10-04 The remediation and tank battery dike conditions were unacceptable.
310594654 2007-06-13 Met with Frank Herald, regarding the condition of the tank battery. Once again, the NOV requirements were explained to Mr. Herald.
43937358 2006-09-14 No improvement was found at the tank battery.
PL10962 Preliminary Restoration done information from Data Point