34-153-23053

Well Details

Well ID: 34-153-23053
Loading map...
County:
Municipality:
Operator Name:
Well Pad ID:
Farm/Lease Name:
First Permit Date:
Last Permit Date:
Spud Date: 2008-11-11
Unconventional:
Horizontal:
Producing: No
Violations: 0
Latitude: 41.3044843508
Longitude: -81.4423851674

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION_COMMENT
-1734601147 2009-12-03 Preliminary restoration is approved.
-1871089542 2008-11-28 The drilling pits have been solidified and covered over. No violations at this time.
-2083223467 2009-01-21 The well is now in production and the required fencing and identification are in place. No violations at this time.
1228336736 2008-11-25 The well has been fraced and the pits are still open. They are scehduled to be solidified tomorrow morning. No violations at this time.
1591640752 2008-11-14 Capstar Rig 2 is drilling ahead just above the salt. The pits are lined, fenced and in good condition. No violations at this time.
2132907763 2008-11-10 Capstar Drilling Rig 2 is moving on location and should spud the well later tonight. The pits have not been dug. The required ID and permit are posted.
235555165 2008-11-19 Capstar moved off location and the site is being rough graded. The pits are fenced, lined and in good condition. No violations at this time. The well is scheduled to be fraced next week.
812487984 2008-12-17 The well has been completed, the tank battery is under contruction and the sales line is being installed. The well can be turned on as soon as the required fencing is installed, which should be around the first of the year.