{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":41.0474613797,"lon":-81.6577717291,"icon":""}]} |
County: | |
Municipality: | |
Operator Name: | |
Well Pad ID: | |
Farm/Lease Name: | |
First Permit Date: | |
Last Permit Date: | |
Spud Date: 2010-11-01 | |
Unconventional: | |
Horizontal: | |
Producing: No | |
Violations: 0 | |
Latitude: 41.0474613797 | |
Longitude: -81.6577717291 |
PERIOD | GAS QUANTITY | GAS PRODUCTION DAYS | CONDENSATE QUANTITY | CONDENSATE PRODUCTION DAYS | OIL QUANTITY | OIL PRODUCTION DAYS |
---|
PERIOD | TYPE | QUANTITY | UNITS | DISPOSAL METHOD | WASTE FACILITY PERMIT ID | WASTE FACILITY NAME | FACILITY CITY | FACILITY STATE |
---|
INSPECTION ID | DATE | DESCRIPTION | COMMENT | VIOLATION ID | VIOLATION CODE | VIOLATION_COMMENT |
---|---|---|---|---|---|---|
-1328418953 | 2011-07-06 | Industry Standard has a contractor on site grading the location and spreading topsoil. The affected area should be ready to seed within a week. The security fencing is up and the well is in production. | ||||
-1397008601 | 2010-11-01 | G&H Drilling moved on location this past weekend and spudded the well this morning. The drilling pits were lined, fenced and in good condition. This is an urban location. No violations at this time. | ||||
-1399591150 | 2010-11-02 | G&H Drilling is coming out from under surface cement and drilling the 7-7/8" main hole with fresh water. They will drill the well with fluid. The pits are fenced, lined and in good condition. No violations at this time. | ||||
-1654383073 | 2010-11-16 | The drilling pits have been pumped down, are still lined and fenced. Solidification is scheduled for 11/19. | ||||
-969722324 | 2010-12-22 | The well has been fraced and the tank battery has been built. ISSI still needs to set a pump jack and install the security fencing before turn on. | ||||
1208343467 | 2010-10-28 | The location has been built and G&H Drilling is starting to move in. | ||||
1291045342 | 2010-11-19 | Witness pit solidification. Chemtech delivered and applied two loads of dust to the drilling pits. The landowner requested that the stumps be placed in the pits before they are covered over. He also requested that the tank battery be moved approximately 50 feet to the northeast. I advised the operator and the landowner of the minimum spacing requirements that must be met. | ||||
1663160904 | 2010-10-27 | The drilling location is being built. The rig is scheduled to arrive later this week. | ||||
1910749422 | 2011-12-14 | Preliminary Restoration is approved. | ||||
1971344387 | 2011-03-04 | Status check inspection found that the pump jack was installed and pumping. The fence has been installed around the tank battery but not around the wellhead. I called Tim Levengood and told him to shut the well down until all of the fence was installed. There is also a question as to the legality of one of the leases in this unit. Columbus has requested but not yet received additional documentation from ISSI. | ||||
239164036 | 2010-11-04 | G&H is drilling ahead on fluid. The pits are fenced, lined and in good condition. | ||||
791218496 | 2011-01-25 | A pump jack has not yet been set on the well which has been equipped with rods. The tank battery is being constructed. The required security fence has not been started but will need to be completed before turn on. No indication from the company as to when the well will be ready for turned on. Preliminary restoration is due this spring. |