X

Track changes made to this page

If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.



Privacy policy
Close this window

powered by ChangeDetection

37-111-20309

Well Details

Well ID: 111-20309
Loading map...
County: Somerset
Municipality: Addison Township
Operator Name: CHIEF OIL & GAS LLC
First Permit Date: 2011-07-15
Last Permit Date: 2011-07-15
Spud Date: None
Unconventional: Yes
Horizontal: Yes
Violations: None
Latitude: 39.743555
Longitude: -79.357638

Well Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID
2088108 2012-01-08 No Violations Noted Routine inspection. No issues noted.
2093090 2012-06-12 No Violations Noted At the time of inspection, no E&S issues were present at the site.
2094699 2012-08-06 No Violations Noted At the time of inspection, no E&S issues were present at the site. Gas well was not in production


2094795 2012-08-14 No Violations Noted At the time of inspection, no E&S issues were present at the site. Gas well was not in production


2095563 2012-08-28 No Violations Noted At the time of inspection, no E&S issues were present at the site. Gas well was not in production
2107617 2012-10-09 No Violations Noted At the time of inspection the Operator indicated that the well has not been drilled. The Erosion and Sedimentation plan was onsite and appeared to installed as outlined in the plan. No observation of accelerated erosion or sedimentation in relation to the well pad area or access road. The Department suggest the Operator continue to monitor the site weekly and after significant precipitation event to ensure the stability of the site is maintained.
2120850 2012-11-30 No Violations Noted At the time of inspection, no E&S issues were present at the site. Surface casing was set at 25feet from grade with 30 sacks of Type I (24” pipe).
2123099 2012-12-12 No Violations Noted At the time of inspection, no E&S issues were present at the site. Conductor casing was set at 38feet from grade with 30 sacks of Type I (24” pipe). Water Protection pipe (16”) was set at 413 feet and was cemented with 421 sacks of Class A with 17 bbl. of return cement. Cement was completed on 12/12/12 at 1:00 hrs.

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
2011-2 0.0 0.0 0.0 0.0 0.0 0.0

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE

References