Well ID: 37-111-20309 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":39.743556,"lon":-79.357639,"icon":""}]} |
Country: United States | |
State: Pennsylvania | |
County: Somerset | |
Municipality: Addison Township | |
Operator Name: CHIEF OIL & GAS LLC | |
Well Pad ID: | |
Farm/Lease Name: PMG ALLEN UNIT 2H | |
License Status: | |
Spud Date: | |
Permit Date: 2011-07-15 | |
Well Type: GAS | |
Unconventional Well: Y | |
Configuration: Horizontal Well | |
Conservation: No | |
Latitude: 39.743556 | |
Longitude: -79.357639 |
Date | Event |
---|---|
2011-07-15 | New Permit Application |
For data sources see[4]
Period | Operator Name | Gas Quantity (mcf) | Gas Production Days | Oil Quantity (bbl) | Oil Production Days | Water Quantity (bbl) | Water Production Days |
---|---|---|---|---|---|---|---|
2011 | CHIEF OIL & GAS LLC | 0.00 | 0 | 0.00 | 0 | 0.00 | 0 |
For data sources see[5]
Inspection ID | Inspection Category | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|---|
2088108 | Primary Facility | 2012-01-08 | Routine/Complete Inspection | No Violations Noted | Routine inspection. No issues noted. |
2093090 | Primary Facility | 2012-06-12 | Routine/Complete Inspection | No Violations Noted | At the time of inspection, no E&S issues were present at the site. |
2094699 | Primary Facility | 2012-08-06 | Routine/Complete Inspection | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Gas well was not in production |
2094795 | Primary Facility | 2012-08-14 | Routine/Complete Inspection | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Gas well was not in production |
2095563 | Primary Facility | 2012-08-28 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Gas well was not in production |
2107617 | Primary Facility | 2012-10-09 | Routine/Complete Inspection | No Violations Noted | At the time of inspection the Operator indicated that the well has not been drilled. The Erosion and Sedimentation plan was onsite and appeared to installed as outlined in the plan. No observation of accelerated erosion or sedimentation in relation to the well pad area or access road. The Department suggest the Operator continue to monitor the site weekly and after significant precipitation event to ensure the stability of the site is maintained. |
2120850 | Primary Facility | 2012-11-30 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Surface casing was set at 25feet from grade with 30 sacks of Type I (24” pipe). |
2123099 | Primary Facility | 2012-12-12 | Drilling/Alteration | No Violations Noted | At the time of inspection, no E&S issues were present at the site. Conductor casing was set at 38feet from grade with 30 sacks of Type I (24” pipe). Water Protection pipe (16”) was set at 413 feet and was cemented with 421 sacks of Class A with 17 bbl. of return cement. Cement was completed on 12/12/12 at 1:00 hrs. |
2337764 | Primary Facility | 2015-01-12 | Plugging(Includes Plugged/Mined Through) | No Violations Noted | DEP inspected plugging of abandoned well on Penndot property. Yost drilling company set up on well. Yost opened well to 5200 feet. Gas was encountered at 1,400 feet. No other gas zones were encountered 9 5/8 inch pipe depth was 1460 feet. The remaining hole was open to bottom at 5,208 feet Wireline was run and was determined to set 6 cement plugs based on wireline results. In addition, the top 200 feet will be cemented with Class A cement and graded to Penndot specification at surface. At the time of inspection, no E&S issues were present at the site |
For data sources see[6]