Well ID: 37-125-23173 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":40.226357,"lon":-80.516472,"icon":""}]} |
County: Washington | |
Municipality: Independence Township | |
Operator Name: RANGE RESOURCES APPALACHIA LLC | |
Well Pad ID: 147866 | |
Farm/Lease Name: BROWNLEE 1H | |
First Permit Date: 2008-05-20 | |
Last Permit Date: 2008-05-20 | |
Spud Date: 2008-08-18 | |
Unconventional: Yes | |
Horizontal: No | |
Well Status: ACTIVE | |
Violations: 6 | |
Latitude: 40.226357 | |
Longitude: -80.516472 |
PERIOD | GAS QUANTITY | GAS PRODUCTION DAYS | CONDENSATE QUANTITY | CONDENSATE PRODUCTION DAYS | OIL QUANTITY | OIL PRODUCTION DAYS |
---|---|---|---|---|---|---|
2008-0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2009-0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2010-0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2011-0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 |
2011-0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 |
For data sources see[1]
PERIOD | TYPE | QUANTITY | UNITS | DISPOSAL METHOD | WASTE FACILITY PERMIT ID | WASTE FACILITY NAME | FACILITY CITY | FACILITY STATE |
---|---|---|---|---|---|---|---|---|
2008-0 | DRILLING | 906.0 | Bbl | MUNICIPAL SEWAGE TREATMENT PLANT | PA0026158 | MON VALLEY SEWAGE AUTHORITY SEWAGE TREATMENT PLANT | PA | |
2008-0 | DRILLING | 6.0 | Bbl | OTHER | ||||
2008-0 | FRACKING FLUID | 2.0 | Bbl | MUNICIPAL SEWAGE TREATMENT PLANT | PA0026891 | CHARLEROI BORO AUTHORITY | CHARLEROI | PA |
2008-0 | FRACKING FLUID | 3.0 | Bbl | MUNICIPAL SEWAGE TREATMENT PLANT | PA0026158 | MON VALLEY SEWAGE AUTHORITY SEWAGE TREATMENT PLANT | PA | |
2009-0 | BRINE | 208.0 | Bbl | OTHER | ||||
2009-0 | DRILLING | 1.0 | Bbl | OTHER | ||||
2009-0 | FRACKING FLUID | 150.0 | Bbl | OTHER |
For data sources see[2]
INSPECTION ID | DATE | DESCRIPTION | COMMENT | VIOLATION ID | VIOLATION CODE | VIOLATION_COMMENT |
---|---|---|---|---|---|---|
1731843 | 2008-08-27 | No Violations Noted | Complaint about stream being dried up - no hard evidence that Range caused situation - gave them PPOP | |||
1853132 | 2009-12-18 | No Violations Noted | Inactive status applied for on this well. Cellar full of water and covered. Appears well is not completed beyond the vertical bore as stated in completion report. No open pit and site partially reclaimed. | |||
1955612 | 2011-03-02 | Violation(s) Noted | I inspected this site on 03/02/2011 for ESCGP-1 (ESX10-125-0062) Major Modification Application (submitted on 01/13/2011). A deficiency letter was sent on 01/21/2011, but the response on 02/22/2011 didn't include all information related with the deficiencies. However, I found the site constructions were different from the drawings (plans) originally issued on 08/16/2010 (e.g. pipeline, impoundment, etc.). Impoundments were not structurally sound, impermeable, 3rd party protected, greater than 20" of seasonal high ground water table. In addition, the inspection found "failure to implement Special Protection BMPs for HQ or EV stream." The pipelines were also found where they were not indicated and/or not located in the valid ESCGP-1and on stream w/o 105 permits. See the details attached. | 606148 | 78.53 - Failure to implement and maintain BMPs in accordance with Chapter 102. | |
1955612 | 2011-03-02 | Violation(s) Noted | I inspected this site on 03/02/2011 for ESCGP-1 (ESX10-125-0062) Major Modification Application (submitted on 01/13/2011). A deficiency letter was sent on 01/21/2011, but the response on 02/22/2011 didn't include all information related with the deficiencies. However, I found the site constructions were different from the drawings (plans) originally issued on 08/16/2010 (e.g. pipeline, impoundment, etc.). Impoundments were not structurally sound, impermeable, 3rd party protected, greater than 20" of seasonal high ground water table. In addition, the inspection found "failure to implement Special Protection BMPs for HQ or EV stream." The pipelines were also found where they were not indicated and/or not located in the valid ESCGP-1and on stream w/o 105 permits. See the details attached. | 606149 | 78.56PITCNST - Impoundment not structurally sound, impermeable, 3rd party protected, greater than 20" of seasonal high ground water table | |
1955612 | 2011-03-02 | Violation(s) Noted | I inspected this site on 03/02/2011 for ESCGP-1 (ESX10-125-0062) Major Modification Application (submitted on 01/13/2011). A deficiency letter was sent on 01/21/2011, but the response on 02/22/2011 didn't include all information related with the deficiencies. However, I found the site constructions were different from the drawings (plans) originally issued on 08/16/2010 (e.g. pipeline, impoundment, etc.). Impoundments were not structurally sound, impermeable, 3rd party protected, greater than 20" of seasonal high ground water table. In addition, the inspection found "failure to implement Special Protection BMPs for HQ or EV stream." The pipelines were also found where they were not indicated and/or not located in the valid ESCGP-1and on stream w/o 105 permits. See the details attached. | 606150 | 102.4 - Failure to minimize accelerated erosion, implement E&S plan, maintain E&S controls. Failure to stabilize site until total site restoration under OGA Sec 206(c)(d) | |
1955612 | 2011-03-02 | Violation(s) Noted | I inspected this site on 03/02/2011 for ESCGP-1 (ESX10-125-0062) Major Modification Application (submitted on 01/13/2011). A deficiency letter was sent on 01/21/2011, but the response on 02/22/2011 didn't include all information related with the deficiencies. However, I found the site constructions were different from the drawings (plans) originally issued on 08/16/2010 (e.g. pipeline, impoundment, etc.). Impoundments were not structurally sound, impermeable, 3rd party protected, greater than 20" of seasonal high ground water table. In addition, the inspection found "failure to implement Special Protection BMPs for HQ or EV stream." The pipelines were also found where they were not indicated and/or not located in the valid ESCGP-1and on stream w/o 105 permits. See the details attached. | 606151 | 102.4HQBMP - Failure to implement Special Protection BMPs for HQ or EV stream. | |
1955612 | 2011-03-02 | Violation(s) Noted | I inspected this site on 03/02/2011 for ESCGP-1 (ESX10-125-0062) Major Modification Application (submitted on 01/13/2011). A deficiency letter was sent on 01/21/2011, but the response on 02/22/2011 didn't include all information related with the deficiencies. However, I found the site constructions were different from the drawings (plans) originally issued on 08/16/2010 (e.g. pipeline, impoundment, etc.). Impoundments were not structurally sound, impermeable, 3rd party protected, greater than 20" of seasonal high ground water table. In addition, the inspection found "failure to implement Special Protection BMPs for HQ or EV stream." The pipelines were also found where they were not indicated and/or not located in the valid ESCGP-1and on stream w/o 105 permits. See the details attached. | 606152 | 105.11 - Water obstruction or encroachment constructed, operated, maintained, modified, enlarged or abandoned without a 105 permit. | |
1955612 | 2011-03-02 | Violation(s) Noted | I inspected this site on 03/02/2011 for ESCGP-1 (ESX10-125-0062) Major Modification Application (submitted on 01/13/2011). A deficiency letter was sent on 01/21/2011, but the response on 02/22/2011 didn't include all information related with the deficiencies. However, I found the site constructions were different from the drawings (plans) originally issued on 08/16/2010 (e.g. pipeline, impoundment, etc.). Impoundments were not structurally sound, impermeable, 3rd party protected, greater than 20" of seasonal high ground water table. In addition, the inspection found "failure to implement Special Protection BMPs for HQ or EV stream." The pipelines were also found where they were not indicated and/or not located in the valid ESCGP-1and on stream w/o 105 permits. See the details attached. | 606153 | 102.11 - Failure to design, implement or maintain BMPs to minimize the potential for accelerated erosion and sedimentation. | |
2011277 | 2011-10-07 | No Violations Noted |
For data sources see[3]