X

Track changes made to this page

If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.



Privacy policy
Close this window

powered by ChangeDetection

37-063-35167

Well Details

Well ID: 37-063-35167
Loading map...
County: Indiana
Municipality: Center Township
Operator Name: XTO ENERGY INC
Well Pad ID:
Farm/Lease Name: GAMBLE 8226
First Permit Date: 2006-12-12
Last Permit Date: 2006-12-12
Spud Date: 2007-02-24
Unconventional: No
Horizontal: No
Well Status: ACTIVE
Violations: 1
Latitude: 40.52152
Longitude: -79.113775

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
2006-0 0.0 0.0 0.0 0.0 0.0 0.0
2007-0 510.0 63.0 0.0 0.0 0.0 0.0
2008-0 133.0 365.0 0.0 0.0 0.0 0.0
2009-0 170.0 365.0 0.0 0.0 0.0 0.0
2010-0 318.0 365.0 0.0 0.0 0.0 0.0
2011-0 352.0 365.0 0.0 0.0 0.0 0.0
2012-0 92.0 366.0 0.0 0.0 0.0 0.0
2013-0 68.0 365.0 0.0 0.0 0.0 0.0
2014-0 33.0 327.0 0.0 0.0 0.0 0.0

For data sources see[1]

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE
2008-0 BRINE 50.0 Bbl BRINE OR INDUSTRIAL WASTE TREATMENT PLT PA0095273 FLUID RECOVERY SERVICE JOSEPHINE FACILITY JOSEPHINE PA
2010-0 PRODUCED FLUID 40.0 Bbl CENTRALIZED TREATMENT PLANT FOR RECYCLE PA0095273 FLUID RECOVERY SERVICE JOSEPHINE FACILITY JOSEPHINE PA
2013-0 PRODUCED FLUID 41.0 Bbl CENT WASTE TRT FAC NPDES DISCHARGE PA0095273 FLUID RECOVERY SERVICE JOSEPHINE FACILITY JOSEPHINE PA

For data sources see[2]

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION_COMMENT
1794193 2009-04-16 No Violations Noted Well site appears to be in production. No evidence of accelerated erosion and sedimentation noted on the access road. Brine Tank located on-site is in sound condition. Several concerns were noted during the inspection:

1- The old silt fence is still on-site. The area is well vegetated and the silt fence is no longer needed, so it should be removed. 2- There is an area adjacent to the brine tank where the ground is bare. Seeding and mulching the area is recommended.


1894873 2010-06-15 Violation(s) Noted Johnathon Longwill and Adriene Smochek from Representative Dave Reed's office on site during inspection.

Well tag in place. Access road stable, with no signs of accelerated erosion. Site is stabilized with adequate vegetation. No signs of accelerated erosion on site. Inspection revealed the following deficiencies:

 1)  Discharge of brine to the ground. -  Fluids were found to be leaking at a union joint on the pipe between the seperator and the 
      production fluids tank.  Fluids were found puddled under the leak.  Moist areas with dead vegetation began at this point and continued 
      down the site to just below the tank.  Source of leak needs corrected, contaminated soil must be removed, and affected areas limed, 
      fertilized, and seeded/mulched. 
590453 401CSL - Discharge of pollultional material to waters of Commonwealth.
1894873 2010-06-15 Violation(s) Noted Johnathon Longwill and Adriene Smochek from Representative Dave Reed's office on site during inspection.

Well tag in place. Access road stable, with no signs of accelerated erosion. Site is stabilized with adequate vegetation. No signs of accelerated erosion on site. Inspection revealed the following deficiencies:

 1)  Discharge of brine to the ground. -  Fluids were found to be leaking at a union joint on the pipe between the seperator and the 
      production fluids tank.  Fluids were found puddled under the leak.  Moist areas with dead vegetation began at this point and continued 
      down the site to just below the tank.  Source of leak needs corrected, contaminated soil must be removed, and affected areas limed, 
      fertilized, and seeded/mulched. 
590453 401CSL - Discharge of pollultional material to waters of Commonwealth.
1904553 2010-08-04 No Violations Noted Well tag in place. Well is equipped for production. Tank appears sound.

Access road stable, with no signs of accelerated erosion. Site is stabilized with adequate vegetation. No signs of accelerated erosion on site. NOV issued on 6/30/10 for discharge of brine to the ground. Compliance evaluation inspection revealed the following: Joint on pipe to the production fluids tank has been repaired/replaced. No signs of additional leak found. Area of discharge below the joint has been filled with rock. Contaminated soil from discharge has been removed, and replaced with fill material. This small area has been seeded and mulched. Site is in compliance. No further violaitons found.

For data sources see[3]

References