X

Track changes made to this page

If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.



Privacy policy
Close this window

powered by ChangeDetection

34-167-29736

Well Details

Well ID: 34-167-29736
Loading map...
County: Washington
Municipality:
Operator Name: BETHEL OIL & GAS CO
Well Pad ID:
Farm/Lease Name:
First Permit Date:
Last Permit Date:
Spud Date: 2014-05-08
Unconventional: No
Configuration: Vertical
Well Status: Drilling
Violations: 0
Latitude: 39.35236845
Longitude: -81.59454015

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
2014-0 28.0 89.0 0.0 89.0

For data sources see[1]

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION COMMENT
-110366428 2014-06-18 Witnessed drilling operations in progress. Total depth at the time of inspection was 699 ft. They are using a 10 in. bit to drill with. I spoke with the drillers on site. They will be running 8 in. casing as a working string soon.
1130566525 2014-06-24 I took Inspector LJ Parkins to the site to show him where it was at. Drillers were in the process of changing the drilling line. Current depth was at 700 ft.
-1142171407 2014-06-03 Witnessed company running 10 in. surface casing in the well. The joints were welded together. Good circulation was achieved while cementing the casing. Cement was present at the surface after plug was landed. No chlorides were detected in the mix water. Cement was weighed at 15.6 lbs. per gallon.
-1277372173 2014-07-21 Visited this location to check the status of cable tool drilling activities. Upon arrival, the bit depth was at approximately 1250'. Drilling is being done with an 8 bit. The rate of penetration is averaging about 20'/day.
-1303457804 2014-06-09 Witnessed drilling operations in progress. They have drilled through the plug and the shoe at the bottom of the surface casing. Total depth at the time of inspection was 320 ft. They are drilling with a 10 in bit. Spoke with drillers on site.
1400589546 2014-05-19 Status check on drilling operations. Total depth at the time of inspection was 100 ft. Spoke with drillers on site.
1401279172 2014-05-27 Status check on drilling operations. Total depth at the time of inspection was 185 ft. A 13 in bit was being used to drill. Spoke with drillers on site.
1402077330 2014-06-06 Witnessed pressure test on the surface casing. The test started at 9:39 am at 300 psi. and ended at 10:09 at 295 psi. Mr. Bob Lane was there on site. The test passed.
1403553555 2014-06-23 Total depth of hole at the time of inspection was 890 ft. 888 ft of 8 in. pipe was ran as a working string. Spoke to the drillers on site. They were changing the drill bit to an 8 in bit.
1404935015 2014-07-08 Visited location to check on status of drilling activities. The rig was not operating upon my arrival, and no one was on location. The depth indicator on the rig indicated that the hole was at 1093'.
1410808078 2014-09-15 Visited this location to pick up cement ticket from production string cement job and to check status of drilling activities. The 8 working string is currently being pulled from the hole. The cement will be drilled out of the bottom of the 4.5 production casing and the hole will be deepened into the Berea Sandstone in preparation for open hole completion.
-1423548474 2014-08-13 Visited this location to check on drilling operations for this well. The Bucyrus Erie 36L cable tool rig is currently drilling at 1639' with an 8 bit. Witnessed tripping-out of bit and then 3 bailer trips. Cuttings currently consist of grey sand and some shale/mudstone.
1489829748 2014-08-20 Cable tool rig is currently drilling at 1721' with an 8 bit. The rate of penetration has slowed significantly and is currently 15-20 ft/day. Witnessed 2 bailer trips and the cuttings are whitish-brown sand.
-1923133351 2014-05-12 The total depth at the time of inspection was 26 ft. Drillers were using a 13 in. bit. Spoke with drillers on site.
21250361 2014-08-28 Bucyrus-Erie 36L Cable Tool Rig currently drilling at 1803' with a 6 bit. Since last inspection, the 8 working string has been pulled, and 1750' of 7 working string is now in the well bore. Cuttings currently consist of sandstone and mudstone.
-890964459 2014-08-05 Visited this location to witness drilling operations and check on the depth of the hole. Upon arrival, the Bucyrus-Erie 36L cable tool rig was at 1527' and drilling with an 8 bit. Witnessed 3 bailer trips into the well bore to remove fluid and cuttings.
-897193631 2014-06-30 Observed cable tool rig drilling activities on this location. The bit depth was approximately 1020' upon arrival and 1030' upon departure. An 8 bit is being used and there is approximately 880' of 8 working string in the well bore. Observed the tripping out of the bit and two trips in with the bailer to remove cuttings and fluid.
911649682 2014-06-24 Accompanied Inspector Andy Thomas to observe drilling operations at this well location. Upon inspection, the rig crew was preparing to strip old drilling cable to replace it with new cable.
-970880193 2014-06-02 Inspected drilling operations in progress. Total depth at the time of inspection was 293 ft. The hole is 13 in. in diameter. Spoke with drillers on site.

For data sources see[2]

References

  1. "Ohio Department of Natural Resources RBDMS". [1]. 2015-06-19. Retrieved 2015-06-20. 
  2. "Ohio Department of Natural Resources RBDMS". [2]. 2015-06-19. Retrieved 2015-06-20.