34-045-21264

Well Details

Well ID: 34-045-21264
Loading map...
Country: United States
State: Ohio
County: Fairfield
Municipality: Clearcreek Township
Operator Name: MFC DRILLING INC
Well Pad ID:
Farm/Lease Name: ROUSH M
License Status: Final Restoration
License Date: 2017-01-24
Spud Date: 2000-07-05
Spud Drilling Contractor: MARIC DRILLING CO.
Final Drill Date: 2000-07-11
Well Total Depth: 3661 ft
Configuration: Vertical
Latitude: 39.595783853
Longitude: -82.75131407

For data sources see[1]

Well History

Well Status Well Status Date Comment
Original Spud 2000-07-05 DRY...WILL BE PLUGGED PER WCR
Completed 2000-07-11 DRY...WILL BE PLUGGED PER WCR
Reached Total Depth 2000-07-11 DRY...WILL BE PLUGGED PER WCR
APP 2000-07-14 Proposed Formations:ROSE RUN/TREMPEALEAU, Issued Date:7/14/00, Expired Date:7/14/01 6:00:00 AM, Drilling unit acres:40, Proposed Well Type:OG, Proposed Well Class:EW
Completion Report Received 2001-01-17 DRY...WILL BE PLUGGED PER WCR
APP 2009-06-18 Proposed Formations:ROSE RUN, Issued Date:6/18/2009, Expired Date:6/18/2010 6:00:00 AM, Drilling unit acres:40, Proposed Well Type:OG, Proposed Well Class:
APP 2014-05-01 Proposed Formations:ROSE RUN, Issued Date:5/1/2014, Expired Date:4/30/2016 12:00:00 PM, Drilling unit acres:40, Proposed Well Type:OG, Proposed Well Class:
APP 2017-01-24 Proposed Formations:ROSE RUN, Issued Date:1/24/2017, Expired Date:1/24/2019 12:00:00 PM, Drilling unit acres:40, Proposed Well Type:OG, Proposed Well Class:
Plugged/Abandoned 2017-05-10 DRY...WILL BE PLUGGED PER WCR
Construction Permit Expires 2019-01-24 DRY...WILL BE PLUGGED PER WCR
Record Last Modified 2019-02-13 DRY...WILL BE PLUGGED PER WCR

For data sources see[2]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2003 MFC DRILLING INC 52207 0 0
2004 MFC DRILLING INC 8248 0 365
2005 MFC DRILLING INC 2683 0 365
2006 MFC DRILLING INC 796 0 365
2007 MFC DRILLING INC 242 0 365
2008 MFC DRILLING INC 414 0 365
2009 MFC DRILLING INC 300 0 365
2010 MFC DRILLING INC 100 0 365
2011 MFC DRILLING INC 0 0 0
2012 MFC DRILLING INC 0 0 366
2013 MFC DRILLING INC 0 0 0
2016 MFC DRILLING INC 0 0 0
2017 MFC DRILLING INC 0 0 0

For data sources see[3] [4]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2003 MFC DRILLING INC Brine 0
2004 MFC DRILLING INC Brine 0 365
2005 MFC DRILLING INC Brine 0 365
2006 MFC DRILLING INC Brine 0 365
2007 MFC DRILLING INC Brine 0 365
2008 MFC DRILLING INC Brine 0 365
2009 MFC DRILLING INC Brine 0 365
2010 MFC DRILLING INC Brine 0 365
2011 MFC DRILLING INC Brine 0 0
2012 MFC DRILLING INC Brine 0 366
2013 MFC DRILLING INC Brine 0 0
2016 MFC DRILLING INC Brine 0 0
2017 MFC DRILLING INC Brine 0 0

For data sources see[5] [6]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
0864446325 2019-02-06 Final Restoration No Violations My inspection revealed the site meets requirements for final restoration. The area where the well was located is a hay field. There was no evidence of the well or any production equipment.
1494451616 2017-05-10 Plug / Plug Back No Violations The purpose of my inspection was to witness plugging operations. Cemenco Services Incorporated and Coshocton Pipe and Leasing were on location. The well is a Rose Run well with a total depth of 3660 feet, equipped with 20 pound per foot 8.625 inch diameter surface casing to a depth of 400 feet, and 10.5 pound per foot 4.5 inch diameter production casing to a depth of 3654 feet. The well was completed through the 4.5 inch production casing by setting perforations from 3573 feet to 3583 feet with 31 shots. During my inspection I witnessed Coshocton Pipe dig and line the pit and Cemenco rig up to the well. Fresh water was pumped ahead of a 250 foot of class A cement bottom Rose Run plug from 3376 feet to 3626 feet that was set through 2.375 inch diameter tubing. The plug was displaced to 3376 feet with fresh water. The 2.375 inch diameter tubing was tripped out of the hole to prepare to rip the 4.5 inch diameter production casing. The 4.5 inch diameter production casing was ripped at 2360 feet. The 4.5 inch diameter casing was pulled up to 2000 feet. Cemenco set a 250 foot Clinton plug through the 4.5 inch diameter casing from 2000 feet to 1750 feet using class A cement and 2% Gel. The Clinton plug was displaced to 1750 feet using fresh water. The 4.5 inch casing was pulled up to 1260 feet. Cemenco pumped a 150 foot Big Lime plug through the 4.5 inch diameter casing from 1260 feet to 1110 feet using class A cement with 2% gel. The plug was displaced with fresh water to 1110 feet. The 4.5 inch diameter casing was pulled up to 500 feet to set a 200 foot bottom of surface casing plug through the 4.5 inch diameter casing from 500 feet to 300 feet using class A cement with 2% gel. The plug was displaced with fresh water to 300 feet. The 4.5 inch diameter casing was pulled out of hole. Cemenco set a 100 foot plug to surface using class A cement with 2% gel. The plug stayed at surface.

For data sources see[7]