Well ID: 37-023-20230 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":41.597346,"lon":-78.362245,"icon":""}]} |
Country: United States | |
State: Pennsylvania | |
County: Cameron | |
Municipality: Shippen Township | |
Operator Name: SENECA RESOURCES CO LLC | |
Well Pad ID: 151525 | |
Farm/Lease Name: SRC WT 2354 250HU 52747 | |
License Status: | |
Spud Date: 2018-06-15 | |
Permit Date: 2018-03-09 | |
Well Type: GAS | |
Unconventional Well: Y | |
Configuration: Horizontal Well | |
Conservation: Yes | |
Latitude: 41.597346 | |
Longitude: -78.362245 |
Date | Event |
---|---|
Deviated | |
2018-03-09 | New Permit Application |
2018-06-05 | MOD |
2018-06-15 | Performed Spud Operation |
2019-01-27 | Drilling Completion |
For data sources see[4]
Period | Operator Name | Gas Quantity (mcf) | Gas Production Days | Oil Quantity (bbl) | Oil Production Days | Water Quantity (bbl) | Water Production Days |
---|---|---|---|---|---|---|---|
2019 | SENECA RESOURCES CO LLC | 890,137.36 | 158 | 0.00 | 0 | 0.00 | 0 |
For data sources see[5]
Period | Operator | Waste Type | Quantity | Disposal Method | Waste Facility ID |
---|---|---|---|---|---|
2018 | SENECA RESOURCES CO LLC | Other Oil & Gas Wastes | 50.77 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW005 |
2018 | SENECA RESOURCES CO LLC | Drill Cuttings | 1,044.26 Tons | LANDFILL | 100361 |
2019 | SENECA RESOURCES CO LLC | Waste Water Treatment Sludge | 74.57 Tons | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW005 |
2019 | SENECA RESOURCES CO LLC | Produced Fluid | 147,422.40 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW011 |
2019 | SENECA RESOURCES CO LLC | Synthetic Liner Materials | 122.85 Tons | LANDFILL | 100361 |
2019 | SENECA RESOURCES CO LLC | Drill Cuttings | 1,383.74 Tons | LANDFILL | 100361 |
2019 | SENECA RESOURCES CO LLC | Other Oil & Gas Wastes | 19.23 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW005 |
2019 | SENECA RESOURCES CO LLC | Other Oil & Gas Wastes | 18.33 Bbl | REUSE (AT WELL PAD) | |
2019 | SENECA RESOURCES CO LLC | Other Oil & Gas Wastes | 657.83 Bbl | RESIDUAL WASTE PROCESSING FACILITY | WMGR123NW011 |
For data sources see[6]
Inspection ID | Inspection Category | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|---|
2743463 | Primary Facility | 2018-06-19 | Routine/Complete Inspection | No Violations Noted | At the time of this inspection this well status was 120' of 20" conductor only. Well development is ongoing. No violations were noted at this inspection. |
2762018 | Primary Facility | 2018-08-09 | Routine/Complete Inspection | No Violations Noted | At the time of this inspection this well was a condutor only. This is scheduled to be the 6th Utica well drilled on this pad. No set date has been determined for the start of the drilling of this well at the time of this inspection. Justin Greene(drilling consultant) was at this inspection. No violations were noted at the time of this inspection. |
2765966 | Primary Facility | 2018-08-16 | Routine/Complete Inspection | No Violations Noted | Department representative Sue Herzing conducted a routine site inspection at Seneca Resources CRV Pad C08-X on August 16, 2018 with company man Justin Greene. The site sign, weekly E&S log, drilling permits, emergency response plan, and PPC plan were onsite for review.
There are currently 7 producing Marcellus wells located on the well pad. The operator is currently in the process of drilling 1 of 6 Utica wells. All six Uitca wells have been spud. The operator was is in the process of drilling Utica well 023-20235 using Patterson 328 Rig. The drilling depth was at approximately 6,650 ft. during the Departments inspection. The kick-off point is at 10,500 ft. with a total depth of 21,000 ft. All rig equipment, tanks, silos, diesel fuel tanks, oils, etc. have been placed on the primary rig timber mat containment. An additional layer of secondary containment separates all of the equipment listed above. Overall, the containment system looks great, no water was observed laying on the containment. A dedicated v |
2813473 | Primary Facility | 2018-12-11 | Routine/Complete Inspection | No Violations Noted | Department representative Sue Herzing conducted a routine site inspection at Seneca Resources CRV Pad C08-X on December 11, 2018. The site sign, weekly E&S log, drilling permits, emergency response plan, and PPC plan were onsite for review.
There are currently 7 producing Marcellus wells located on the well pad. The operator just finished drilling Utica well 023-2033 and then walked the Patterson 328 rig over to begin drilling on well 023-20230. Drilling on Utica well 033-20230 just began today (December 11, 2018). All rig equipment, tanks, silos, diesel fuel tanks, oils, etc. have been placed on timber rig mats serving as primary containment. An additional layer of secondary containment separates all of the equipment listed above and consists of geotextile and additional liners. Overall, the containment system looks great, no water was observed laying on the containment. A dedicated vacuum set system is stationed onsite within secondary containment. Freshwater is being trucked onsite and offloaded into |
2825288 | Primary Facility | 2019-01-10 | Routine/Complete Inspection | No Violations Noted | At the time of this inspection this well was being drilled. Kevin Deal, a drilling consultant was at this inspection. The drilling was started on 12-12-18 and drilling was not yet completed at the time of this inspection. The hole had been drilled to a TMD (total measured depth) of 21,919'. At the time of this inspection the Patterson 328 rig and crew were bringing the drill bit out of the hole and then were rigging up to run (advance) the last string of casing (5 1/2") into the hole and at that time this wells drilling will be complete. No determined set date was available as to when the drilling of this well would be completed. No violations were noted at this inspection. |
2830022 | Primary Facility | 2019-01-22 | Routine/Complete Inspection | No Violations Noted | At the time of this inspection the Patterson Rig 328 and crew were prepping to run ( advance) the final caring string of 21,878' (length) of 5 1/2" (size) production pipe. Kevin Deal, the drilling consultant , informed me that an approximate time frame between 9:00 pm 1-22-19 and 12:00 am 1-23-19 is the anticipated time of starting the advancement of the final string of pipe. Upon completion of the advancement of the 5 1/2" production casing the pipe will be cemented. No violations were noted at this inspection. |
2839509 | Primary Facility | 2019-02-13 | Routine/Complete Inspection | No Violations Noted | At the time of this inspection the drilling of this well had been completed. The Excel Rig #853 and crew were cleaning out the well in preparation for Hydraulic Fracturing (stimulation) to be done at a later date. Adam Pierce (Stimulation consultant) was at this inspection. No violations noted at this inspection. |
2850654 | Primary Facility | 2019-03-06 | Routine/Complete Inspection | No Violations Noted | Department representative Sue Herzing conducted a routine site inspection at Seneca Resources CRV Pad C08-X on March 6, 2019.
There are a total of 7 producing Marcellus wells located on this well pad. Each well is currently enclosed in a yellow cage. In addition, there are 6 recently drilled Utica wells on this pad. Each Utica well head is currently wrapped in black fabric. Adjacent to the Utica wells are 5 frac tanks stationed in secondary containment with a berm. Snow was observed within the containment system, There are 7 gas production units located on the E edge of the well pad. In addition, there are (5) 400 BBL produced fluids tanks stationed in a modular secondary cobtainment along the N edge of the well pad. Water within this containment is frozen and snow covered. Adjacent to the produced fluids containment are 20 manifolded frac tanks stationed in secondary containment with a berm. Snow was observed in the containment system. The well pad and surrounding areas are snow covered. E&S controls |
For data sources see[7]