Well Details

Well ID: 37-125-21401
Loading map...
Country: United States
State: Pennsylvania
County: Washington
Municipality: Canton Township
Operator Name: PENN ENERGY INC
Well Pad ID:
Farm/Lease Name: JOHN BARRON
License Status: Plugged and Abandoned
Spud Date: 1981-07-20
Permit Date: 1981-06-30
Well Type: COMB. OIL&GAS
Unconventional Well: N
Configuration: Vertical Well
Conservation: No
Latitude: 40.196656
Longitude: -80.309639

For data sources see[1][2][3]

Well History

Date Event
1981-06-30 New Permit Application
1981-07-20 Performed Spud Operation
1981-07-25 Drilling Completion
1982-08-13 Performed Stimulation
1986-07-12 Newly Drilled
2017-02-15 Begin Plugging
2017-03-14 Finished Plugging

For data sources see[4]

Stimulation Data

Stimulation Date Phase Number Chemical Agent Volume (gal) Treating Pressure (psi) Breakdown Pressure (psi)
1982-08-13 0 0 0

For data sources see[5]


Inspection Data

Inspections Performed

Inspection ID Inspection Category Inspection Date Inspection Type Inspection Result Inspection Comments
2526326 Primary Facility 2016-10-06 Routine/Complete Inspection Adverse Events or Actions Reported Met Range Resources personnel and Eric Peterson at site. Range uncovered a well that was drilled, fraced and abandoned by Penn Energy and later covered by ~ two feet of soil by landowner. Well is between homes, ~ 15 feet off Best Avenue, ~ 25 feet from mobile home @ 624 Best Ave. and ~ 50 feet from other mobile home. Only the top of the wellhead was exposed to reveal 1 1/2" nipple on top of a 4 1/2" balon valve (closed). Gas readings at base of valve were 5% gas and up to 100% LEL. Numerous test holes in surrounding yard revealed LEL levels as high as 5%. Gas tests from beneath adjacent mobile home were 0% LEL. Range, at DEP request installed a corrugated ventpipe around top of wellhead, filled in remainder of the hole, then fenced in the vent stack.
2527647 Primary Facility 2016-10-13 Routine/Partial Inspection Adverse Events or Actions Reported Inspected site to check gas levels in soil surrounding wellhead and from vent stack. Soil gas levels appear to have generally improved since the well was uncovered and the vent installed. Vent stack readings were 2-4% LEL. Numerous holes in yard surrounding the well and beside nearby trailer all yielded 0% LEL, with the exception of one test hole ~two feet from vent stack to the northwest, which initially pegged at 100% LEL, but leveled to ~4% LEL. Holes adjacent to this hole showed no gas/LEL.
2534628 Primary Facility 2016-10-24 Routine/Partial Inspection Adverse Events or Actions Reported Visited site after heavy rains to take stray gas readings. The venst stack yielded 0% LEL, either due to high ground saturations or winds. Got positive readings in test holes surrounding the vent stack, with sustained readings of 2-3% LEL north, south and west of the stack, 10 % sustained reading east of the stack. All readings were 0% LEL beside the mobile home to the south and 0% LEL toward the mobile home to the north.
2534630 Primary Facility 2016-11-02 Routine/Partial Inspection Adverse Events or Actions Reported Visited site to take stray gas readings. Vent stack was found to be venting with a sustained reading of 4% LEL. Only two test holes had positive gas readings. A hole west of the stack and a hole south of the stack had 2% LEL sustained readings. All other test holes were 0% LEL.
2547551 Primary Facility 2016-12-20 Routine/Partial Inspection No Violations Noted Met w/ representative from Yost Drilling to develop plan to excavate around well, blow down well and evaluate for venting/plugging.
2554659 Primary Facility 2017-01-24 Plugging(Includes Plugged/Mined Through) No Violations Noted Met with Town & Country property owners and Yost Drilling representatives to discuss plugging operations, location of equipment and communication with residents.
2565676 Primary Facility 2017-02-27 Plugging(Includes Plugged/Mined Through) No Violations Noted Well hot tapped and pressure relieved by flare. DEP on location with emergency responders and plugging OGI. NOVIO
2570951 Primary Facility 2017-03-08 Plugging(Includes Plugged/Mined Through) No Violations Noted Yost #2 finished POOH with 4 1/2" csg. Rigging up to RIH with tbg. NOVIO
2579257 Primary Facility 2017-02-27 Routine/Complete Inspection No Violations Noted performed overnight inspection of set monritoring points.
2579259 Primary Facility 2017-02-28 Routine/Complete Inspection No Violations Noted performed overnight inspection of set monitoring points
2579296 Primary Facility 2017-03-01 Routine/Complete Inspection No Violations Noted performed oversight of monitoring points.
2579298 Primary Facility 2017-03-02 Routine/Complete Inspection No Violations Noted performed monitoring of dedicated points.
2579299 Primary Facility 2016-03-03 Routine/Complete Inspection No Violations Noted performed monitoring of dedicated points.
2579302 Primary Facility 2017-03-04 Routine/Complete Inspection No Violations Noted performed monitoring of dedicated points
2579306 Primary Facility 2017-03-06 Routine/Complete Inspection No Violations Noted performed monitoring of dedicated points
2581614 Primary Facility 2017-03-13 Routine/Complete Inspection No Violations Noted Today I responded to a NRC report that a clean up crew and vac truck was observed cleaning up waste at 2800 Jefferson Avenue .

I made a stop at the Yost plugging site (John Barron 1) on top of the hill. No fluids or waste materials were on site. The well was plugged and Yost was breaking down the rig to move it off site. No violations observed.

2599509 Primary Facility 2017-01-30 Plugging(Includes Plugged/Mined Through) No Violations Noted Met w/Bialosky, Gustafson, Sabocheck & Keller from DEP and several representatives from Yost Drilling to discuss preparations and considerations to be ready for plugging to begin.
2599510 Primary Facility 2017-01-31 Plugging(Includes Plugged/Mined Through) No Violations Noted Met with a representative of Town & Country and Range Resources@ site. Talked to residents from each of the 6 homes within 100 feet of the wellhead to describe what plugging activities would be taking place. We let them know that it was recommended that they find another place to be during plugging procedures and offered alternatives.
2599512 Primary Facility 2017-02-03 Plugging(Includes Plugged/Mined Through) In Compliance with Schedule Visited wellsite to see is any work had been done to remove the mobile home that is closest to wellhead (The home has to be temporarily moved off location while plugging takes place, then returned when activities are completed.) It had not been moved yet.
2599513 Primary Facility 2017-02-06 Plugging(Includes Plugged/Mined Through) In Compliance with Schedule Visited site for progress. Trailer remains to be moved. Many of the underground utilities have been flagged. Received signed consent forms from all three property owners.
2599515 Primary Facility 2017-02-09 Plugging(Includes Plugged/Mined Through) In Compliance with Schedule No work has been done yet to move the mobile home closest to the wellhead.
2599519 Primary Facility 2017-02-13 Plugging(Includes Plugged/Mined Through) In Compliance with Schedule Work is being done on the mobile home in preparation to move it. Breezeway is being detached from the home and will be removed from the site, along with the home.
2599520 Primary Facility 2017-02-13 Plugging(Includes Plugged/Mined Through) In Compliance with Schedule Work continues on preparations to move mobile home closest to wellhead. The decking of breezeway will be removed now that roofing was removed.
2599521 Primary Facility 2017-02-14 Plugging(Includes Plugged/Mined Through) In Compliance with Schedule Trailer, breezeway deck and utility shed have all been removed from site.
2599525 Primary Facility 2017-02-15 Plugging(Includes Plugged/Mined Through) In Compliance with Policy Yost dug around wellhead to completely expose and evaluate for performing hot tap. The most noticeable leak is around the slips of the casinghead. Excavation continued around the wellhead, allowing a corrugated-pipe cellar to be installed. Yost rigged up the flare stack in the back of the location. Moody installed four monitor holes to test for soil gas.
2599526 Primary Facility 2017-02-16 Plugging(Includes Plugged/Mined Through) In Compliance with Policy Yost layed down rig mats, spotted water tank. Plumbed & opened up 8 5/8" to manifold/flare stack.No measurable pressure using high pressure gauge, some gas present, but quickly blew down.
2599532 Primary Facility 2017-02-17 Plugging(Includes Plugged/Mined Through) In Compliance with Policy No activity @ time of inspection. Earlier Yost spotted mud tank & mud pump. DEP Emergency Response van is set up above site on adjoining lot. Flare stack was lowered while not in use, on the request of the resident of a neighboring property to the rear of the site.
2599533 Primary Facility 2017-02-21 Plugging(Includes Plugged/Mined Through) In Compliance with Policy No activity until hot tap is performed next week. Checked for gas around site and in cellar. All readings were 0% LEL except for leak @ 4 1/2" casing collar, which was 30% LEL.
2599534 Primary Facility 2017-02-23 Plugging(Includes Plugged/Mined Through) In Compliance with Policy Pittsburgh Tire Service on site replacing a tire on Yost forklift. No other activity on site. Took gas readings around site (air only), all 0% LEL, including cellar air. Measured 30-38% LEL @ 4 1/2" casing head and collar leaks. Weather is warm, partly sunny w/ a mild breeze.
2599572 Primary Facility 2017-02-27 Plugging(Includes Plugged/Mined Through) In Compliance with Policy Extreme Machining Services & Elite Midstream Services were on site to perform the hot tap. They began rigging up @ 8:00 AM, strapped the valved saddle onto the 4 1/2" swage, nippled up the tap to the manifold/flare stack and successfully tapped the well. The well had ~850 psi when tapped. Flaring began at 9:40 AM and was completed by 10:36 AM. The hole was loaded at first through the tap. Later a new balon valve was added to the balon valve on top of the swage, the water line was nippled up on it and loading the hole continued. The well was topped off @ 4:30PM using a total of 45 bbl to load the hole. A light film of oil was noted on the top of water.
2599576 Primary Facility 2017-02-28 Plugging(Includes Plugged/Mined Through) In Compliance with Policy Yost gauged 40 PSI on the well after overnight shut-in, disconnected the well from the manifold/flare stack and plumbed the well to the steel pit. The well flowed water, oil & gas to the pit, sputtering & dying several times, then flowed again, for a total return of several bbl. The hole was then reloaded. Yost brought rig & doghouse on site & rigged up. BOP was installed.
2599579 Primary Facility 2017-03-01 Plugging(Includes Plugged/Mined Through) In Compliance with Policy TIMCO on location before 8:00 AM, rigged up & ran GR, CCL, Bond & VDL. Found 4 1/2" casing well-cemented to TOC @ 2380'. Logger TD=5255'. Possible perfs (?): 5188'-5207' (?), 4620'-4623', 4651'-4652' (?). There may be other perfed intervals uphole, but the CCL shows a lot of scale or noise in those sections. Yost began to run cement string; got ~ 1300' in hole before shutting down for the day.
2599582 Primary Facility 2017-03-02 Plugging(Includes Plugged/Mined Through) In Compliance with Policy Yost ran cement string all AM, Formation Cementing arrived before 1:00 PM. Yost got tubing down to 5281' where they met hard resistence. Formation nippled up and circulated ~80 bbl water to flush hole. Pumped 300 foot (calculated) bottom hole plug, 5281' to 4981'. Finished pumping 23 sacks @ 4:15 PM. Pulled 15 joints of tubing, flushed and shut down for day.
2599584 Primary Facility 2017-03-03 Plugging(Includes Plugged/Mined Through) In Compliance with Policy Yost tried to move cement string, but it was cemented-in. When they pulled 20% over string weight, the rig mats sank into the mud, so they shut down operations, released cementers and moved rig off of mats to add add'l mats. After add'l mats were added, rig was moved back over well. Nippled up a pump on tubing & pumped 300# pressure while puling-releasing-pulling-releasing repeatedly. Could not break tubing free or establish circulation. Shut down.
2599586 Primary Facility 2017-03-04 Plugging(Includes Plugged/Mined Through) In Compliance with Policy TIMCO ran in hole w/CCL + biwire w/ one shot, set down @ 4556', shot one hole @4540 (to pump through to confirm circulation). TOOH, Yost rigged up pump truck & established circulation. TIMCO TIH w/ collar-buster & shot tubing collar @ 4528' (Correlates to 4519' on GR/CCL/Bond log that was zeroed @ GL instead top of tubing today). Yost pulled tubing free & pulled/layed down tubing.
2599590 Primary Facility 2017-03-05 Plugging(Includes Plugged/Mined Through) In Compliance with Policy (Plan is to set a Cast Iron Bridge Plug as deep as possible, then cement to surface) TIMCO TIH w/ casing gauge before TIH w/ CIBP. Casing was clear, so TIMCO TIH w/ CIBP to 4500' & set. Yost began running cement string by 10:00 AM. By 2:40 PM they tagged the bridge plug @ 4503' - held.
2599593 Primary Facility 2017-03-06 Plugging(Includes Plugged/Mined Through) In Compliance with Policy Yost fabricated a 15' tubing sub so they could spot cement right on top of the CIBP. Formation was on location @ 8:25 AM, started pumping initial cement plug @ 4503' CIBP by 9:00 AM. A solid cement plug was pumped in 5 stages, with the final plug spotted by 1:20 PM @ ~2386' TOC (calculated). Pulled cement string to 2386' & flushed until ~ 2:00 PM, then TOOH w/ cement string.
2602603 Primary Facility 2017-03-07 Plugging(Includes Plugged/Mined Through) In Compliance with Policy Yost removed BOP from 4 1/2" casing. TIMCO rigged up, TIH & tagged TOC plug @ 2386 feet (as calculated). Successfully shot collar buster on 4 1/2" @ 2356 feet. Yost began pulling 4 1/2" casing @ 10:30 AM. Joints were very tight. They pulled 35 joints by wrenching and determined that power tongs were necessary. Shut down @ 4:00 PM.
2602606 Primary Facility 2017-03-08 Plugging(Includes Plugged/Mined Through) In Compliance with Policy Yost used power tongs to finish pulling 4 1/2" casing. Pulled remaining joints by 9:30 AM. TIMCO rigged up after 11:00 AM, logged the 8 5/8" casing. Bond log showed areas that lacked velocity readings that loggers interpreted as good bond. Had conference call w/ Harrisburg DEP to discuss interpretation and concluded casing had good cement to surface so OK to cement to surface.
2602607 Primary Facility 2017-03-09 Plugging(Includes Plugged/Mined Through) In Compliance with Policy Formation Cementing pumped a total of 5 cement plugs, cementing the 8 5/8" casing to surface. Last plug was finished by 1:55 PM. Some oil was circulated off bottom while spotting the first plug. Returns circulated w/o oil once additional fresh water was added and oily water was pumped to pit.
2602609 Primary Facility 2017-03-13 Plugging(Includes Plugged/Mined Through) In Compliance with Policy Yost has rig and most of the equipment demobilized from site, w/ flare stack, water tank, mud pump & rig mats remaining. The monument was set on wellhead. Yost representative was on site. While demobilizing, Yost truck snagged overhead phone/cable lines near the entrance to the mobile home park, breaking the pole. The damage was quickly reported. Repair crew was on site @ 9:30 AM to make repairs.
2602611 Primary Facility 2017-03-13 Plugging(Includes Plugged/Mined Through) In Compliance with Policy Repairs (pole replaced) to utility pole damaged by Yost demob were complete by noon. Yost representative was @ site.
2602617 Primary Facility 2017-03-14 Plugging(Includes Plugged/Mined Through) In Compliance with Policy Yost has all pads lifted and stacked to be removed, with some already removed. Cellar pipe has been pulled and cellar is ready for fill.
2602619 Primary Facility 2017-03-17 Plugging(Includes Plugged/Mined Through) In Compliance with Policy Yost has site graded, seeded & mulched. Some minor touch-ups remain. Damaged drain across the road from site has been repaired, but no concrete or paving done yet. Met w/ representative of the trailer park to discuss site restoration.
2602633 Primary Facility 2017-03-21 Plugging(Includes Plugged/Mined Through) In Compliance with Policy Mobile home is being moved back onto location at time of inspection.
2602635 Primary Facility 2017-03-22 Plugging(Includes Plugged/Mined Through) In Compliance with Policy Mobile home is back in place on site. Checked inside of monument for gas; none detected. Installed tee on monument vent to prevent rainwater fillup.
2602636 Primary Facility 2017-06-05 Plugging(Includes Plugged/Mined Through) In Compliance with Policy Site restoration looks good with area grassed-in completely. Mobile home & breezeway that was temporarily removed during plugging operations looks fully restored and shed is back in place. Discussed site restoration w/ park representative. He is pleased with results, with no additional requirements.
2608927 Primary Facility 2017-02-21 Plugging(Includes Plugged/Mined Through) In Compliance with Schedule Visited site, updated owner as to timing of upcoming activities on the site.
2612815 Primary Facility 2017-06-29 Plugging(Includes Plugged/Mined Through) In Compliance with Policy Visited site to do final gas checks at monitor holes, then remove liner piping and cones. The southern monitor hole liner piping was apparently removed when the mobile home was brought back on site. The north, west and east monitor holes remained. All three monitor holes tested 0% LEL. The vent on the monument also tested 0% LEL. Piping & cones were removed, leaving no further action required at site.
2776915 Primary Facility 2018-09-19 Routine/Partial Inspection No Viols - Permanently Shut Down Visit site of this plugged well to check status of monument, condition of restoration. All appears well.
766616 Primary Facility 1994-08-17 Routine/Complete Inspection Violation(s) Noted ABD; NO TAG/BOND/PROD RECORD

Violations Commited

Inspection ID Violation ID Violation Date Date Resolved Violation Code Violation Type Violation Comments
766616 103857 08/17/1994 1994-08-17 210A - Failure to adequately plug or schedule plugging of a well upon abandonment Administrative ABANDONED & UNPLUGGED
766616 103858 08/17/1994 1994-08-17 212301 - Failure to file annual production report on each well or gas storage maps & information Administrative NO PRODUCTION RECORD
766616 103859 08/17/1994 1994-08-17 201TAG - Failure to install, in a permanent manner, the permit number on a completed well Administrative NO TAG PERMIT #
766616 103860 08/17/1994 1994-08-17 215 - Failure to bond well, replace or maintain bond Administrative NO BOND

For data sources see[6]

References

  1. "Permits Issued Detail Report". Pennsylvania Department of Environmental Protection. 2019-05-20. Retrieved 2019-05-21. 
  2. "Spud Data Report". Pennsylvania Department of Environmental Protection. 2019-04-30. Retrieved 2019-05-16. 
  3. "Oil and Gas Well Pad Report". Pennsylvania Department of Environmental Protection. 2019-05-20. Retrieved 2019-05-21. 
  4. "Compiled from multiple data sources - see Pennsylvania Oil and Gas Data Sources". 2020-02-27. Retrieved 2020-02-27. 
  5. "Completion Reports - Stimulations". Pennsylvania Department of Conservation and Natural Resources. 2020-03-02. Retrieved 2020-03-02. 
  6. "Oil and Gas Compliance Report". Pennsylvania Department of Environmental Protection. 2019-05-20. Retrieved 2019-05-21.