Well ID: 34-151-25818 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":40.84,"lon":-81.18,"icon":""}]} |
Country: United States | |
State: Ohio | |
County: Stark | |
Municipality: Washington Township | |
Operator Name: ENERVEST OPERATING LLC | |
Well Pad ID: | |
Farm/Lease Name: SCHMUCKER E | |
License Status: Producing | |
License Date: 2012-10-24 | |
Spud Date: 2012-12-07 | |
Spud Drilling Contractor: PEP DRLG | |
Final Drill Date: 2012-12-13 | |
Well Total Depth: 5387.00 ft | |
Configuration: Vertical | |
Latitude: 40.840000 | |
Longitude: -81.180000 |
For data sources see[1]
Well Status | Well Status Date | Comment |
---|---|---|
APP | 2012-10-24 | Proposed Formations:OHIO SHALE THRU CLINTON, Issued Date:10/24/2012, Expired Date:10/24/2014 12:00:00 PM, Drilling unit acres:59.84, Proposed Well Type:OG, Proposed Well Class:POOL |
Original Spud | 2012-12-06 | |
Reached Total Depth | 2012-12-13 | |
Completion Report Received | 2013-02-07 | |
Construction Permit Expires | 2014-10-24 | |
Record Last Modified | 2017-10-23 |
For data sources see[2]
Perforation Date | Interval Top (ft) | Interval Base (ft) | Number of Shots |
---|---|---|---|
2013-02-08 | 5126 | 5177 | 39 |
5126 | 5177 | 39 | |
5126 | 5177 | 39 |
For data sources see[3]
Stimulation Date | Chemical Agent | Chemical Agent Concentration (%) | Fracking Fluid Volume | Mass of Proppant Used (lb) | Fracking Company | Comments |
---|---|---|---|---|---|---|
2013-01-03 | H2O | 0 | 175587 Gal | 0 | Superior Well Services | I inspected the hydraulic fracturing operations at the Schmucker E 2 (34151258180000) site on January 3, 2013. My inspection found Superior Well Services was contracted by Enervest Operating LLC to complete the hydraulic fracturing of the well. The job started at 08:28 and ended at 11:02 with an average operating pressure of 1900 psi. The average slurry rate was 35.1 bbls of water per minute. A total of 175,587 gallons of water was used to complete the operation. |
For data sources see[4]
Period | Operator Name | Gas Quantity (mcf) | Oil Quantity (bbl) | Production Days |
---|---|---|---|---|
2013 | ENERVEST OPERATING LLC | 2782.00 | 2870.00 | 354 |
2014 | ENERVEST OPERATING LLC | 1618.00 | 1087.00 | 365 |
2015 | ENERVEST OPERATING LLC | 1304.00 | 755.00 | 365 |
2016 | ENERVEST OPERATING LLC | 798.00 | 509.00 | 366 |
2017 | ENERVEST OPERATING LLC | 794.00 | 584.00 | 365 |
2018 | ENERVEST OPERATING LLC | 429.00 | 448.00 | 365 |
Period | Operator Name | Waste Type | Quantity (bbl) | Production Days |
---|---|---|---|---|
2013 | ENERVEST OPERATING LLC | Brine | 2156 | 354 |
2014 | ENERVEST OPERATING LLC | Brine | 478 | 365 |
2015 | ENERVEST OPERATING LLC | Brine | 410 | 365 |
2016 | ENERVEST OPERATING LLC | Brine | 195 | 366 |
2017 | ENERVEST OPERATING LLC | Brine | 133 | 365 |
2018 | ENERVEST OPERATING LLC | Brine | 37 | 365 |
Inspection ID | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|
-1471277665 | 2012-12-11 0:00 | DD | No Violations | 1.00 |
-1614507625 | 2018-6-28 0:00: | PW | No Violations | 0.50 |
-1760468407 | 2012-12-8 0:00: | DD | No Violations | 1.00 |
-768739485 | 2015-9-29 0:00: | PL | No Violations | 1.50 |
0295427286 | 2012-12-10 | Drill / Deepen / Reopen | No Violations | I inspected the drilling operations at the Schmucker E 2 (34151258180000) site on December 10, 2012. The drilling contractor for this well is PEP Drilling Inc., rig number 10. My inspection found an operator sign at the entrance to the site. The access road is graveled from Paris Avenue to the well site. Silt fencing is in good condition. The working pit and blow pit are located to the south of the wellhead; soil berms are being utilized to isolate the pits. The working pit has 5 feet of free board and the blow pit has 3 feet of free board. The pits are cordoned off with safety fencing. PEP is drilling a 7.875 inch borehole and the current depth is 2289 feet. The blow out preventer and rotating air head are in place and PEP is drilling on air while soaping. The cellar is lined. The blow out preventer was tested and held 500 psi for 15 minutes without a loss of pressure. Herb is the driller on duty. A copy of the permit is located in the dog house. The Berea Formation was wet but did not make lots of water. |
0768739485 | 2015-09-29 | Preliminary Restoration | No Violations | I was on location to pass preliminary restoration for this well. The lease road is gravel, stable and has a gate. The electrically driven pumpjack has all required valves and gauges and is identified. The tank battery is surrounded by a dike and contains a vertical separator, 210bbl production tank, poly brine tank and a chart box. The roadway, tank battery and wellhead all conform to spacing requirements. The wellhead and tank battery are properly identified. The location has been reclaimed and vegetation has been established. At this time preliminary restoration has been passed. |
1239852788 | 2012-12-13 | Drill / Deepen / Reopen | No Violations | I inspected the drilling operations at the Schmucker E 2 (34151258180000) site on December 13, 2012. The drilling contractor for this well is PEP Drilling Inc., rig number 10. My inspection found an operator sign at the entrance to the site. The access road is graveled from Paris Avenue to the well site. Silt fencing is in good condition. The working pit and blow pit are located to the south of the wellhead; soil berms are being utilized to isolate the pits. The working pit has 4 feet of free board and the blow pit has 3 feet of free board. The pits are cordoned off with safety fencing. PEP drilled a 7.875 inch borehole to a total depth of 5387 feet. The blow out preventer and rotating air head are in place and PEP is circulating on the hole. The cellar is lined. Herb is the driller on duty. A copy of the permit is located in the dog house. The top of the Clinton Formation was recorded at 5119 feet and the top of the Queenston Formation at 5299 feet. |
1355767912 | 2012-12-07 | Drill / Deepen / Reopen | No Violations | I inspected the drilling operations at the Schmucker E 2 (34151258180000) site on December 7, 2012. The drilling contractor for this well is PEP Drilling Inc., rig number 10. My inspection found an operator sign at the entrance to the site. The access road is graveled from Paris Avenue to the well site. Silt fencing has been installed northeast of the wellhead, parallel to the unnamed stream. The working pit and blow pit are located to the south of the wellhead; soil berms are being utilized to isolate the pits. The working pit has 8 feet of free board and the blow pit is lined but empty. The pits are cordoned off with safety fencing. PEP drilled a 17.5 inch borehole to a depth of 137 feet and was setting 11.75 inch conductor casing and cementing to surface. The blow out preventer and rotating air head were not in place; PEP is set up to drill on fluid. Herb is the driller on duty. A copy of the permit is located in the dog house. |
1357237411 | 2013-01-03 | Drill / Deepen / Reopen | No Violations | I inspected the hydraulic fracturing operations at the Schmucker E 2 (34151258180000) site on January 3, 2013. My inspection found Superior Well Services was contracted by Enervest Operating LLC to complete the hydraulic fracturing of the well. The job started at 08:28 and ended at 11:02 with an average operating pressure of 1900 psi. The average slurry rate was 35.1 bbls of water per minute. A total of 175,587 gallons of water was used to complete the operation. |
1471277665 | 2012-12-11 | Drill / Deepen / Reopen | No Violations | I inspected the drilling operations at the Schmucker E 2 (34151258180000) site on December 11, 2012. The drilling contractor for this well is PEP Drilling Inc., rig number 10. My inspection found an operator sign at the entrance to the site. The access road is graveled from Paris Avenue to the well site. Silt fencing is in good condition. The working pit and blow pit are located to the south of the wellhead; soil berms are being utilized to isolate the pits. The working pit has 4 feet of free board and the blow pit has 3 feet of free board. The pits are cordoned off with safety fencing. PEP is drilling a 7.875 inch borehole and the current depth is 3945 feet. The blow out preventer and rotating air head are in place and PEP is drilling on air while soaping. The cellar is lined. Herb is the driller on duty. A copy of the permit is located in the dog house. The top of the Big Lime was recorded at 3224 feet. |
1614507625 | 2018-06-28 | Production Wells | No Violations | I did a status check inspection for this well. The well is equipped with a pumpjack. The tank battery consists of a steel production tank, a plastic brine tank, a vertical separator and a meter. The well is legibly identified. No Compliance issues are cited at this time. |
1760468407 | 2012-12-08 | Drill / Deepen / Reopen | No Violations | I inspected the drilling operations at the Schmucker E 2 (34151258180000) site on December 8, 2012. The drilling contractor for this well is PEP Drilling Inc., rig number 10. My inspection found an operator sign at the entrance to the site. The access road is graveled from Paris Avenue to the well site. Silt fencing is in good condition. The working pit and blow pit are located to the south of the wellhead; soil berms are being utilized to isolate the pits. The working pit has 4 feet of free board and the blow pit has 4 feet of free board. The pits are cordoned off with safety fencing. PEP drilled an 11 inch borehole to a depth of 607 feet and was setting 8.625 inch surface casing and cementing to surface. The blow out preventer and rotating air head were not in place, but PEP did use an air body attached to the 11.75 inch conductor casing to drill on air and fresh water. Herb is the driller on duty. A copy of the permit is located in the dog house. |
295427286 | 2012-12-10 0:00 | DD | No Violations | 1.00 |
For data sources see[9]