INSPECTION ID
|
DATE
|
DESCRIPTION
|
COMMENT
|
VIOLATION ID
|
VIOLATION CODE
|
VIOLATION_COMMENT
|
-1186889465
|
2008-12-17
|
|
Status check inspection found no violations at this time.
|
|
|
|
-1284440370
|
2008-03-31
|
|
Quarterly status inspection found no violations at this time. I did call Dave Ballentine and requested that he attend to several housekeeping issues around the loading pad and tank battery.
|
|
|
|
-1310867745
|
2003-07-17
|
|
Status check inspection - the needle valves on both the injection and annular sides are heavily corroded and need to be replaced.
|
|
|
|
-1390280194
|
2006-02-28
|
|
Salt water disposal well quarterly status check. No violations at this time.
|
|
|
|
-1520455209
|
2011-06-14
|
|
Quarterly status check inspection found no violations at this time. The company pressure gauge on the annulus was broken but could not be removed to check the annulus pressure. I asked B&B to replace the gauge.
|
|
|
|
-1618852364
|
2013-09-25
|
|
My inspection of the well and injection facility found no violations.
|
|
|
|
-1794938019
|
2002-04-24
|
|
FOLLOW UP TO NOV # 18 Inspectors Claus and Worstall checked UIC pressures and inspected the facility. The injection system was operating during the inspection. Met with landowner/operator (Mr. Ferrara) and requested a general improvement in housekeeping practices.
|
|
|
|
-1814706466
|
2006-12-11
|
|
Quarterly status inspection found no violations at this time.
|
|
|
|
-1894009940
|
2013-06-12
|
|
My inspection of the well and surface facility found no violations.
|
|
|
|
-198723090
|
2004-02-19
|
|
Status check inspection - no violations at this time. Could not get an annular pressure due to valve frozen or seized. Both the tank battery and the well have proper identification. 180# injection.
|
|
|
|
-2001721559
|
2009-03-03
|
|
Quarterly status check inspection found general housekeeping issues at this time. The concrete vault connected to the slit drain in the unloading pad is full and needs to be pumped. Used sock filters need to be picked up inside of the pump house. A pressure valve failed at the wellhead and sprayed a small 3x3 area. The impacted vegetation needs to be removed and the valve replaced.
|
|
|
|
-2059817421
|
2009-09-10
|
|
Status check inspection found that the injection and annulus pressures are still close but not equalized. I still could not verify the injection pressure with the MRM gauge.
|
|
|
|
-258088677
|
2008-08-25
|
|
Quarterly status check inspection found no violations at this time. The well is operating below the maximum allowable injection pressure.
|
|
|
|
-275704762
|
2010-09-11
|
|
Heagan successfully recovered the remaining 2-3/8" tubing and the old packer. On this morning Heagan ran a reconditioned Halliburton R-4 packer on a string of 2-7/8" tubing. I witnessed the packer going in the hole and Inspector Roberts witnessed the MIT. After the packer reached setting depth, five gallons of inhibitor was mixed with 80 bbl of fresh water and the mixture was pumped down the tubing and up through the annulus until the inhibitor mixture circulated to surface. The packer was set in tension at 4118.5 by pulling 15,000# over string weight. The annulus was pressured up to 1198 psi. After 15 minutes, the annulus pressure had fallen to 1181 psi for a total loss of 17 psi. The pressure loss was well below the allowed loss of 60 psi. The MIT was successful and the Compliance Notice is resolved.
|
|
|
|
-288464133
|
2014-01-10
|
|
Service rig was running into the well in order to tag bottom. No violations were found.
|
|
|
|
-314001160
|
2005-08-23
|
|
Status check inspection - no violations at this time. I spoke with Dave Ballentine about cleaning up the tank battery and maintenance around the wellhead. He stated that he intended to complete the tank battery and maintenance work this fall.
|
|
|
|
-421507322
|
2012-03-28
|
|
No violations were found at the time of inspection.
|
|
|
|
-462622723
|
2006-05-02
|
|
Status check inspection found no violations at this time. I did talk to Dave Ballentine and told him to reclaim the disturbed area around the wellhead, replace the damaged ID sign and paint the tank battery.
|
|
|
|
-463305106
|
2014-01-13
|
|
I was on location with Inspector Steve Ochs to observe workover operations on this well. The operator discovered that there was a hole in the 4.5" casing and were running a bond log to find the top of the cement. Their plan was to run in with tubing and a packer and pressure test zones to find the hole. No violations.
|
|
|
|
-568161232
|
2004-08-12
|
|
Salt water disposal well - no violations at this time. I will contact Twinoaks regarding a replacement schedule for three of the four 210 bbl tanks. The tanks are deteriorating and need attention.
|
|
|
|
-583967160
|
2014-01-16
|
|
The service rig was drilling out the composite bridge plug. All conditions were acceptable.
|
|
|
|
-590102265
|
2005-02-25
|
|
Status check inspection of this salt water disposal well and storage system. No violations at this time.
|
|
|
|
-610490657
|
2009-11-17
|
|
Quarterly status check inspection found no violations at this time.
|
|
|
|
-67125542
|
2006-08-30
|
|
Quarterly status check inspection. No violations at this time.
|
|
|
|
1014468226
|
2010-08-31
|
|
Quarterly status check inspection found that the injection pressure and annulus pressure had equalized at 680 psi. The injection pump was running at the time. I contacted Dave Ballentine and told him of the problem and requested that the system be shut down until the problem can be corrected. He will schedule a MIT as soon as possible.
|
|
|
|
1078078730
|
2009-08-27
|
|
Status check inspection found the injection pressure and the annulus pressure nearly equal. The injection pressure could not be verified with the MRM issued gauge due to the fact that the B&B gauge could not be removed. I advised the company that the pressures would be rechecked next week and if they remained nearly equal or equal, a MIT would be required.
|
|
|
|
1101777927
|
2004-11-18
|
|
I received a call from Red Davis with Twinoaks informing me that this disposal well has been sold to B&B Oilfield Services (Dave Ballentine). I spoke with Dave Balentine and told him what was necessary to get this well back into operation. The leaking 210 bbl storage tanks need to be repaired or replaced and the pump house needs cleaned out. Ballentine said that he planned to replace three 210 bbl tanks with two 300 bbl horizontal tanks.
|
|
|
|
1130949139
|
2005-10-24
|
|
Witnessed pulling, reconditioning, and running Halliburton R-4 packer. Witnessed MIT on the packer. Test passed.
|
|
|
|
1135263691
|
2005-12-06
|
|
Completed a MIT on the 2" injection line from the pump house to the wellhead. The test was conducted with Barton Well Service. The initial shut in pressure was 1180 psi, after 5 minutes the pressure was 1180 psi and after 15 minutes, the pressure was 1180 psi. The injection line passed the MIT.
|
|
|
|
1189627869
|
2007-08-30
|
|
Quarterly status check inspection found no violations at this time.
|
|
|
|
1212092734
|
2008-05-21
|
|
Quarterly status check inspection found no violations at this time.
|
|
|
|
1216i33
|
2001-11-07
|
|
No violations noted this date. Last inspection: 09-12-2001
|
|
|
|
1284377435
|
2010-09-11
|
|
I witnessed the running in the hole with 2 7/8" tubing. The tubing length is 4115.55'. The B & B pump truck pumped 63 barrels of fresh water with Halliburton corrosion inhibitor AN HIBII. The Halliburton R-4 packer was set at 4118.55' in 15,000# tension. The annulus was pressured up to 1198 psi. The pressure after 5 minutes was 1198 psi. The 15 minute pressure was 1181 psi. This well passed MIT.
|
|
|
|
1301579988
|
2011-11-02
|
|
I performed the quarterly UIC test on the annulus and the injection. The well was not running. There were no violations at this time.
|
|
|
|
1302293285
|
2011-03-21
|
|
Quarterly status check inspection found no violations at this time. The vault associated with the loading pad was full and I contacted Dave Ballentine and asked that the vault be emptied.
|
|
|
|
131618200
|
2010-05-20
|
|
Quarterly status check inspection found no violations at this time. Used the company gauge for the annulus pressure.
|
|
|
|
1324557525
|
2011-12-21
|
|
John Fleming and myself witnessed the pressure testing of the injection line from the tank battery to the wellhead by Dave Balentine. The line was pressured up to 1200 PSI and there was no pressure lost in 15 minutes. The injection line passed and there were no violations at this time.
|
|
|
|
1360093060
|
2012-11-13
|
|
My inspection of the surface facility found the new tank battery dike constructed. The liner was installed. The operator was in the process of spreading out sand over the liner. All completed construction was acceptable.
|
|
|
|
1390923104
|
2014-01-17
|
|
I was on location with inspector Steve Ochs to witness the setting of the packer and the mechanical integrity test (MIT) at this active injection well. Petrowell, Nabors, Pryamid Pipeline, Baker Atlas, and Northeast Ohio Oilfield Services were on location conducting operations. Petrowell ran 2.875" tubing into the hole with a packer and an on/off tool and set the packer. They came off of the tool and Nabors began circulating the hole with freshwater and pumped 3 gallons of corrosion inhibitor into the annulus between the tubing and 4.5" casing. Pyramid pumped diesel fuel to fill the top of the annulus to prevent freezing and damage to the casing and tubing in cold conditions. The tubing was placed back on the on/off tool and Nabors rigged up to conduct the MIT test. The test was conducted at 1410psi and after 15 minutes the pressure had not dropped. The test passed and the well can resume operations. See Inspector Ochs' report for details on this job. No violaltions.
|
|
|
|
1404327282
|
2014-06-30
|
|
There were no violations at the time of inspection.
|
|
|
|
1433981518
|
2010-09-02
|
|
The quarterly status check inspection found that the injection and annulus pressures were equalized indicating that the packer or tubing has failed. Barton Well Treating was on site to complete a mechanical integrity test on the annulus. The annular pressure increased less than 100 psi after pumping four barrels of water. Dave Ballentine is scheduling a service rig to unseat and pull the packer.
|
|
|
|
1637266940
|
2011-08-03
|
|
I performed the quarterly UIC test on the annulus and the injection. The well was running. There were no violations at this time.
|
|
|
|
1684639158
|
2014-01-14
|
|
A contractor was running a bond log. No violations were found.
|
|
|
|
1879485
|
2002-04-24
|
|
Inspectors Claus and Worstall checked UIC pressures and inspected the facility. The injection system was operating during the inspection. Met with landowner/operator (Mr. Ferrara) and requested a general improvement in housekeeping practices.
|
|
|
|
2154i245
|
2002-06-25
|
|
4-24-02 Inspectors Claus and Worstall requested Mr. Ferrara to install new needle valves at the wellhead and informed him that the injection pump shed should be cleaned up. 5-29-02 Inspector Claus showed Jay Cheslock (North Region Assistant Manager) the injection pump shed. Mr. Cheslock agreed that the pump shed should be cleaned up. 6-25-02 System was not running. Unable to get an injection pressure reading due to a bad needle valve. Met with Mr. Ferrara and requested him to replace the injection needle valve and the annulus needle valve. The pump shed still needs cleaned up. Issued N.O.V.
|
|
9-3-04(A)
|
|
2154i245
|
2002-06-25
|
|
4-24-02 Inspectors Claus and Worstall requested Mr. Ferrara to install new needle valves at the wellhead and informed him that the injection pump shed should be cleaned up. 5-29-02 Inspector Claus showed Jay Cheslock (North Region Assistant Manager) the injection pump shed. Mr. Cheslock agreed that the pump shed should be cleaned up. 6-25-02 System was not running. Unable to get an injection pressure reading due to a bad needle valve. Met with Mr. Ferrara and requested him to replace the injection needle valve and the annulus needle valve. The pump shed still needs cleaned up. Issued N.O.V.
|
|
9-3-05(A)3
|
|
2154i395
|
2002-08-22
|
|
Needs additional clean-up in pump house. System was running.
|
|
9-3-04(A)
|
|
437918227
|
2005-06-01
|
|
Status check inspection for this salt water disposal well. Ownership of the well recently changed to B&B from Twinoaks. The 210 bbl tanks need to repaired of replaced and the pumphouse needs to be cleaned. I will contact Dave Ballentine about starting this work. No violations at this time.
|
|
|
|
448725675
|
2007-05-09
|
|
Quarterly status check found no violations at this time.
|
|
|
|
528747897
|
2010-09-10
|
|
Heagen Well Service is on site to release and unseat the old Halliburton R-4 packer. When pulling the packer, the tubing parted. At this time, Heagen was picking up fishing tools and will attempt to recover the remaining tubing and the packer. If successful, the new packer and a new string of 2-7/8" tubing will be run in the hole tomorrow.
|
|
|
|
634615893
|
2009-06-10
|
|
The trash and debris have been removed from in and around the tank battery and the pump house as requested. While they were not leaking this day, there is still concern for the condition of the manway hatch seals on the easternmost tanks. They will need to checked regularly.
|
|
|
|
718254906
|
2009-05-21
|
|
I called Dave Ballentine about removing impacted vegetation around the wellhead and cleaning up trash and debris around the tank battery.
|
|
|
|
808607029
|
2002-06-25
|
|
FOLLOW UP TO NOV # 2154i245 4-24-02 Inspectors Claus and Worstall requested Mr. Ferrara to install new needle valves at the wellhead and informed him that the injection pump shed should be cleaned up. 5-29-02 Inspector Claus showed Jay Cheslock (North Region Assistant Manager) th
|
|
9-3-04(A)
|
|
808607029
|
2002-06-25
|
|
FOLLOW UP TO NOV # 2154i245 4-24-02 Inspectors Claus and Worstall requested Mr. Ferrara to install new needle valves at the wellhead and informed him that the injection pump shed should be cleaned up. 5-29-02 Inspector Claus showed Jay Cheslock (North Region Assistant Manager) th
|
|
9-3-05(A)3
|
|
844038743
|
2012-12-18
|
|
My inspection of the injection facility found no violations. Sod was installed on the dike walls.
|
|
|
|
8479069
|
2002-03-14
|
|
Injection well was running at the time of the inspection. No Violations.
|
|
|
|
905534748
|
2014-01-17
|
|
A Baker Hughes Lok set packer was set in compression at 4086 feet. A mechanical integrity test was performed on the well. 1410 psi. of pressure was placed on the tubing/casing annulus. The test passed.
|
|
|
|
907131595
|
2014-03-07
|
|
The work over pit was closed. The lease road and well site will need restored, when the weather permits. There were no violations at the time of inspection.
|
|
|
|
iTOMK000081
|
2000-07-13
|
|
|
|
03
|
|
iTOMK000081
|
2000-07-13
|
|
|
|
9-3-05(B)4
|
|
UIC1064
|
1991-02-27
|
|
1501:9-3-05 (A) (6) CONSTRUCTION
|
|
|
|
UIC1065
|
1991-02-27
|
|
1501:9-3-04 POLLUTION
|
|
|
|
UIC1414
|
1993-05-05
|
|
1509.03 RULES & REGULATIONS
|
|
|
|
UIC1415
|
1993-05-05
|
|
1501: 9-3-04 (A) PREVENT CONTAMINATE
|
|
|
|
UIC1445
|
1993-08-20
|
|
ACTION 940218 1509.22 (A) (2) STORAGE & DISPOSAL
|
|
|
|
UIC1446
|
1993-08-20
|
|
1501: 9-3-04 PREVENT CONTAMINATE
|
|
|
|
UIC1447
|
1993-08-20
|
|
1509.072 RESTORATION
|
|
|
|
UIC1450
|
1993-11-22
|
|
1509.22 (A) (2) STORAGE & DISPOSAL
|
|
|
|
UIC1451
|
1993-11-22
|
|
1501: 9-3-04 (A) PREVENT CONTAMINATE
|
|
|
|
UIC1669
|
1997-06-10
|
|
1501:9-3-07(H),1501:9-3-8 EMPTY PITS
|
|
|
|
UIC897
|
1990-04-20
|
|
1509.22 A STORAGE AND DISPOSAL
|
|
|
|