Well ID: 34-133-24362 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":41.1408519476,"lon":-81.3277909518,"icon":""}]} |
County: | |
Municipality: | |
Operator Name: | |
Well Pad ID: | |
Farm/Lease Name: | |
First Permit Date: | |
Last Permit Date: | |
Spud Date: 2008-08-06 | |
Unconventional: | |
Horizontal: | |
Producing: No | |
Violations: 0 | |
Latitude: 41.1408519476 | |
Longitude: -81.3277909518 |
PERIOD | GAS QUANTITY | GAS PRODUCTION DAYS | CONDENSATE QUANTITY | CONDENSATE PRODUCTION DAYS | OIL QUANTITY | OIL PRODUCTION DAYS |
---|
PERIOD | TYPE | QUANTITY | UNITS | DISPOSAL METHOD | WASTE FACILITY PERMIT ID | WASTE FACILITY NAME | FACILITY CITY | FACILITY STATE |
---|
INSPECTION ID | DATE | DESCRIPTION | COMMENT | VIOLATION ID | VIOLATION CODE | VIOLATION_COMMENT |
---|---|---|---|---|---|---|
-1776045001 | 2008-09-17 | Intrepid Well Service was on site to remove the down hole pump. The tank battery has been relocated and built. I requested a revised aerial showing the new tank batteryl location. I also told Cutter to remove the dike drain which currently discharges directly into an adjoining creek. | ||||
-2068662266 | 2008-08-06 | Unable to get the conductor casing in the 15" dia. hole. Pulled the conductor casing and reamed the well bore with a 17" dia. bit. | ||||
-293180973 | 2008-10-21 | The well is now in production. The required fencing and identification are in place. The containment dike drain, which discharges directly into an adjacent creek, has not been relocated or removed as requested. I spoke with CJ Cutter who said he would relocate the drain. | ||||
-355878719 | 2008-08-20 | Cutter Oil and Chemtech were on site to solidify the drilling pits. The frac job is scheduled for next week. No violations at this time. | ||||
-502107558 | 2008-11-18 | The well is in production and the dike drain has been removed as requested. | ||||
-823913645 | 2009-09-16 | Preliminary restoration is approved. | ||||
212717842 | 2008-08-14 | Poulson Drilling has moved off site. The pits are fenced, lined and in good condition. Solidification is scheduled for next week. | ||||
802141604 | 2008-08-08 | Cemented surface casing. Pits and liners are intact. |