34-099-23172

Well Details

Well ID: 34-099-23172
Loading map...
County:
Municipality:
Operator Name:
Well Pad ID:
Farm/Lease Name:
First Permit Date:
Last Permit Date:
Spud Date: 2012-05-24
Unconventional:
Horizontal:
Producing:
Violations: 0
Latitude: 40.9935513333
Longitude: -80.8241951876

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS

Waste Data

PERIOD TYPE QUANTITY UNITS DISPOSAL METHOD WASTE FACILITY PERMIT ID WASTE FACILITY NAME FACILITY CITY FACILITY STATE

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION_COMMENT
-1556599608 2012-06-06 On 6/6/2012, Northeast East Energy Rig # 10 still rigging up and setting up equipment.
-207726443 2013-03-14 I was on location with inspector John Fleming. We were checked by security before we entered the site. The lease road was stable and drainage controls were in place. Operator had recently repaired the drainage along the west side of the lease road, north end with mesh and seeded the area. The well is currently shut in and being prepped for flow testing. Operator was working on the construction of the tank battery and the separator units. The two impoundments on location were fenced. Operator is planning on reclaiming the north impoundment at the time of inspection it was being pumped down. No violations on location.
-341932116 2013-02-20 On 2/20/2013, I inspected the above location. At present CNX personal are setting tanks and hooking up their well head equipment. They will be doing a production test. They will call before starting.
-355797905 2012-06-30 Northeast Energy Rig #10 finished drilling to a depth of 5900'. Cal Frac was on location to load the 12.25" well bore with 947 barrels of fresh water mud. The well will be shut in until Nabors M-62 Drilling Rig moves on location.
-570084470 2012-05-22 On 5/22/2013, Express Energy moved on location to start drilling 72" cellar ring and to start drilling 30" conductor pipe.
1321595457 2012-06-14 On 6/14/2012, Cal Frac was on location, made connection to casing head, circulated 65 barrels of fresh water to surface and cemented 375' of 20" casing with 672 sacks of Class A cement with 30 barrels of returns.
1325688107 2011-12-28 This drill site is not yet under construction. The lease road is staked out but no ground has been broken at this time.
1339763119 2012-06-14 On 6/14/2012, Cal Frac was on location, made connection to casing head and circulated 65 barrels of fresh water to surface and cemented 375' of 20" casing good cement return to surface, plug down at 8:05 pm. See casing report.
1340022445 2012-06-17 On 6/17/2012, the ran 776' of 13 3/8 54.5 lb casing pipe cemented to surface, good returns.
1340907511 2012-06-18 On 6/18/2012, I meet with Adam Pauley (Assistant Drilling Engineer), and received the charts for the Blow-Out Preventor test. This test was performed on 6/17/2012.
1344450819 2012-07-28 Halliburton on location to cement 5900' of 40# grade P-110 9.625 casing, this was a 2 stage cement job.The DV tool set at 4083' using 615 sack of Halcem ? system. Waiting 4 hour before setting next plug with 1195 sacks of Varicem ? Cement. We did not get returns to surface. Will wait 36 hours for cement to cure before running bond log.
1348241923 2012-09-20 On 9/20/2012, I did a satus ckeck on the above location, they are in the process of filling the reserve in-ground pit with the water from the Trumble County CNX location, the frac pit has about 5' of free board, there is still some contaiment on location for the frac team when they move in. At this time there is no violation.
1358957781 2012-12-31 I received a call from Jeramiah Alton Completions Engineer for C N X Energy, that Calfrac would be moving frac equipment on location. I inspected the location for containment, there was equipment on location removing ice and snow before the equipment could be set up. At this time there is no violations.
1359141442 2013-01-08 On 1/8/2013, I was on location to wittiness the fracing of the 3rd stage. After the safety meeting we went to Calfrac's Command Center. When everybody was in their operating areas they began to start the frac operation. The average pressure was 7796, the average barrels pumped per minute were 77 with a total of 7122 barrels were used. Job was completed.
1359647699 2013-01-24 On 1/23/2013, I received a phone call from Ken Cerny, Environmental Enforcement for C N X Energy informing me that they had a 120 barrel releases of flow back water into a contained area. There were vacuumed trucks on location at that time they responded with-in minutes. On 1/24/2013, I met with Ken Cerny and Andrew Sarver who were on location when this occrued. There was a plug on the manifold line that broke . The Primary containment size is 20" deep by 50' long and 40' wide. This was also setting on a larger containment pad. No release was on soil. All flow back is properly disposed of. I inspected the area and there is no violation.
1359656417 2013-01-18 I was on location and met with Cody Croker and Andrew Sarver That they are gone to start testing the above well, there will be a flair I instructed them to contact the Ellsworth Fire Department and myself when they start the testing.
1667489435 2012-05-29 On 5/292012, Express Energy drilled 20" hole to a depth of 75' and set 74' of 16" casing. Sidley Concrete was on location with Class A grout to grout the mouse hole and top off 30". A total of 14 yards of Class A grout was used.
1673005891 2012-05-29 On 5/29/2012, Express Energy drilled the 20" diameter mouse hole to a total depth 75' and set 74' of 16" diameter casing. Sidley Concrete was on location to grout the mouse hole and also to top off the 30" diameter conductor hole. A total of 14 yards of Class A grout was used for this job.
1931185961 2012-06-10 On 6/10/2012, I arrived on location at 3:45pm they were trying to install the float shoe on the bottom of the 20" on the drill rig floor but it kept getting cross threated, they layed the 20" back on the pipe handler and lowered it to the ground and got the float shoe started, they started back to running the 20" and kept getting it cross threated, they were able to get 4 joints (160') connected but the 20"pipe stoped gone down the 26" wellbore due to a blockage, they brought in Cal Frac and hooked up to the casing pipe and tried to circulate down the wellbore but only dropped 7', they decided to pull all pipe back out and go in with a Tri-Cone bit and open the well bore to 388'.
264015838 2012-06-10 On 6/10/2012, I arrived on location at 3:45 pm. They were trying to install the float shoe on the bottom of the 20" casing, on the rig floor but kept getting cross threaded. They lowered the casing down to the pipe floor and installed it there. They started running the 20" casing and could only get 4 joint 160' in the 26" bore hole. They hooked Cal-Frac up to the casing pipe and tried to circulate down but only dropped 7" They decided to pull it back out and go in with a Tri-Cone bit and rimer and drill to 388'.
307061568 2912-06-10 On 06/12/2012, I arrived on location at 3:45 pm. The rig crew was trying to install the float shoe on the bottom of the 20" casing, after several attempts they successfully installed the shoe and started running the 20" casing. They were able to get 4 joints ( 160' ) in the well before it stopped. They hooked up Cal Frac to circulated down the 20" casing but only dropped 7'. They decided to pull casing back out and go in with a Tri-Cone bit and open up the well bore to 388'.
348757874 2013-01-03 I was on location to inspect the containment area where Calfrac would be setting there frac equipment. All containment is in place.
464389719 2012-06-17 On 6/17/2012, they ran 776' of 13 3/8", 54.5 lb casing. Cal Frac circulated with fresh water, pumped 602 sacks of Class A cement with 15 barrels of returns. Plug down at 10:52 pm.
76368322 2012-07-24 Attended a pre-spud and safety meeting with CNX and Nabors Drilling Rig M62 personnel before proceeding to drill.