34-105-23268

Well Details

Well ID: 34-105-23268
Loading map...
County: Meigs
Municipality:
Operator Name: J D DRILLING CO
Well Pad ID:
Farm/Lease Name:
First Permit Date:
Last Permit Date:
Spud Date: 1984-12-30
Unconventional: No
Configuration: Vertical
Well Status: Active Injection
Violations: 0
Latitude: 39.09526231
Longitude: -81.89858137

Production Data

PERIOD GAS QUANTITY GAS PRODUCTION DAYS CONDENSATE QUANTITY CONDENSATE PRODUCTION DAYS OIL QUANTITY OIL PRODUCTION DAYS
1985-0 5509.0 0.0
1986-0 5224.0 0.0
1987-0 4554.0 0.0
1988-0 3758.0 0.0
1989-0 3461.0 0.0
1990-0 3145.0 0.0
1991-0 2900.0 0.0
1992-0 2691.0 0.0
1993-0 2837.0 0.0
1994-0 3065.0 0.0
1995-0 2648.0 0.0
1996-0 2540.0 0.0
1997-0 2307.0 0.0
1998-0 2337.0
1999-0 2212.0
2000-0 2223.0
2001-0 2208.0 0.0
2002-0 2350.0 0.0
2003-0 2127.0 0.0
2004-0 1669.0 0.0
2005-0 1416.0 0.0
2006-0 1346.0 0.0
2007-0 1287.0 0.0
2008-0 17.0 0.0
2009-0 0.0 0.0
2010-0 7.0 0.0
2011-0 50.0 0.0
2012-0 0.0 0.0

For data sources see[1]

Inspection Data

INSPECTION ID DATE DESCRIPTION COMMENT VIOLATION ID VIOLATION CODE VIOLATION COMMENT
-1048406739 2013-05-22 Inspected the injection pressure, annulus pressure, unloading pad, containment dike and tanks. Dike is free of oil and water. Establishing vegetative cover on bare areas. Seed and straw have been applied to location. Access road has gate that is lockable. Phone Call
1126847620 2015-04-07 Inspected the unloading pads, containment dikes, tanks, injection pump, injection line, injection manifold connecting the Conroy and Showalter injection wells to this facility. The manifold was tested today at 1020 psi for 15 minutes with no loss in pressure, Identification posted at the well. Containment dikes are free of water.
-1200455161 2012-06-25 Well does not appear to be in use for injection. No equipment or lines on site. All valves closed at wellhead. Unable to test pressures at well.
-1227901331 2015-04-28 No noted violations.
1251542102 2013-10-09 Inspected the unloading pad, containment dike, tanks, annulus pressure, and injection pressure. Containment dike is free of water. Good identification at the wellhead and containment dike.
1257851502 2014-10-06 Inspected the unloading pads, containment dike, tanks, injection pump, injection line, annulus pressure and injection pressure. Identification posted at well and containment dike. Currently working on the second containment dike.
1286474651 2010-10-06 Convert to SWIW inspection request from Tom Tomastik. Well site is located in a corn field. Corn crop is on 3 sides with the 4th side a wood line with pine trees and mixed hard woods. There are three water wells with in 1/2 mile (2640'). (1) Windon is 1240' South West of proposed Injection well. (2) Millhone is 1189' East of the proposed Injection Well. (3) Nutzling is 1550' East of the proposed Injection well. There are two intermittent streams (1) 1832' to West of proposed Injection well. (2) 2302' to East of the proposed Injection well. Production well has good identification. Well is equipped with 7 casing head, 4 1/2 casing head, with 1 1/2 tubing (valve on tubing is closed). Well has a 2 black plastic line that is connected to a 1100 gallon plastic tank (tank is empty). Well is not connected for gas production. No leaks or contamination observed during inspection. Well site has good vegetative cover established.
1316561633 2012-10-17 Topped off annulus with 2 barrels fresh water. Pumped annular pressure to 800 psi then pressure dropped rapidly. Pulled more tension on tubing and packer total of 26,000 lbs. Tested three aditional times using 15 gallons of fresh water. Unable to hold 880 psi for 15 minutes with no more than 5% loss. Pulled more tension on the packer 27,000 lbs. Tested at 910 psi for 15 minutes with no decline in pressure. Test passed.
1350416109 2012-10-16 Conversion to salt water injection well. Appalachian Well Surveys logged (Gamma Ray CCL) and perforated the 4.5 casing from 3728' to 3668' (60 shots). Wire line total depth was 3764'. Halliburton R-4 (rebuilt) Packer set at 2978' with new 2 3/8 R-2 10 round tubing. Packer ran with 3 shear pins. Packer set at 25,000 lbs (tubing string weight 12,500 lbs). Packer was set at 25,000lbs. Annulus was filled with 30 barrels fresh water and 4 gallons inhibitor. Unable to test annulus due to air in the annulus.
1350555475 2012-10-17 Well settled down over night. Water was added on top of the packer too quickly entrapping air. This caused the well to burp air and water. The operator decided to wait until the next day to continue the mechanical integrity test on the packer. Performed three failed mechanical integrity test at the beginning of the morning, reseating the packer after each test with increasingly higher pull pressure on the drill string and packer. The fourth reseating of the packer had a total pull weight on the drill string and packer of 27000 lbs, with approximately 14000 pounds of that applied to the packer. The maximum allowable injection pressure on this well was permitted at 880 psi. This last mechanical integrity test started at 910 psi and stayed at that pressure for 15 minutes. It passed.
1356633494 2012-12-27 Surface facility construction ongoing. Well is not connected to injection line. Checked injection tubing pressure (formation pressure) and annulus pressure.
1358443513 2013-01-17 The concrete pads have been poured and the tanks are set. The lines are being laid down today. The injection line to the well has not been set.
1361378405 2013-02-20 Injection operations began today and I accompanied Jon Scott on an inspection of the facilities.
1361480275 2013-02-21 Inspected the unloading pad, Containment dike. Checked the injection pressure and the annulus pressure.
1372584698 2012-11-15 Dike formed area 34' by 55'. Pouring concrete walls and slab. Used 6 bag mix concrete with wire reinforcement. 60 yards ordered. 8 thick slab.
1411060821 2014-09-18 Second unloading pad is being constructed today. Pad will be 60' by 14' concrete with wire reinforcement.
1416417232 2014-11-19 Inspected the unloading pads, containment dike, tanks, injection pump, injection line, annulus pressure and injection pressure. The construction of the second containment dike has not progressed past the excavation of soil and the build up of the dike walls.
1416866876 2014-11-24 Witnessed company constructing dike for tank placement.
1419350873 2014-12-23 Constructing second containment dike. 30 mil liner has been installed with a layer of sand below the liner and a layer of sand on top of the liner. Geo fabric has been installed over the top layer of sand. Currently installing two 400 barrel steel tanks in the containment dike.
1430761544 2015-05-04 Inspected the unloading pads, containment dikes, tanks, injection pump, injection line, injection pressure and annulus pressure. Identification posted at well.
-1467681564 2014-11-19 No violations at facility. Company has begun construction on dike associated with new tank battery.
1513705399 2004-06-02 No violations at the time of inspection.
1540637698 2015-01-07 Installing plumbing on the 2 new 400 barrel steel tanks in the new containment dike.
1769069770 2014-11-24 I stopped back at the site to see if the company had begun layering the sand or laying the liner in the pit yet. They were still doing dirt work at the site.
1791242897 2012-12-19 Installed three 210 barrel tanks, two 100 barrel tanks and one 400 barrel tank in dike.
1830109954 2012-11-09 Checked injection tubing pressure and annulus pressure. Injection tubing not connected to equipment. Tubing pressure is formation pressure. Crew on site digging dike foundation.
-1966946755 2014-08-26 Inspected the unloading pad, containment dike, tanks, injection pump, injection line, annulus pressure and injection pressure. Good identification posted on well and tank. Concrete containment dike has multiple cracks that need repaired. I called Jonathan Reese and left a message about the need to repair the cracks.
2010247437 2014-02-25 Upon inspection it was noticed the injection tubing was on vacuum and annulus had zero psi. I met tom Schoonover in the field and we noticed the production casing head had developed a small leak around the threads. A fresh water MIT mini test was administered and the annulus held 405 psi for 15 minutes with zero drop in pressure.
-2025441506 2009-05-01 No violations were found.
2144823656 2014-07-24 No noted violations.
226107741 2013-04-12 Inspected the containment dike, tanks, pump, unloading pad, injection pressure and annulus pressure. Identification on wellhead and dike. Dike was free of water. 4 brine line between the tanks and the injection pump was disconnected. All valves were shut.
240974105 2013-10-30 No leaks or signs of contamination at well, tanks, or unloading pad.
243547150 2012-10-16 Observed the conversion of this Ohio Shale production well to an injection well. Met Jon Scott at the well site. Appalachian Well Surveys was at the site waiting on JD Drilling personnel. JD Drilling service truck, flatbed truck with new 100 joints of 2-3/8 inch production tubing with a measured total length of 3030 feet,, and a UIC brine truck filled with fresh water were also parked around the wellhead. Appalachian logged the well with gamma ray-collar locator logs. Rigged up a 60-feet perforator string, one shot per foot and shot perfs at 3668 to 3728 interval to enhance injection capacity of brine combined with existing perforations in the upper Ohio Shale. JD used a refurbished Halliburton R4 Packer with three shear pins in place, each rated at 6600 lbs of shear before failure for a total of 19800 lbs. They lowered the packer into the hole to a depth of 2978.2 feet with 98 joints of the 100 on location. They tried to flush the perfs with some of their water but lost all of their supply due to vacuum down the hole. So they had to get a new supply of fresh water and Baker Hughes inhibitor to perform the mechanical annular space integrity test.. Using the tubing JR Drilling seated the packer at 2978.2 feet with 25,000 lbs total pull on drill pipe and packer with 12,500 lbs on packer. They poured their fresh water with inhibitor down the hole but not slowly. The well continued to burp air and water forcefully so they decided to let it settle over night. Shut down until tomorrow
389454341 2015-05-27 Review of site facilities and well head conditions. No noted violations.
397870735 2013-07-10 Unloading pad and dike around tanks were in good condition.
443323385 2014-05-21 Follow up to -560805446. Witnessed A fresh water MIT mini test was administered and the annulus held 400 psi for 15 minutes with zero drop in pressure.
459912636 2012-12-04 Access road is gravel with a gravel parking lot. Unloading pad has been constructed. Concrete dike is completed. Currently installing electric poles for the service line.
-560805446 2014-05-20 The annulus had zero pressure on it at the time of inspection, but the injection was on vacuum. Well shall be shut in and a mini MIT shall be administered in order to prove mechanical integrity before injection is allowed to proceed.
-580345375 2014-12-04 Currently waiting on the 30 mil containment dike liner for the 2nd containment dike. Sand is on site.
77184243 2013-02-20 Witnessed initial injection. Initial injection pressure of 580 psi. Injection pressure dropped from 580 psi to vacuum with-in 10 minutes and stayed on vacuum. The annulus valve was frozen solid and unable to be opened. I collected a water sample and transported it to the lab in Cambridge.
-806164535 2015-03-19 No noted violations at the time of inspection.
-816382428 2013-05-29 Good identification. No issues with dike, tanks, or loading pad.
84747148 2014-10-14 Inspected the unloading pads, containment dike, tanks, injection pump, injection line, annulus pressure and injection pressure. Identification is posted at the well and containment dike. No additional work has been done to the new containment dike area.
952353910 2014-09-10 Inspected the unloading pad, containment dike, tanks, injection pump, injection line, annulus pressure and injection pressure. Good identification posted at well and containment dike. Met with Jim Diddle and Spence Carpenter on site to review plans for a second unloading pad.
PL10687 Preliminary Restoration done information from Data Point

For data sources see[2]

References

  1. "Ohio Department of Natural Resources RBDMS". [1]. 2015-06-19. Retrieved 2015-06-20. 
  2. "Ohio Department of Natural Resources RBDMS". [2]. 2015-06-19. Retrieved 2015-06-20.