If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.
powered by ChangeDetection
Well ID: 34-073-23603 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":39.490502914,"lon":-82.45699866,"icon":""}]} |
Country: United States | |
State: Ohio | |
County: Hocking | |
Municipality: Falls Township | |
Operator Name: HOCKING HILLS ENERGY AND WELL | |
Well Pad ID: | |
Farm/Lease Name: HOCKING WILDERNESS LTD | |
License Status: Well Drilled | |
License Date: 2011-08-03 | |
Spud Date: 2011-08-26 | |
Spud Drilling Contractor: BOWMAN DRILLING | |
Final Drill Date: 2011-09-02 | |
Well Total Depth: 4855 ft | |
Configuration: Vertical | |
Latitude: 39.490502914 | |
Longitude: -82.45699866 |
For data sources see[1]
Well Status | Well Status Date | Comment |
---|---|---|
APP | 2011-08-03 | Proposed Formations:QUEENSTON THROUGH ROSE RUN, Issued Date:8/3/2011, Expired Date:8/2/2013 12:00:00 PM, Drilling unit acres:40, Proposed Well Type:OG, Proposed Well Class:EDPW |
Reached Total Depth | 2011-09-02 | WELL WAS PERFORATED IN TREMP AND ONLY PERMITTED FOR ROSE RUN. CURRENTLY SHUT IN. JG |
Completion Report Received | 2012-04-30 | WELL WAS PERFORATED IN TREMP AND ONLY PERMITTED FOR ROSE RUN. CURRENTLY SHUT IN. JG |
Correction to Well | 2012-06-29 | CORRECTION TO PROPOSED GEOLOGICAL FORMATION, NOW PERMITTED FOR QUEENSTON THRU TREMPEALEAU. |
Construction Permit Expires | 2012-08-02 | WELL WAS PERFORATED IN TREMP AND ONLY PERMITTED FOR ROSE RUN. CURRENTLY SHUT IN. JG |
Change of Owner | 2012-11-02 | Operator changed from 8595, PDC ENERGY INC to 8416, LOGAN GAS INC |
Change of Owner | 2014-05-19 | Operator changed from 8416, LOGAN GAS INC to 5755, HOCKING HILLS ENERGY WELL SERV |
Record Last Modified | 2015-03-20 | WELL WAS PERFORATED IN TREMP AND ONLY PERMITTED FOR ROSE RUN. CURRENTLY SHUT IN. JG |
For data sources see[2]
Perforation Date | Interval Top (ft) | Interval Base (ft) | Number of Shots |
---|---|---|---|
2012-07-16 | 4770 | 4774 | 16 |
2012-07-16 | 4796 | 4800 | 16 |
For data sources see[3]
Stimulation Date | Chemical Agent | Chemical Agent Concentration (%) | Fracking Fluid Volume | Mass of Proppant Used (lb) | Fracking Company | Comments |
---|---|---|---|---|---|---|
2011-11-04 | ACID | 15 | 800 Gal | 0 | Producers Service Corporation |
For data sources see[4]
Period | Operator Name | Gas Quantity (mcf) | Oil Quantity (bbl) | Production Days |
---|---|---|---|---|
2012 | LOGAN GAS INC | 0 | 0 | 0 |
2014 | HOCKING HILLS ENERGY AND WELL | 0 | 0 | 365 |
2015 | HOCKING HILLS ENERGY AND WELL | 0 | 0 | 365 |
2016 | HOCKING HILLS ENERGY AND WELL | 0 | 0 | 365 |
2017 | HOCKING HILLS ENERGY AND WELL | 0 | 0 | 365 |
Period | Operator Name | Waste Type | Quantity (bbl) | Production Days |
---|---|---|---|---|
2012 | LOGAN GAS INC | Brine | 0 | 0 |
2014 | HOCKING HILLS ENERGY AND WELL | Brine | 0 | 365 |
2015 | HOCKING HILLS ENERGY AND WELL | Brine | 0 | 365 |
2016 | HOCKING HILLS ENERGY AND WELL | Brine | 0 | 365 |
2017 | HOCKING HILLS ENERGY AND WELL | Brine | 0 | 365 |
Inspection ID | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|
0130852029 | 2012-10-31 | Administrative Inspection | No Violations | Received phone call from Mr. Randy Ferguson at 10:34 am stating that this well has been transferred to Jim Kilbarger. |
0157254629 | 2012-08-16 | Administrative Inspection | No Violations | Received phone call from Randy Ferguson from PDC. He stated that he was going to hire Columbus Environmental Consultants to inspect sites and give recommendations for remediation. After that they will hire a contractor to do the work. They want to seed the sites in September. |
0216590981 | 2012-01-06 | Preliminary Restoration | No Violations | Vegetation had not been established even though straw and seed were present on the side of the hill where the drilling pit had been. Mr. David White stated that seed and straw were applied the November before. One frac tank remains on site. Accompanied by inspector Kip Thompson. |
0569648348 | 2012-08-29 | Preliminary Restoration | No Violations | Met with Mr. Mike Reeves from CEC (Civil and Environmental Contractors). They are a third party contractor for PDC Energy and will be making recommendations for the completion of the preliminary restoration on this well site. We inspected the site together and came to a consensus on how to remedy the erosion problems. |
1190763327 | 2019-02-07 | Production Wells | No Violations | My inspection of the well revealed that it was shut in and not capable of production. The well was equipped with a 4.5 inch to 2 inch swage with a gate valve. I did not observe any production lines connected to the well. According to production records the well has never produced any gas or oil. I took several photos of the well location and lease road. I left a voicemail message for Doug Kitchen at 2:16 PM on 2/8/2019. The well owner/operator shall submit a written plugging schedule to Brandon Mitchell at 5880 Memory Road Zanesville, Ohio 43701-9553 within 30 days, per ORC 1509:13(B)(7), and plug the well within 180 days. The well owner/operator will be notified if the plugging schedule is approved or denied. Time of inspection: 10:30 AM. Weather: 56 degrees F, Rain |
1315502989 | 2011-08-29 | Drill / Deepen / Reopen | No Violations | Witnessed cementing of 7 intermediate string. Good circulation was achieved. |
1348228477 | 2012-09-18 | Preliminary Restoration | No Violations | Met with 2 company representatives from CEC. They wanted to assess where the lease road crosses the stream. We also looked at the drainage from the rest of the lease road. |
1409056112 | 2014-08-26 | Production Wells | No Violations | I received a request from Doug Kitchen to confirm the clean up of a brine leak from a tank that was being used to hold brine. The property is owned by Mr. Greg Lint. I received a conference call with Mr. Kitchen and Mr. Lint. I told both partys I would conduct a investigation to determine if the spill area was cleaned up properly. I obtained three soil samples to check for chlorides. I added water to make a slurry to determine if any chlorides were present. The samples were taken 20 feet, 30 feet, and 40 feet from the tank that leaked. The sample locations were down hill were the brine would have flowed. The highest reading was 106 PPM using low range Quantab Titrators. I called Mr. Lint back to inform him of my findings. |
1483438997 | 2011-08-27 | Drill / Deepen / Reopen | No Violations | Witnessed cementing of surface casing. Good circulation. Good returns. |
1647714561 | 2019-02-07 | Preliminary Restoration | No Violations | I conducted a preliminary restoration status check on this well today. During the inspection I observed the well location for vegetation. My inspection revealed that vegetation was sparse. I observed substantial erosional ruts on the lease road. I took several photos of the well location and lease road. The well owner shall establish vegetation at the well location and correct rain water runoff along the lease road to prevent erosion. I left a voicemail message for Doug Kitchen at 2:16 PM on 2/8/2019. Time of inspection: 10:30 AM. Weather: 56 degrees F, Rain |
1820496031 | 2012-08-15 | Administrative Inspection | No Violations | Spoke with Jeff Glossa from PDC at 3:29 pm. We spoke about the preliminary restoration on this well and another (p# 3601). I told him that it was past due and needed to be completed as soon as possible. I also made mention of the lack of vegetation and erosion problems. He stated that PDCs environmental compliance person had been on scene and was evaluating the situation. He then stated that he would have Randal Ferguson call me. He also works with their environmental department. Mr. Glossa also reported that he had been in contact with Columbus as far as the completion of the well and had submitted all necessary paperwork. |
2005862019 | 2011-09-04 | Drill / Deepen / Reopen | No Violations | Witnessed cementing of 4.5production casing. Good circulation achieved. |
2114774067 | 2012-08-09 | Preliminary Restoration | No Violations | Vegetation extremely sparse throughout site. Lease road is eroded and has 6 inch ruts in some places. One frac tank remains on site. Photos were taken. Accompanied by inspector Morgan Button. Phone calls were made, and messages left with Joey Smith and Jeff Glossa of PDC on 8/15/12. |
For data sources see[9]