0385040208002

Well Details

Well ID: 0385040208002
Loading map...
Location: 00/08-02-038-04W5/2
Location Alias: 00/08-02-38-04 W5M
Location Alias 2: 00/08-02-038-04 W5/02
Country: Canada
Province: Alberta
Township: 038
Meridian: 5
Range: 04
Section: 02
County/Municipality: Clearwater County
Well Name: NAL ACE SYLAKE 8-2-38-4
Operator Name: NAL Resources Limited
License Number: 0126633
License Date: 1987-05-28
License Status: Issued
Spud Date: 1987-05-30
Final Drill Date: 1987-06-21
Well Total Depth: 2374.00 m
Surface Hole Latitude: 52.235916
Surface Hole Longitude: -114.459123

For data sources see[1][2]

Well History

Date Event
1987-05-28 Obtained License
1987-05-31 Surface Casing Operation Performed
1987-06-12 Drill Stem Test Performed
1987-06-18 Drill Stem Test Performed
1987-06-21 Finished Drilling
1987-06-24 Well Log Performed
1987-06-25 Well Log Performed
1987-06-26 Production Casing Operation Performed
1987-06-26 Rig Released
1987-06-26 Well Mode changed to Drilled and Cased
1987-07-22 Perforation Treatment Performed - Jet Perforation
1987-07-22 Well Log Performed
1987-08-21 Perforation Treatment Performed - Bridge Plug Capped W/Cement
1987-08-21 Plug Back Performed
1987-08-21 Well Log Performed
1987-08-22 Perforation Treatment Performed - Jet Perforation
1987-08-22 Well Log Performed
1987-08-25 Perforation Treatment Performed - Acid Squeeze - Press Used
1987-10-07 Perforation Treatment Performed - Jet Perforation
1987-10-07 Well Log Performed
1987-10-14 Perforation Treatment Performed - Jet Perforation
1987-10-14 Well Log Performed
1987-10-15 Perforation Treatment Performed - Acid Squeeze - Press Used
1987-11-07 Well Began Production
1987-11-07 Well Fluid changed to Crude Oil
1987-11-07 Well Mode changed to Flowing
1988-03-28 Well Log Performed
1988-08-02 Well Log Performed
1988-12-02 Well Log Performed
1988-12-06 Perforation Treatment Performed - Cement Squeeze
1988-12-09 Perforation Treatment Performed - Cement Squeeze
1988-12-16 Perforation Treatment Performed - Jet Perforation
1988-12-16 Well Fluid changed to Crude Oil
1988-12-16 Well Log Performed
1988-12-16 Well Mode changed to Flowing
1989-01-05 Well Log Performed
1989-01-06 Perforation Treatment Performed - Jet Perforation
1989-01-10 Perforation Treatment Performed - Acid Squeeze - Press Used
1989-01-24 Well Log Performed
1989-01-26 Perforation Treatment Performed - Jet Perforation
1989-01-26 Well Log Performed
1989-02-06 Perforation Treatment Performed - Acid Squeeze - Press Used
1989-02-08 Perforation Treatment Performed - Jet Perforation
1989-02-08 Well Log Performed
1990-07-18 Perforation Treatment Performed - Cement Squeeze
1990-07-18 Plug Back Performed
1990-07-27 Perforation Treatment Performed - Jet Perforation
1990-07-27 Well Fluid changed to Crude Oil
1990-07-27 Well Mode changed to Flowing
1990-07-31 Perforation Treatment Performed - Fractured
1990-08-01 Perforation Treatment Performed - Acid Squeeze - Press Used
2001-09-11 Well Fluid changed to Crude Oil
2001-09-11 Well Mode changed to Pumping
2007-09-28 Perforation Treatment Performed - Jet Perforation
2007-09-28 Well Log Performed
2007-09-29 Perforation Treatment Performed - Acid Squeeze - Press Used
2007-10-01 Well Log Performed
2011-09-01 Well Fluid changed to Crude Oil
2011-09-01 Well Mode changed to Suspended

For data sources see[3]


Perforation Treatments

Perforation Date Perforation Type Interval Top (m) Interval Base (m) Number of Shots
1987-07-22 Perforation 2324.00 2327.50 13
1988-12-16 Perforation 2291.50 2295.50 13
1989-01-06 Perforation 2283.00 2285.00 13
1989-01-06 Perforation 2286.00 2287.00 13
1989-01-10 Acid Treatment 2283.00 2287.00 0
1989-01-26 Perforation 2255.50 2257.00 13
1989-02-06 Acid Treatment 2255.50 2257.00 0
1989-02-08 Perforation 2265.00 2274.00 13
1990-07-18 Cement Squeeze 2255.50 2295.50 0
1990-07-27 Perforation 2255.00 2257.00 14
1990-07-27 Perforation 2265.00 2274.00 14
1987-08-21 Packing Device Capped w/Cement 2307.00 2315.00 0
1990-07-31 Fracture 2255.00 2274.00 0
1990-08-01 Acid Treatment 2255.00 2274.00 0
2007-09-28 Perforation 2324.00 2327.50 17
2007-09-28 Perforation 2319.50 2322.00 17
2007-09-29 Acid Treatment 2319.50 2327.50 0
1987-08-22 Perforation 2280.00 2286.00 13
1987-08-25 Acid Treatment 2280.00 2286.00 0
1987-10-07 Perforation 2271.00 2274.00 13
1987-10-14 Perforation 2265.00 2270.50 13
1987-10-15 Acid Treatment 2265.00 2274.00 0
1988-12-06 Cement Squeeze 2265.00 2274.00 0
1988-12-09 Cement Squeeze 2280.00 2286.00 0

For data sources see[4]


Production Data

Period Total Production Hours Gas Quantity (m3) Oil Quantity (m3) Water Quantity (m3)
1987 1206 0.0 0.0 0.0
1988 3216 0.0 0.0 0.0
1989 5753 0.0 0.0 0.0
1990 6959 0.0 0.0 0.0
1991 7290 0.0 0.0 0.0
1992 7493 0.0 0.0 0.0
1993 7241 0.0 0.0 0.0
1994 8759 0.0 0.0 0.0
1995 8414 0.0 0.0 0.0
1996 4621 0.0 0.0 0.0
1997 5994 0.0 0.0 0.0
1998 8256 0.0 0.0 0.0
1999 7767 0.0 0.0 0.0
2000 7935 0.0 0.0 0.0
2001 6275 0.0 0.0 0.0
2002 8293 0.0 0.0 0.0
2003 8225 0.0 0.0 0.0
2004 8433 0.0 0.0 0.0
2005 8321 0.0 0.0 0.0
2006 8606 0.0 0.0 0.0
2007 5579 0.0 0.0 0.0

For data sources see[5]

References