0555181807000

Well Details

Well ID: 0555181807000
Loading map...
Location: 00/07-18-055-18W5/0
Location Alias: 00/07-18-55-18 W5M
Location Alias 2: 00/07-18-055-18 W5/00
Country: Canada
Province: Alberta
Township: 055
Meridian: 5
Range: 18
Section: 18
County/Municipality: Yellowhead County
Well Name: SOC PINE CK 7-18-55-18
Operator Name: AlphaBow Energy Ltd.
License Number: 0086941
License Date: 1980-11-10
License Status: Abandoned
Spud Date: 1980-11-15
Final Drill Date: 1980-12-13
Well Total Depth: 2010.00 m
Surface Hole Latitude: 53.748863
Surface Hole Longitude: -116.659986

For data sources see[1][2]

Well History

Date Event
1909-09-09 Well Log Performed
1980-11-10 Obtained License
1980-11-15 Lost Circulation Occurred
1980-11-25 Water Flow Occurred
1980-12-13 Finished Drilling
1980-12-13 Well Mode changed to Drilled and Cased
1980-12-18 Production Casing Operation Performed
1981-02-25 Perforation Treatment Performed - Jet Perforation
1981-02-28 Perforation Treatment Performed - Fractured
1981-03-06 Perforation Treatment Performed - Jet Perforation
1981-03-08 Perforation Treatment Performed - Fractured
1981-03-22 Well Began Production
1981-03-22 Well Fluid changed to Crude Oil
1981-03-22 Well Mode changed to Flowing
1981-08-16 Well Fluid changed to Crude Oil
1981-08-16 Well Mode changed to Pumping
1997-02-01 Well Fluid changed to Crude Oil
1997-02-01 Well Mode changed to Suspended
2004-01-07 Well Fluid changed to Crude Oil
2004-01-07 Well Mode changed to Pumping
2008-08-01 Perforation Treatment Performed - Bridge Plug Capped W/Cement
2008-08-01 Plug Back Performed
2008-08-01 Well Fluid changed to Crude Oil
2008-08-01 Well Mode changed to Abandoned Zone
2008-08-02 Perforation Treatment Performed - Bridge Plug Capped W/Cement
2008-08-02 Plug Back Performed
2008-08-03 Perforation Treatment Performed - Bridge Plug Capped W/Cement
2008-08-03 Plug Back Performed
2008-08-03 Well Log Performed
2008-08-06 Perforation Treatment Performed - Cement Plug
2008-08-06 Plug Back Performed
2008-08-06 Well Log Performed
2008-08-10 Well Abandoned

For data sources see[3]


Perforation Treatments

Perforation Date Perforation Type Interval Top (m) Interval Base (m) Number of Shots
1981-02-25 Perforation 1955.00 1958.00 7
1981-02-25 Perforation 1964.00 1965.50 7
1981-02-28 Fracture 1955.00 1965.50 0
1981-03-06 Perforation 1936.00 1940.00 13
1981-03-08 Fracture 1936.00 1940.00 0
2008-08-01 Packing Device Capped w/Cement 1922.00 1930.00 0
2008-08-02 Packing Device Capped w/Cement 1108.90 1321.50 0
2008-08-03 Packing Device Capped w/Cement 550.00 595.00 0
2008-08-06 Cement Plug 0.00 125.00 0

For data sources see[4]


Production Data

Period Total Production Hours Gas Quantity (m3) Oil Quantity (m3) Water Quantity (m3)
1981 3852 0.0 0.0 0.0
1982 2833 0.0 0.0 0.0
1983 1646 0.0 0.0 0.0
1984 3587 0.0 0.0 0.0
1985 6571 0.0 0.0 0.0
1986 7214 0.0 0.0 0.0
1987 3277 0.0 0.0 0.0
1988 1464 0.0 0.0 0.0
1990 1464 0.0 0.0 0.0
2004 8471 0.0 0.0 0.0
2005 7557 0.0 0.0 0.0
2006 8379 0.0 0.0 0.0
2007 5085 0.0 0.0 0.0

For data sources see[5]

Occurences

Occurence Date Occurence Type Occurence Depth (m) Occurence Control Depth (m)
1980-11-15 Lost Circulation 29.00 95.00
1980-11-25 Water Flow 899.00 0.00

For data sources see[6]

References