0705230815002

Well Details

Well ID: 0705230815002
Loading map...
Location: 00/15-08-070-23W5/2
Location Alias: 00/15-08-70-23 W5M
Location Alias 2: 00/15-08-070-23 W5/02
Country: Canada
Province: Alberta
Township: 070
Meridian: 5
Range: 23
Section: 08
County/Municipality: Sturgeon Lake 154
Well Name: GULF ET AL STURLS 15-8-70-23
Operator Name: ConocoPhillips Canada Resources Corp.
License Number: 0027227
License Date: 1964-11-24
License Status: Re-Entered
Spud Date: 1964-11-28
Final Drill Date: 1964-12-30
Well Total Depth: 2673.10 m
Surface Hole Latitude: 55.052130
Surface Hole Longitude: -117.467722

For data sources see[1][2]

Well History

Date Event
1909-09-09 Well Log Performed
1964-11-24 Obtained License
1964-12-30 Finished Drilling
1964-12-30 Well Mode changed to Drilled and Cased
1964-12-31 Production Casing Operation Performed
1965-01-05 Perforation Treatment Performed - Acid Squeeze - Press Used
1965-01-05 Perforation Treatment Performed - Jet Perforation
1965-01-11 Perforation Treatment Performed - Cement Squeeze
1965-01-13 Perforation Treatment Performed - Acid Squeeze - Press Used
1965-01-13 Perforation Treatment Performed - Bullet Perforation
1975-08-09 Perforation Treatment Performed - Bridge Plug Capped W/Cement
1975-08-09 Perforation Treatment Performed - Cement Squeeze
1975-08-12 Perforation Treatment Performed - Cement Squeeze
1975-08-12 Perforation Treatment Performed - Jet Perforation
1975-08-16 Perforation Treatment Performed - Jet Perforation
1975-08-20 Perforation Treatment Performed - Jet Perforation
1976-04-26 Well Began Production
1976-04-26 Well Fluid changed to Gas
1976-04-26 Well Mode changed to Flowing
1980-09-15 Well Fluid changed to Gas
1980-09-15 Well Mode changed to Suspended
1985-01-26 Perforation Treatment Performed - Bridge Plug Capped W/Cement
1985-01-26 Plug Back Performed
1985-01-26 Well Abandoned
1985-01-26 Well Fluid changed to Gas
1985-01-26 Well Mode changed to Abandoned
1986-01-25 Well Log Performed
1986-02-06 Well Log Performed
1986-02-07 Well Log Performed

For data sources see[3]


Perforation Treatments

Perforation Date Perforation Type Interval Top (m) Interval Base (m) Number of Shots
1965-01-05 Perforation 2662.10 2662.70 7
1975-08-12 Cement Squeeze 1508.80 1509.10 0
1975-08-12 Perforation 1444.80 1445.10 13
1975-08-12 Cement Squeeze 1444.80 1445.10 0
1975-08-12 Cement Squeeze 1444.80 1445.10 0
1975-08-16 Perforation 1452.40 1455.40 13
1975-08-20 Perforation 1433.20 1435.00 13
1975-08-20 Perforation 1436.20 1437.40 13
1985-01-26 Packing Device Capped w/Cement 1422.00 1430.00 0
1965-01-05 Acid Treatment 2662.10 2662.70 0
1965-01-11 Cement Squeeze 2662.10 2662.70 0
1965-01-13 Bullet Perforation 2661.20 2661.80 13
1965-01-13 Bullet Perforation 2662.70 2663.00 7
1965-01-13 Acid Treatment 2661.20 2663.00 0
1975-08-09 Cement Squeeze 2661.20 2663.00 0
1975-08-09 Packing Device Capped w/Cement 2563.40 2563.40 0
1975-08-12 Perforation 1508.80 1509.10 13

For data sources see[4]


Production Data

Period Total Production Hours Gas Quantity (m3) Oil Quantity (m3) Water Quantity (m3)
1976 1624 0.0 0.0 0.0
1977 296 0.0 0.0 0.0
1978 2802 0.0 0.0 0.0
1979 4312 0.0 0.0 0.0
1980 3299 0.0 0.0 0.0
1981 84 0.0 0.0 0.0

For data sources see[5]

References