If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.
powered by ChangeDetection
Well ID: 34-005-24169 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":40.66,"lon":-82.15,"icon":""}]} |
Country: United States | |
State: Ohio | |
County: Holmes | |
Municipality: Washington Township | |
Operator Name: HARLEY DRILLING & PRODUCING LT | |
Well Pad ID: | |
Farm/Lease Name: MARVIN YOUNG | |
License Status: Producing | |
License Date: 2013-03-28 | |
Spud Date: 2013-04-27 | |
Spud Drilling Contractor: MARIC DRILLING CO. | |
Final Drill Date: 2013-05-09 | |
Well Total Depth: 5086.00 ft | |
Configuration: Vertical | |
Latitude: 40.660000 | |
Longitude: -82.150000 |
For data sources see[1]
Well Status | Well Status Date | Comment |
---|---|---|
APP | 2013-03-28 | Proposed Formations:TREMPEALEAU, Issued Date:3/28/2013, Expired Date:3/28/2015 12:00:00 PM, Drilling unit acres:40, Proposed Well Type:OG, Proposed Well Class:EW |
Reached Total Depth | 2013-05-09 | |
Completion Report Received | 2014-07-24 | |
Construction Permit Expires | 2015-03-28 | |
Record Last Modified | 2018-03-14 |
For data sources see[2]
Perforation Date | Interval Top (ft) | Interval Base (ft) | Number of Shots |
---|---|---|---|
2014-07-25 | 4940 | 4950 | 28 |
4940 | 4950 | 28 | |
4940 | 4950 | 28 |
For data sources see[3]
Stimulation Date | Chemical Agent | Chemical Agent Concentration (%) | Fracking Fluid Volume | Mass of Proppant Used (lb) | Fracking Company | Comments |
---|---|---|---|---|---|---|
2013-05-31 | ACID | 15 | 2000 Bbl | 28000 | Producers Service Corporation |
For data sources see[4]
Period | Operator Name | Gas Quantity (mcf) | Oil Quantity (bbl) | Production Days |
---|---|---|---|---|
2013 | HARLEY DRILLING & PRODUCING LT | 1130.00 | 1034.00 | 365 |
2014 | HARLEY DRILLING & PRODUCING LT | 1913.00 | 3737.00 | 365 |
2015 | HARLEY DRILLING & PRODUCING LT | 1624.00 | 3452.00 | 365 |
2016 | HARLEY DRILLING & PRODUCING LT | 1987.00 | 2981.00 | 365 |
2017 | HARLEY DRILLING & PRODUCING LT | 1152.00 | 2116.00 | 365 |
2018 | HARLEY DRILLING & PRODUCING LT | 880.00 | 1841.00 | 365 |
Period | Operator Name | Waste Type | Quantity (bbl) | Production Days |
---|---|---|---|---|
2013 | HARLEY DRILLING & PRODUCING LT | Brine | 12668 | 365 |
2014 | HARLEY DRILLING & PRODUCING LT | Brine | 17775 | 365 |
2015 | HARLEY DRILLING & PRODUCING LT | Brine | 18545 | 365 |
2016 | HARLEY DRILLING & PRODUCING LT | Brine | 15273 | 365 |
2017 | HARLEY DRILLING & PRODUCING LT | Brine | 12601 | 365 |
2018 | HARLEY DRILLING & PRODUCING LT | Brine | 10121 | 365 |
Inspection ID | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|
-1206683092 | 2013-10-17 0:00 | PL | No Violations | 0.50 |
-1396654262 | 2018-3-27 0:00: | PW | No Violations | |
-1562228 | 2013-7-30 0:00: | PL | No Violations | 0.50 |
-1785455075 | 2013-4-28 0:00: | DD | No Violations | 8.00 |
-778015674 | 2013-5-6 0:00:0 | DD | No Violations | 1.50 |
0001562228 | 2013-07-30 | Preliminary Restoration | No Violations | The site has been resoiled and graded. Portable tanks remaining on site need to be removed to approve the preliminary restoration. The well is in production. Glenda and Rick of the ODNR Columbus office accompanied the inspector. |
0174038071 | 2013-07-17 | Preliminary Restoration | No Violations | Harley Drilling is on site grading topsoil around the well location. Three portable tanks remain at the location and will need to be removed. Preliminary restoration is nearly completed. |
0341268762 | 2013-04-29 | Drill / Deepen / Reopen | No Violations | Maric is drilling below the surface casing on fluid. Drilling was at 960 feet. BOP test was conducted at 11 this morning, DNR was notified. |
0771353679 | 2013-05-07 | Drill / Deepen / Reopen | No Violations | Hole is at TD, 5086ft. A mud logger is on site. Weak show of gas at the Trempealeau, due to problems with the soap pump the formation is not clear. Harley is considering an E-log of the well, will advise by 4am if he is going to plug or run production casing. Met with Tom Benko to go over plug design in the event the operator decides to plug the well. |
0778015674 | 2013-05-06 | Drill / Deepen / Reopen | No Violations | Drilling has proceeded through the Clinton. Hole at 4800ft, TD expected at about 5100. No show of gas at the Clinton, Columbia personnel were on site when the Clinton was penetrated. |
1169401365 | 2013-05-13 | Drill / Deepen / Reopen | No Violations | The rig has moved out. Pits remain with fluid in them. Portable tank trailers on site. Marics dozer is also on site. One of the portable tanks is leaking brine from a valve on the front of the tank. The operator was contacted and responded to repair the valve. Fluid was contained on the disturbed area of the location. |
1206683092 | 2013-10-17 | Preliminary Restoration | No Violations | Portable tanks have been removed from the location. The site is graded back to fallow field around the well. The landowner is going to be farming around the well. Preliminary restoration is approved. |
1366122795 | 2013-04-16 | Surface Facility Construction | No Violations | Requested by Steve Harley of Harley Drilling to meet on site for pre drilling assessment. The drilling is going to be subcontracted. Site construction is to start this week. The well location is staked. Surrounding ground conditions are crop field. The site is flat, no water features or dwellings close. |
1366644985 | 2013-04-22 | Surface Facility Construction | No Violations | Maric drilling has a dozer on site. Topsoil has been stripped from the pad area and 2 pits have been excavated. Subgrade soil material is sand and gravel. No personnel on site today. |
1368720164 | 2013-05-15 | Drill / Deepen / Reopen | No Violations | Met with Tom Benko on site. The operator was closing pits and grading the site. Fluid in the pits was being picked up by vaccuum truck. Mud was being solidified and buried on site. |
1396654262 | 2018-03-27 | Production Wells | No Violations | The well is equipped with a pump jack, rods and tubing and is in production. There are 2-200 barrel tanks in the tank battery. The ID sign has weathered off the tanks. The operator was contacted to replace identification. |
1425490532 | 2015-03-04 | Production Wells | No Violations | The operator is replacing the production unit. The burner failed on the existing unit. |
1499564990 | 2015-04-14 | Production Wells | No Violations | The well is in production. The separator has been replaced. The operator needs to post ID at the tanks. Harley stated he is having signs made. |
1577734534 | 2019-12-30 0:00 | PW | No Violations | 1.00 |
1736504848 | 2013-06-26 | Preliminary Restoration | No Violations | The site still needs to be topsoiled. There is a large pile of topsoil near the well. The well is equipped with a pump jack, rods and tubing. ID needs to be posted at the well. Upon arrival to the site, plugs in the flow line were dripping brine at the well head. The operator was notified. The pumper arrived on site and determined that the production unit was malfunctioning which caused the flow line to pressure up to about 500 psi. A motor valve on the production unit was adjusted and the leaks stopped when pressure fell back to 90 psi. |
174038071 | 2013-7-17 0:00: | PL | No Violations | 0.50 |
1744667620 | 2013-05-08 | Drill / Deepen / Reopen | No Violations | Requested by Ralph Beech of Maric drilling to witness production string cement job. Began running pipe at 4:15am. Cement at 7:30. Job was partially witnessed. Petroset supplied 125 sacks of Petropic cement (thixotropic) for the job. |
1785455075 | 2013-04-28 | Drill / Deepen / Reopen | No Violations | Requested by Ralph Beech of Maric Drilling to witness surface casing job. See casing ticket for details. |
1863938570 | 2013-09-04 | Preliminary Restoration | No Violations | The site has vegetated with native species. Portable tanks need to be removed from the drill site. Met with the landowner during inspection. |
2030028153 | 2013-05-01 | Drill / Deepen / Reopen | No Violations | Drilling is approaching the Clinton formation. Columbia Gas is concerned they may be in the storage field. Waited on site to see if they were going to penetrate the Clinton formation, however drilling was proceeding slowly and it was not expected to see the Clinton for several more hours. |
2126267640 | 2013-04-30 | Drill / Deepen / Reopen | No Violations | Drilling is continuing on fluid. Bit is at 2087ft in the Oriskany limestone. |
341268762 | 2013-4-29 0:00: | DD | No Violations | 1.00 |
771353679 | 2013-5-7 0:00:0 | DD | No Violations | 6.00 |
For data sources see[9]