If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.
powered by ChangeDetection
Well ID: 34-005-24203 | ![]() Sorry, we have no imagery here. Sorry, we have no imagery here. Sorry, we have no imagery here. ![]() |
Country: United States | |
State: Ohio | |
County: Ashland | |
Municipality: Vermillion Township | |
Operator Name: COLUMBIA GAS TRANSMISSION LLC | |
Well Pad ID: | |
Farm/Lease Name: KENNETH D OBERHOLZER #1 | |
License Status: Storage Well | |
License Date: 2018-07-06 | |
Spud Date: 2018-09-24 | |
Spud Drilling Contractor: H A D INC | |
Final Drill Date: 2018-10-14 | |
Well Total Depth: 2910.00 ft | |
Configuration: Vertical | |
Latitude: 40.790000 | |
Longitude: -82.330000 |
For data sources see[1]
Well Status | Well Status Date | Comment |
---|---|---|
Completion Report Received | 2018-01-30 | |
APP | 2018-07-06 | Proposed Formations:CLINTON SANDSTONE, Issued Date:7/6/2018, Expired Date:7/5/2020 12:00:00 PM, Drilling unit acres:86, Proposed Well Type:GS, Proposed Well Class:POOL |
Reached Total Depth | 2018-10-14 | |
Record Last Modified | 2019-02-01 | |
Construction Permit Expires | 2020-07-05 |
For data sources see[2]
Inspection ID | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|
-1539427771 | 2019-2-27 0:00: | SO | No Violations | |
-911108851 | 2018-11-20 0:00 | DD | No Violations | |
0699319852 | 2018-10-22 | Drill / Deepen / Reopen | No Violations | HAD Drilling is moving equipment off location. Baker Hughes is rigged up on the well with wireline equipment running logs. The operator is planning to bring in a service rig to plug the well. |
0911108851 | 2018-11-20 | Drill / Deepen / Reopen | No Violations | Drilling equipment has been removed. The rig mats have been removed. A wellhead has been installed on the well and the well is shut in. The location needs to be finish graded to complete restoration. |
1538140497 | 2018-09-26 | Storage Well | No Violations | 16 inch conductor has been installed in the well to 160 feet. Workhorse Excavating is installing cellar around the conductor casing. HAD will be moving in the drill rig on 10/1/18 |
1539427771 | 2019-02-27 | Storage Well | No Violations | Performed annual inspection for Columbia Gas Storage Well #12607 on 02/27/2019. The well is equipped with a flanged wellhead with a swedge. The cellar remains open with steel grating laid on top of it. The location has been graded, seeded, and strawed, but vegetation has not yet re-established, nor has the final lease road been built. No problems were noted at the time of the inspection. |
1539873697 | 2018-10-17 | Drill / Deepen / Reopen | No Violations | HAD Drilling is moving out. Drilling is completed. The operator did not run production casing and they are planning to plug the well with a service rig. Met with Rick Conley on location to discuss plugging plans. |
1540391181 | 2018-10-24 | Drill / Deepen / Reopen | No Violations | Hagan has their service rig rigged up on the well. HAD Drilling is moving equipment off location. The plug job was scheduled for today but has been postponed. |
699319852 | 2018-10-22 0:00 | DD | No Violations |
For data sources see[3]