Well Details

Well ID: 34-031-26578
Loading map...
Country: United States
State: Ohio
County: Coshocton
Municipality: Monroe Township
Operator Name: MASON PRODUCING INC
Well Pad ID:
Farm/Lease Name: REISS MARY
License Status: Final Restoration
License Date: 2016-09-13
Spud Date: 1995-08-04
Spud Drilling Contractor: PROFESSIONAL WELL SVC-PWS
Final Drill Date: 1995-08-16
Well Total Depth: 5813.00 ft
Configuration: Vertical
Latitude: 40.410000
Longitude: -82.030000

For data sources see[1]

Well History

Well Status Well Status Date Comment
Oil and Gas 1995-07-14 Issued Date 7/14/95 Expired Date 7/13/96 Acres 0040000 Tool Type RTAF Proposed Formation ROSE RUN-TREMPL Proposed Depth 05813 Proposed Drill Depth 05813
Original Spud 1995-08-03 GM PLUG STATUS CHANGED PER PLUG REPORT
Completed 1995-08-16 GM PLUG STATUS CHANGED PER PLUG REPORT
Reached Total Depth 1995-08-16 GM PLUG STATUS CHANGED PER PLUG REPORT
CO 1995-09-18 1983 MASON DRILLING INC GeoDate 7/14/95
Completion Report Received 1995-10-04 GM PLUG STATUS CHANGED PER PLUG REPORT
Change of Owner 2003-01-14 Operator changed from 1983, MASON DRILLING INC to 7333, MASON PRODUCING
APP 2016-09-13 Proposed Formations:CLINTON, Issued Date:9/13/2016, Expired Date:9/13/2018 12:00:00 PM, Drilling unit acres:40, Proposed Well Type:OG, Proposed Well Class:
Plugged/Abandoned 2017-05-25 GM PLUG STATUS CHANGED PER PLUG REPORT
Record Last Modified 2018-06-26 GM PLUG STATUS CHANGED PER PLUG REPORT
Construction Permit Expires 2018-09-13 GM PLUG STATUS CHANGED PER PLUG REPORT

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
1997-06-29 5618 5766 0
5618 5766 0
5618 5766 0

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
0 0 0 NONE

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
1995 MASON DRILLING INC 49244.00 459.00 104
1996 MASON DRILLING INC 80666.00 746.00 104
1997 MASON DRILLING INC 61658.00 419.00 365
1998 MASON DRILLING INC 54019.00 296.00 104
1999 MASON DRILLING INC 51650.00 271.00 104
2000 MASON DRILLING INC 77863.00 156.00 0
2001 MASON DRILLING INC 49764.00 72.00 365
2002 MASON PRODUCING INC 3663.00 0.00 31
2003 MASON DRILLING INC 0.00 0.00 365
2004 MASON PRODUCING INC 24844.00 0.00 365
2005 MASON PRODUCING INC 18325.00 0.00 365
2006 MASON PRODUCING INC 17026.00 0.00 365
2007 MASON PRODUCING INC 14728.00 0.00 365
2008 MASON PRODUCING INC 13466.00 0.00 366
2009 MASON PRODUCING INC 11492.00 0.00 365
2010 MASON PRODUCING INC 9814.00 14.00 365
2011 MASON PRODUCING INC 10189.00 0.00 365
2012 MASON PRODUCING INC 9517.00 0.00 366
2013 MASON PRODUCING INC 8075.00 0.00 365
2014 MASON PRODUCING INC 7558.00 0.00 365
2015 MASON PRODUCING INC 7026.00 0.00 365
2016 MASON PRODUCING INC 5080.00 0.00 365
2017 MASON PRODUCING INC 723.00 22.00 365

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
1995 MASON DRILLING INC Brine 13 104
1996 MASON DRILLING INC Brine 0 104
1997 MASON DRILLING INC Brine 41 365
1998 MASON DRILLING INC Brine 74 104
1999 MASON DRILLING INC Brine 99 104
2000 MASON DRILLING INC Brine 120
2001 MASON DRILLING INC Brine 8 365
2002 MASON DRILLING INC Brine 87 334
2003 MASON DRILLING INC Brine 0 365
2004 MASON PRODUCING INC Brine 108 365
2005 MASON PRODUCING INC Brine 120 365
2006 MASON PRODUCING INC Brine 60 365
2007 MASON PRODUCING INC Brine 100 365
2008 MASON PRODUCING INC Brine 50 366
2009 MASON PRODUCING INC Brine 84 365
2010 MASON PRODUCING INC Brine 39 365
2011 MASON PRODUCING INC Brine 34 365
2012 MASON PRODUCING INC Brine 100 366
2013 MASON PRODUCING INC Brine 51 365
2014 MASON PRODUCING INC Brine 50 365
2015 MASON PRODUCING INC Brine 90 365
2016 MASON PRODUCING INC Brine 27 365
2017 MASON PRODUCING INC Brine 375 365

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-2147037364 2004-2-11 0:00: PW No Violations
-957206536 2017-5-22 0:00: PB No Violations 2.00
0000011948 Preliminary Restoration No Violations PASSED Y WITNESSED 4/9/97 INSPECTOR DATE 04/0919/97 DATA FROM OLD VAX INFO
0957206536 2017-05-22 Plug / Plug Back No Violations On the day of my inspection I found that Mike Wheeler was rigged up to plug the well. The pit was dug and lined. There was a 500 barrel frac tank of salt water and a water truck of fresh water staged on site. Mike had tripped the tubing out and ran back in to a depth of 5705 feet to set the bottom plug. Mike said that the tubing had been left in the hole with a rotary bit on the end. They were getting drilling mud back when they pulled the tubing. Mike said that he did not want to run the tubing any deeper than one or two joints past the bottom of the 4.5 inch diameter casing because he has encountered problems in the past when plugging a well that was drilled open hole and never cleaned out. Cemenco is scheduled to set the bottom plug tomorrow morning.
0970128675 2017-07-27 Final Restoration No Violations On the day of my inspection I found that the site was final graded and there were no materials or debris. The site was mostly bare with sparse weeds coming up. The surrounding landscape is relatively flat and there were no signs of erosion. I called Mason Producing and left a message to contact me about getting the site seeded. The access road and production equipment will remain in place for existing wells.
11948 PL No Violations
1251810591 2017-05-25 Plug / Plug Back No Violations On the day of my inspection I found that Mike Wheeler had ripped the 4.5 inch diameter casing at a depth of 4510 feet. Mike pulled the casing up to the bottom of the Clinton plug and Formation Cementing established circulation. They circulated approximately 10 barrels of oil out of the hole before they started mixing cement. Wheeler and Formation also set cement plugs at the top of the Big Lime, through the Berea Sand, at the base of the surface casing and at the surface. All of the plugs were set through 4.5 inch casing. Circulation was established and maintained throughout each stage of the plug job. Cement was circulated to surface on the final plug, and it stayed at the surface after pumping. Wheeler said that he would be back next week to cap the well with a plate.
1459037184 2018-06-07 Final Restoration No Violations On the day of my inspection I found that the well site was 80 percent covered in tall grasses and broadleaf vegetation. There were some areas of rocky soil that werent growing very well, but the site was mostly covered. The topography is flat and there were no issues with erosion. There were no oilfield related materials or debris left at the site. The access road and tanks are still in use for existing production wells. This site passes final restoration.
1495558352 2017-05-23 Plug / Plug Back No Violations On the day of my inspection Cemenco pumped a 30 sack bottom plug through 2.375 inch diameter tubing. The calculated plug depth was displaced to 5305 feet with 20.5 barrels of salt water. The well did not circulate during the plug. Mike Wheeler then pulled all of the tubing from the well. I met with Aaron Austin, field supervisor for Mason Producing. He said that there were no known problems with the 4.5 inch diameter casing. They are plugging the well because of the volume of water it produces. Aaron and Mike intend to plug the rest of the well through the 4.5 inch casing. Mike released the casing from the slips and shut down for the day.
1562954245 2010-02-18 Production Wells No Violations Ground snow covered , inspection of site .
1639367466 2008-06-11 Production Wells No Violations Well in production.
2060656258 2017-05-31 Plug / Plug Back No Violations On the day of my inspection I found that Mike Wheeler had rigged down and moved out. The pit was closed and the site was graded to the surrounding contour. There were no oilfield related materials or debris left at the well site. I called Mike Wheeler and he said that they were out on 5/30/17 to cap the well and grade the site. He said that the cement was still at the surface when they capped the well. The access road is still in use for permits 1507 and 1527. The production equipment is still in use for permit 6516. The site still needs to be seeded for erosion control.
2147037364 2004-02-11 Production Wells No Violations Well in production . Gas well
970128675 2017-7-27 0:00: FR No Violations 0.50

For data sources see[9]