Well ID: 34-031-27128
Loading map...
Country: United States
State: Ohio
County: Coshocton
Municipality: Pike Township
Operator Name: HOPCO RESOURCES INC
Well Pad ID:
Farm/Lease Name: MOORE
License Status: Producing
License Date: 2009-12-11
Spud Date: 2010-01-22
Spud Drilling Contractor: H & D DRILLING
Final Drill Date: 2010-02-08
Well Total Depth: 3320.00 ft
Configuration: Vertical
Latitude: 40.210000
Longitude: -82.140000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2009-12-11 Proposed Formations:CLINTON, Issued Date:12/11/2009, Expired Date:12/11/2010 6:00:00 AM, Drilling unit acres:20, Proposed Well Type:OG, Proposed Well Class:POOL
Reached Total Depth 2010-02-08
Completion Report Received 2010-11-15
Construction Permit Expires 2010-12-11
Record Last Modified 2017-02-15

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2011-01-05 3218 3256 48
3218 3256 48
3218 3256 48

For data sources see[3]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
2010-08-11 H2O 15 2200 Bbl 50000 Producers Service Corporation

For data sources see[4]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2010 HOPCO RESOURCES INC 13.00 0.00 107
2011 HOPCO RESOURCES INC 52.00 72.00 365
2012 HOPCO RESOURCES INC 87.00 26.00 366
2013 HOPCO RESOURCES INC 37.00 37.00 365
2014 HOPCO RESOURCES INC 6.00 39.00 365
2015 HOPCO RESOURCES INC 0.00 23.00 365
2016 HOPCO RESOURCES INC 0.00 9.00 365
2017 HOPCO RESOURCES INC 0.00 0.00 0
2018 HOPCO RESOURCES INC 0.00 0.00 0

For data sources see[5] [6]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2010 HOPCO RESOURCES INC Brine 395 107
2011 HOPCO RESOURCES INC Brine 799 365
2012 HOPCO RESOURCES INC Brine 720 366
2013 HOPCO RESOURCES INC Brine 562 365
2014 HOPCO RESOURCES INC Brine 397 365
2015 HOPCO RESOURCES INC Brine 230 365
2016 HOPCO RESOURCES INC Brine 0 365
2017 HOPCO RESOURCES INC Brine 0 0
2018 HOPCO RESOURCES INC Brine 0 0

For data sources see[7] [8]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1135957007 2010-4-28 0:00: PW No Violations
-1225985989 2010-10-26 0:00 PL No Violations
0367146588 2016-11-18 Production Wells No Violations Gary Hopkins called to let me know that they had finished the work on the dike. On the day of my inspection I found that the brine impacted soil had been removed from inside of the dike for the water tank. The dike had been filled in with fresh soil and gravel. This violation is resolved.
0404876371 2010-01-28 Drill / Deepen / Reopen No Violations H & D Drilling ran 7 surface casing and cemented .
0925121628 2011-12-27 Production Wells No Violations Rain all day, Well capable of production.
1135957007 2010-04-28 Production Wells No Violations Drilling pit closed . Well not in production this inspection .
1225985989 2010-10-26 Preliminary Restoration No Violations Well in production. Pit and location graded and seeded. Vegetation started
1264175179 2010-01-22 Drill / Deepen / Reopen No Violations H & D drilling moving in to drill this date .
1281534978 2010-08-11 Completion Testing No Violations Producers fracing well. Flowing back into 300 bl. Tanks .
1409532117 2016-07-19 Production Wells Violations Noted On the day of my inspection I found that the well was being produced with an electric powered pumping unit. The motor was intact and the lines were connected. The valves were open and I could hear gas flowing trough the lines at the separator. The stuffing box and polished rod were covered in oil. I found no oil on the ground at the wellhead. The tank battery consisted of two separate dikes. The upper dike contained one 100 barrel steel tank and one vertical separator. The lower dike contained one 100 barrel steel tank. Identification was written on the lower tank, but there was no emergency contact phone number. The valve at the rear of the upper tank was leaking oil. Half of the base of the lower dike was saturated with brine water. The issues that need addressed to bring this well into compliance are: post complete, legible identification; repair the leak at the valve on the upper tank, and removed the oil impacted soil; remove the brine impacted soil from the lower dike. I called Gary Hopkins to go over the compliance issues. He agreed to have everything taken care of within 30 days.
1462261033 2016-10-14 Production Wells No Violations On the day of my inspection I found that the brine impacted soil in the dike for the water tank had not been cleaned up. I called Gary Hopkins, who claimed that he was unaware that it had not been taken care of yet. He said that they would get it done next week and call me.
1966394610 2016-09-07 Production Wells No Violations On the day of my inspection I found that correct, legible identification had been posted. The stuffing box had been cleaned. The oil impacted soil in the upper dike had been cleared. The brine impacted soil in the lower dike had not been cleared yet. I spoke with pumper Greg Boyd, who said that he was still working to get it cleaned up.
367146588 2016-11-18 0:00 PW No Violations 1.00
404876371 2010-1-28 0:00: DD No Violations
925121628 2011-12-27 0:00 PW No Violations

Violations Commited

Inspection ID Violation ID Violation Date Violation Code Violation Comments
1409532117 US-OH-112060 2016-11-28 Well operation causing pollution and contamination