Well ID: 34-055-21892 | |
Country: United States | |
State: Ohio | |
County: Geauga | |
Municipality: Chester Township | |
Operator Name: CUTTER EXPLORATION INC | |
Well Pad ID: | |
Farm/Lease Name: PALOMBO | |
License Status: Producing | |
License Date: 2006-07-13 | |
Spud Date: 2007-07-06 | |
Spud Drilling Contractor: POULSON DRILLING | |
Final Drill Date: 2007-07-10 | |
Well Total Depth: 3842.00 ft | |
Configuration: Vertical | |
Latitude: 41.550000 | |
Longitude: -81.340000 |
For data sources see[1]
Well Status | Well Status Date | Comment |
---|---|---|
APP | 2006-07-13 | Proposed Formations:CLINTON, Issued Date:7/13/2006, Expired Date:7/13/2007 6:00:00 AM, Drilling unit acres:21.767, Proposed Well Type:OG, Proposed Well Class:POOL |
Reached Total Depth | 2007-07-10 | RBDMS Rec |
Construction Permit Expires | 2007-07-13 | RBDMS Rec |
Completion Report Received | 2008-04-02 | RBDMS Rec |
Record Last Modified | 2017-02-15 | RBDMS Rec |
For data sources see[2]
Perforation Date | Interval Top (ft) | Interval Base (ft) | Number of Shots |
---|---|---|---|
2008-08-12 | 3656 | 3700 | 23 |
3656 | 3700 | 23 | |
3656 | 3700 | 23 |
For data sources see[3]
Stimulation Date | Chemical Agent | Chemical Agent Concentration (%) | Fracking Fluid Volume | Mass of Proppant Used (lb) | Fracking Company | Comments |
---|---|---|---|---|---|---|
H2O | 0 | 69505 Gal | 25000 |
For data sources see[4]
Period | Operator Name | Gas Quantity (mcf) | Oil Quantity (bbl) | Production Days |
---|---|---|---|---|
2008 | CUTTER EXPLORATION INC | 12745.00 | 92.00 | 365 |
2009 | CUTTER EXPLORATION INC | 5701.00 | 0.00 | 365 |
2010 | CUTTER EXPLORATION INC | 6240.00 | 0.00 | 365 |
2011 | CUTTER EXPLORATION INC | 5728.00 | 46.00 | 0 |
2012 | CUTTER EXPLORATION INC | 2405.00 | 0.00 | 366 |
2013 | CUTTER EXPLORATION INC | 1782.00 | 0.00 | 365 |
2014 | CUTTER EXPLORATION INC | 737.00 | 0.00 | 365 |
2015 | CUTTER EXPLORATION INC | 1055.00 | 0.00 | 365 |
2016 | CUTTER EXPLORATION INC | 292.00 | 0.00 | 365 |
2017 | CUTTER EXPLORATION INC | 0.00 | 200.00 | 365 |
Period | Operator Name | Waste Type | Quantity (bbl) | Production Days |
---|---|---|---|---|
2008 | CUTTER EXPLORATION INC | Brine | 215 | 365 |
2009 | CUTTER EXPLORATION INC | Brine | 60 | 365 |
2010 | CUTTER EXPLORATION INC | Brine | 100 | 365 |
2011 | CUTTER EXPLORATION INC | Brine | 70 | |
2012 | CUTTER EXPLORATION INC | Brine | 0 | 366 |
2013 | CUTTER EXPLORATION INC | Brine | 0 | 365 |
2014 | CUTTER EXPLORATION INC | Brine | 0 | 365 |
2015 | CUTTER EXPLORATION INC | Brine | 0 | 365 |
2016 | CUTTER EXPLORATION INC | Brine | 0 | 365 |
2017 | CUTTER EXPLORATION INC | Brine | 0 | 365 |
Inspection ID | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|
-692796936 | 2017-4-10 0:00: | UP | No Violations | |
0692796936 | 2017-04-10 | UrbanProduction Wells | No Violations | At the time of this inspection, the well was equipped with a plunger lift assembly and the valves on the wellhead were open. There was a domestic line plumbed off of the 4. 5 inch casing with four regulators and two meters. The well was fenced and locked. Production records for this well were up to date. The tank battery consisted of one 100 BBL production tank, one 50 BBL steel brine tank and a mechanical separator. Valves on the separator were open and the chart showed production. The production tank vent stack was plumbed into a 55 gallon charcoal filter and topped with a spark arrestor. The tank battery was diked, fenced and locked and had the proper, legible signage. The lease access was stable. No violations observed. |
1184004946 | 2007-07-09 | Drill / Deepen / Reopen | No Violations | Drill depth 3111 Should be finished by Tuesday. Safety fence is up and in good repair. Site is stable and dry. Roads are clean. Fluid level in the pits is good, pits are in good repair. |
1210092033 | 2008-05-06 | Production Wells | No Violations | Operator has graded and seeded site. Lease road is stable and in good repair. Operator is planning on paving apron of the road. Vegetation is beginning to become established. Called Lynn Strazi, need to repair seed around well. He said they are going to bring topsoil on site and repair grade the area. There are spots holding water. Landscape trees have been planted. ID sign is up at tank battery. Well is a rabbit well. Well head is caged. Tank battery has one 100 BBL tank 50 BBl short tank and a mechanical separator. |
1222876543 | 2008-10-01 | Preliminary Restoration | No Violations | Lease road is stable. Site has been graded and seeded. Vegetation is established. Well is a rabbit well which is caged. Tank battery is fenced and man doors are locked. ID signs is up on tank battery. Met Mr. Palombo on site, he is very happy with the way it turned out. Area around the well head is landscaped. |
1359873790 | 2007-03-06 | Drill / Deepen / Reopen | No Violations | Well not drilled as of 03/06/2007. Lease road is flagged. |
1371562494 | 2013-06-18 | UrbanProduction Wells | No Violations | My inspection found the well to be equipped with a plunger lift unit. The annulus valve is open. The well and tank battery are in good repair and surrounded by a chain link fence. The tank battery consists of a 100 BBL production tank, a 50 BBL brine tank, and a mechanical separator. The production tank is vented through a 55 gallon charcoal filter and then plumbed into a spark arrestor. The proper identification is located on the tank battery. The lease road is in stable condition. |
1599840839 | 2020-9-11 0:00: | UP | No Violations | 1.00 |
For data sources see[9]