34-059-24238

Well Details

Well ID: 34-059-24238
Loading map...
Country: United States
State: Ohio
County: Guernsey
Municipality: Valley Township
Operator Name: EQT PRODUCTION COMPANY
Well Pad ID: US-OH-000636
Farm/Lease Name: CLARK
License Status: Plugged Back
License Date: 2012-10-30
Spud Date: 2013-02-17
Spud Drilling Contractor: PI0NEER DRLG
Final Drill Date: 2013-03-09
Well Total Depth: 7090.00 ft
Configuration: Vertical
Latitude: 39.910000
Longitude: -81.610000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2012-10-30 Proposed Formations:TRENTON-BLACK RIVER, Issued Date:10/30/2012, Expired Date:10/30/2014 12:00:00 PM, Drilling unit acres:0, Proposed Well Type:ST, Proposed Well Class:STRT
Correction to Well 2013-01-18 CORRECTION TO CASING PROGRAM.
Plugged Back 2013-03-09
Reached Total Depth 2013-03-09
Construction Permit Expires 2014-10-30
Completion Report Received 2017-11-09
Record Last Modified 2017-11-09

For data sources see[2]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 06/15/2013 06/24/2013 6633 8,820,720.0 516511

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Sand Halliburton Proppant Crystalline Silica 14808-60-7 100 12.7681 0
LP-65 Halliburton Scale Inhibitor Ammonium Chloride 12125-02-9 10 0.00234 0
SP Breaker Halliburton Oxidizing Breaker Sodium Persulfate 7775-27-1 100 0.00011 0
HAI-OS Halliburton Protects casing Propargyl Alcohol 107-19-7 10 0.00016 0
Methanol 67-56-1 60 0.00094 0
28% HCl Halliburton Dissolves cement & minerals in perforations Hydrochloric Acid 7647-01-0 28 0.12697 0
WG-36 Halliburton Gelling Agent Guar Gum 9000-30-0 100 0.00536 0
FR-66 Halliburton Friction Reducer Hydrotreated light petroleum distillate 64742-47-8 30 0.02693 0
Water Halliburton Carrier Water 7732-18-5 100 86.9063 0
BA-40L Halliburton Buffer Potassium carbonate 584-08-7 60 0.00064 0
LGC-36 Halliburton Adds viscosity to fluid Guar Gum 9000-30-0 30 0.00054 0
Naphtha, hydrotreated heavy 64742-48-9 30 0.00054 0
BE-9 Halliburton Biocide Tributyl tetradecyl phosphonium chloride 81741-28-8 10 0.00093 0
LoSurf-300D Halliburton Increases the viscosity of the fluid Naphthalene 91-20-3 5 0.00311 0
Heavy aromatic petroleum naptha 64742-94-5 30 0.01905 0
Trimethylbenzene 95-63-6 1 0.00062 0
Poly(oxy-1,2-ethanediyl), alpha-(4-nonylphenyl)-omega-hydroxy-,

branched

127087-87-0 5 0.00294 0
Ethanol 64-17-5 60 0.0401 0

For data sources see[3]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2013 EQT PRODUCTION COMPANY Brine 14457 111
2014 EQT PRODUCTION COMPANY Brine 10306 363
2015 EQT PRODUCTION COMPANY Brine 3544 357
2016 EQT PRODUCTION COMPANY Brine 2316 274
2017 PIN OAK ENERGY PARTNERS LLC Brine 962 271
2018 PIN OAK ENERGY PARTNERS LLC Brine 902 360
2019 PIN OAK ENERGY PARTNERS LLC Brine 479 90

For data sources see[4] [5]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-135710445 2016-4-6 0:00:0 PW No Violations 1.00
-1396664478 2016-1-6 0:00:0 PW No Violations 2.00
-1490599490 2020-8-5 0:00:0 PW No Violations 1.00
-1618468581 2018-3-29 0:00: PW No Violations 0.50
-325846017 2013-6-25 0:00: PW No Violations
-43510605 2019-11-21 0:00 PW No Violations 0.50
-795179433 2013-1-29 0:00: DD No Violations
-884662476 2013-4-30 0:00: CS No Violations
0064590918 2013-02-01 Production Wells No Violations Witnessed cement job on the conductor casing, it had good returns and stayed up to the surface.
0135710445 2016-04-06 Production Wells No Violations On the day of my inspection I met with EQT Construction Specialist Mathew Skeen and I witnessed the impoundment was closed with final grade in place. Seeding and mulching will take place later this week as equipment is being loaded and moved to close the Kamm impoundment beginning later today.
0217672927 2014-01-28 Preliminary Restoration No Violations The site passed preliminary restoration according to 1509.072A.
0323237666 2017-06-23 Production Wells No Violations On the day of my inspection I witnessed that the production equipment included a sand trap, a GP Unit, a combustor, a sand purge tank, 12-400 barrel tanks and a 140 barrel tank shared with the 34059242640000 Clark 580007 within containment. The well was equipped with a plunger lift system with valves in the open position. Identification was present and production records were current.
0325846017 2013-06-25 Production Wells No Violations On the day of my inspection I witnessed Halliburton rigging up there frac casing to the goat head and there wire line crew was changing perf guns.
0398186199 2016-12-16 Production Wells No Violations On the day of my inspection I witnessed that the production equipment included a sand trap, a GP Unit, a combustor, a sand purge tank, 12-400 barrel tanks and a 140 barrel tank shared with the 34059242640000 Clark 580007 within containment. The well was equipped with a plunger lift system with valves in the open position.
0432928724 2016-03-10 Production Wells No Violations On the day of my inspection I witnessed that the impoundment has been drained with the liner removed and placed into containers for disposal. Doss Enterprises was on site removing the discharge pipe and closure will begin on Monday 3/14/16.
0795179433 2013-01-29 Drill / Deepen / Reopen No Violations Inspection revealed that drill pad is complete and company rep stated that conductor rig will be on site later in the week to start drilling conductor hole.
0798023255 2015-12-07 Production Wells No Violations On the day of my inspection I witnessed that the production equipment included a sand trap, a GP Unit, a combustor, a sand purge tank, and 12-400bbl tanks and 140bbl tank shared with the 34059242640000 Clark 580007 within containment. The well was equipped with a production tree and plunger lift system. Completed walk around with EQT Well Technician Caleb Sterling revealing no violations.
0884662476 2013-04-30 Casing String Witnessed No Violations On the day of my inspection I witnessed the rig crew of the Pioneer rig #72 running the 5.5 production string in the well bore while maintaining circulation.
1366646401 2013-04-22 Drill / Deepen / Reopen No Violations On the day of my inspection the rig was currently drilling the curve for the lateral drill.
1368098694 2013-05-01 Drill / Deepen / Reopen No Violations On the day of my inspection, the crew was rigging down to move.
1372271258 2013-06-25 Completion Testing No Violations On this day of my inspection with Mike Hartshorn, we met with EQT Frac Engineer and discussed procedures, techniques and equipment as Halliburton was preparing to frac.
1396664478 2016-01-06 Production Wells No Violations On the day of my inspection I met with EQT Director Construction and Production Phil Keeton and Manager of Construction Services Jeff Kerr to discuss impoundment closure. Mr. Keeton stated that they got approval from OEPA to discharge water through a filter bag and were planning on beginning in the next week. Upon drainage of the impoundment reclamation back to grade would begin.
1435627070 2018-03-29 Production Wells No Violations On the day of my inspection I accompanied ODNR Inspector Jeff Adams please see his report for details.
1455837458 2016-02-18 Production Wells No Violations On the day of my inspection I witnessed that Elite Well Service had begun pumping out impoundment with an estimated time frame of 2 weeks to complete and upon completion restoration will take place.
1618468581 2018-03-29 Production Wells No Violations On the day of my inspection accompanied by ODNR Inspector Doug Bennett, I witnessed production equipment included a sand trap and GP Unit. A combustor, a sand purge tank, 12- 400 barrel tanks and 140 barrel tank shared with the 34059242380000 Clark 580007 within containment. The well was equipped with a plunger lift system and valves were in open position. Proper identification was present and production report was up to date.
1756320528 2018-10-22 Production Wells No Violations During my inspection the well was equipped with a plunger lift system with valves in the open position with annular pressure monitoring present. The production equipment consisted of two sand traps, two gas production units twelve 400-barrel tanks, and one combustor. Identification was present.
2087222580 2014-01-28 Preliminary Restoration No Violations The site passed preliminary restoration according to 1509.072A.
217672927 2014-1-28 0:00: PL No Violations 0.50
323237666 2017-6-23 0:00: PW No Violations 0.50
398186199 2016-12-16 0:00 PW No Violations 0.50
432928724 2016-3-10 0:00: PW No Violations 1.00
64590918 2013-2-1 0:00:0 PW No Violations
798023255 2015-12-7 0:00: PW No Violations 0.50

For data sources see[6]

References