34-059-24355

Well Details

Well ID: 34-059-24355
Loading map...
Country: United States
State: Ohio
County: Guernsey
Municipality: Millwood Township
Operator Name: ANTERO RESOURCES CORPORATION
Well Pad ID: US-OH-000914
Farm/Lease Name: J HALL UNIT
License Status: Producing
License Date: 2014-03-28
Spud Date: 2014-04-23
Spud Drilling Contractor: SIDEWINDER DRILLING INC
Final Drill Date: 2014-09-28
Well Total Depth: 14376.00 ft
Configuration: Horizontal
Latitude: 39.990000
Longitude: -81.260000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2014-03-28 Proposed Formations:UTICA/POINT PLEASANT, Issued Date:3/28/2014, Expired Date:3/27/2016 12:00:00 PM, Drilling unit acres:594.37, Proposed Well Type:OG, Proposed Well Class:POOL
Correction to Well 2014-06-06 UNIT SIZE DECREASED TO 428.96 ACRES.
Plugged Back 2014-09-20
Reached Total Depth 2014-09-28
Correction to Well 2015-01-02 CHANGE IN TARGET AND TAKE-POINT INFORMATION (FOOTAGES AND COORDINATES) FROM AS DRILLED SURVEY PLAT.
Completion Report Received 2015-05-05
Correction to Well 2015-08-28 UPDATE TO TAKE-POINT FOOTAGES AND COORDINATES FROM AS DRILLED SURVEY PLAT.
Construction Permit Expires 2016-03-27
Change of Owner 2017-02-15 Operator changed from 8894, R E GAS DEVELOPMENT LLC to 8943, ANTERO RESOURCES CORPORATION
Record Last Modified 2017-10-24

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2015-01-16 8785 14325 0
8785 14325 0
8785 14325 0

For data sources see[3]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 11/09/2014 12/09/2014 8174 10,132,300.0 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 Other Chemicals Water 7732-18-5 0 0.00152758 0
Sodium Sulfonate 870-72-4 0 0.00000611 0
Sodium Bisulfate 7631-90-5 0 0.00002100 0
Hydrochloric Acid (10%) PVS Acidizing Hydrochloric Acid 7647-01-0 10 0.0488428 47321.4
Water 7732-18-5 90 0.439585 425893
Water Rex Energy Carrier/Base Fluid Water 7732-18-5 100 87.2727 84,554,300.0
Sand (Proppant) Sargent/Momentive/Preffered Proppant Silica Substrate 14808-60-7 100 11.5621 11,202,000.0
Clay Stabilizer, Cla-Chek G Shrieve Clay Stabilizer Water 7732-18-5 15 0.00047442 459.643
Other - (non-hazardous) NA 85 0.00268838 2604.64
Chlorine Dioxide Baker Hughes Biocide Chlorine Dioxide 1049-04-4 0.3 0 597.835
Slurry Gel, WGA-7 SLR PolyFrac Plus Gel Clay 14808-60-7 5 0.000515187 499.139
Surfactant 154518-36-2 5 0.000515187 499.139
Petroleum Distillate 64742-47-8 45 0.00463668 4492.26
Guar Gum 9000-30-0 45 0.00463668 4492.26
Acid Inhibitor, Unihib G GeoSafe Acid Inhibitor Methanol 67-56-1 5 0.00002397 23.22
Thiourea 62-56-6 1 0.00000479 4.644
Ethoxylated alcohol 68002-97-1 35 0.000167765 162.54
Short Chained Glycol Ether 112-34-5 60 0.000287598 278.64
Acetophenone 98-86-2 1 0.00000479 4.644
Formaldehyde 50-00-0 1 0.00000479 4.644
AP Breaker Sagar Enterprise Gel Breaker Ammonium Persulfate 7727-54-0 100 0.00008257 80
Scale Inhibitor, ScaleHib A Nalco Scale Inhibitor Ethylene Glycol 107-21-1 30 0.00642799 6227.76
Other - (non-hazardous) NA 70 0.0149986 14531.4
ScaleSorb 7 Baker Hughes Scale Inhibitor Organo Phosphorus Salt NA 30 0.00114569 1110
Diatomaceous Earth, Calcined 91053-39-3 100 0.00381896 3700
Crystalline Silica (Quartz) 14808-60-7 1 0 37
Sodium Chloride 7647-14-5 10 0.000381896 370
Parasorb 5005 Baker Hughes Paraffin Inhibitor Complex Ester 68607-07-8 30 0.00286422 2775
Heavy Aromatic Naphtha 64742-94-5 10 0.000954739 925
Crystalline Silica: Quartz (SiO2) 14808-60-7 1 0 92.5
Naphthalene 91-20-3 1 0 92.5
Ethylene-Vinyl Acetate Copolymer NA 5 0 462.5
Mineral Oil 8042-47-5 5 0 462.5
Calcined Diatomaceous Earth 91053-39-3 100 0.00954739 9250
Sodium Perborate Tetrahydrate Global Chemical Resources Friction Reducer Breaker Sodium Perborate 7632-04-4 98.6 0.00000305 2.958
Friction Reducer, Unislick ST-50 CESI Chemical Friction Reducer Petroleum distillates, hydrotreated light 64742-47-8 30 0.0292763 28364.4
Other - (non-hazardous) NA 70 0.0683114 66183.6
Hydrochloric Acid (7.5%) PVS Acidizing Hydrochloric Acid 7647-01-0 7.5 0.0390305 37814.8
Water 7732-18-5 92.5 0.481376 466382

For data sources see[4]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
2014-11-04 H2O 8 6468 Bbl 302600 Universal Well Services Inc. STAGE 1/37

60 SHOTS STAGE 2-36 SEE IMAGES

2014-12-08 H2O 8 6413 Bbl 298300 Universal Well Services Inc. STAGE 37/37

60 SHOTS

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2015 R E GAS DEVELOPMENT LLC 1140541 38476 356
2016 R E GAS DEVELOPMENT LLC 512552 3718 364
2017 ANTERO RESOURCES CORPORATION 248077 1133 286
2018 ANTERO RESOURCES CORPORATION 207904 436 349
2019 ANTERO RESOURCES CORPORATION 36044 2 84

For data sources see[6] [7]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2015 R E GAS DEVELOPMENT LLC Brine 13055 356
2016 R E GAS DEVELOPMENT LLC Brine 7080 364
2017 ANTERO RESOURCES CORPORATION Brine 1585 286
2018 ANTERO RESOURCES CORPORATION Brine 915 349
2019 ANTERO RESOURCES CORPORATION Brine 15 84

For data sources see[8] [9]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1480124958 2018-7-24 0:00: PW No Violations 0.20
-1851329047 2017-2-13 0:00: PW No Violations 0.50
-1908959609 2016-10-20 0:00 PW No Violations 0.20
-512087603 2016-4-28 0:00: PW No Violations 0.20
-786855590 2016-3-22 0:00: PW No Violations 0.50
0075557225 2014-09-16 Drill / Deepen / Reopen No Violations On the day of my inspection I witnessed Sidewinder Drilling Rig #63 had completed cementing their intermediate casing and was preparing to trip in the hole and drill out the dv tool and then test casing. Walk around with Company Man Aaron Wilhite revealed no violations.
0227865630 2014-10-03 Casing String Witnessed No Violations I was onsite to witness the cementing of the surface casing. Sidewinder rig #63 ran 31 joints of 54.5# J-55 STC 13 3/8 casing, tagged fill at 1298, hooked up the lines and washed/cleaned the fill from 1298 and set the shoe at 1308, hooked up Halliburton cement equipment, pumped 50 bbls of gel ahead followed by 5 bbls of freshwater spacer then mixed and pumped 234 bbls of cement slurry weighing 15.6 ppg using 1080 sacks of Halcem cement + additives, released the top plug, displaced cement with 196 bbls of freshwater, bumped the plug at 02:00 hrs with 1,000 psi, released the pressure, floats held. Circulated 5 bbls of good cement to surface with no fallback. Cleaned up, rigged down Halliburton, removed the flowline and prepared to nipple up while waiting on cement.
0258948207 2014-09-08 Drill / Deepen / Reopen No Violations On the day of my inspection I witnessed that Sidewinder Drilling Rig #63 had ran a temperature/bond log and found that top of cement was at 118 feet. Halliburton was on site and 1 inch pipe was ran and tagged up at 118 feet. Halliburton pumped 125 sacks of Class A cement with a 15.6ppg density and a yield of 1.18 and cement came up to 80 feet. Sidewinder Drilling Rig #63 pulled 2 joints of 1 inch pipe and mixed a LCM pill and Halliburton pumped 125 sacks of Class A cement with a 15.6ppg density and a yield of 1.18. Sidewinder Drilling Rig #63 mixed another LCM pill and Halliburton pumped 125 sacks of Class A cement with a 15.6ppg density and a yield of 1.18. Had good cement returns to surface.
0512087603 2016-04-28 Production Wells No Violations On the day of my inspection I witnessed that the well was equipped with a production tree with valves in the open position and a gauge present read 730psi on the casing. Production equipment included a sand trap, a line heater and a GP Unit with a 4 inch sales meter with a 2 inch orifice and chart recorder. Also present an oil stabilizer unit, a vapor recovery system, 15-400bbl tanks all within containment and a gas combustor all shared with the 2H, 6H, 8H, 10H and the 12H.
0649202824 2014-09-23 Drill / Deepen / Reopen No Violations On the day of my inspection accompanied by ODNR Inspector Justin Smith, I witnessed that the H2S alarms were going off and we remained at the guardhouse and met with Company Man Aaron Whilhite to discuss alarms while tripping out of the hole the alarms went off and all non-essential employees were moved off the well pad to a safe muster area and Sweco was in route to determine problem. Sweco arrived on location and found a faulty filter on a sensor and it was replaced and the rig went back to tripping out to change mud motors
0786855590 2016-03-22 Production Wells No Violations On the day of my inspection I witnessed that the well was equipped with a production tree with valves in the open position and a gauge present read 780psi on the casing. Production equipment included a sand trap, a line heater and a GP Unit with a 4 inch sales meter with a 2 inch orifice and chart recorder. Also present an oil stabilizer unit, a vapor recovery system, 15-400bbl tanks all within containment and a gas combustor all shared with the 2H, 6H, 8H, 10H and the 12H.
0832639259 2015-05-12 Production Wells No Violations On the day of my inspection I witnessed that Mercer Well Service was on site running 2.375 EUE 4.7#/ft. tubing to 60 degrees in the curve to a depth of 8445 feet. Completed walk around with Consultant Larry Boone revealing no violations with proper identification present.
0893716576 2016-06-20 Production Wells No Violations On the day of my inspection I witnessed that the well was equipped with a production tree with valves in the open position and a gauge present read 680psi on the casing. Production equipment included a sand trap, a line heater and a GP Unit with a 4 inch sales meter with a 2 inch orifice and chart recorder. Also present an oil stabilizer unit, a vapor recovery system, 15-400bbl tanks all within containment and a gas combustor all shared with the 2H, 6H, 8H, 10H and the 12H. I placed call to REX Energy EHS Supervisor Derrick Smith and I stated that valves were in place for annular monitoring but no gauges or relief valves. Mr. Smith stated that the work would be completed by the end of the week.
1410105724 2014-09-07 Drill / Deepen / Reopen No Violations On the day of my inspection I witnessed that Sidewinder Drilling Rig #63 drilled a 17.5 inch diameter hole to the depth of 1315 feet. Franks Casing Services ran 1315 feet of 13.375 inch J-55 54.5#/ft. Halliburton was on site and gained circulation with 150bbls of fresh water then pumped 50bbls of gel, 5bbls of fresh water and cemented casing with 1025 sacks of Class A cement with a 15.6ppg density and a yield of 1.21. Displaced cement with 195bbls of fresh water. There was no cement returned to surface and plug was landed at 500psi and pressured up to 1000psi for 5 minutes and the floats held. Rex Energy will be running a temperature and bond log to determine TOC and remediation.
1419343118 2015-02-25 Preliminary Restoration No Violations On the day of my inspection I witnessed that flow back has been completed and the well is online and equipped with a production tree with valves in the open position. Production equipment included a sand trap, a GP Unit, an oil stabilizer unit, a vapor recovery system and a total of 15-400bbl tanks all within containment. The site passed preliminary restoration according to ORC 1509.072A.
1480124958 2018-07-24 Production Wells No Violations The purpose of my inspection was a status check. During my inspection the well was equipped with a plunger lift system with valves in the open position. A pressure gauge was present on all casing strings along with a pressure relief valve on the annulus. The production equipment consisted of six gas production units, one combustor, and fifteen 400-barrel tanks. A triethylene glycol dehydration unit with a contact tower and reboiler was located by the tank battery. The identification was located on the wellhead.
1510741228 2019-11-27 0:00 PW No Violations 0.20
1851329047 2017-02-13 Production Wells No Violations On the day of my inspection I witnessed the well was equipped with a production tree with valves in the open position and a gauge present read 500 pounds per square inch on the casing with annular pressure monitoring in place. Production equipment included a sand trap, a line heater and a GP Unit with a 4 inch sales meter with a 2 inch orifice and chart recorder. Also present an oil stabilizer unit, a vapor recovery system, 15-400 barrel tanks all within containment and a gas combustor all shared with the 2H, 6H, 8H, 10H and the 12H.
1908959609 2016-10-20 Production Wells No Violations On the day of my inspection I witnessed that annular monitoring is now in place. The well was equipped with a production tree with valves in the open position and a gauge present read 590 pounds per square inch on the casing. Production equipment included a sand trap, a line heater and a GP Unit with a 4 inch sales meter with a 2 inch orifice and chart recorder. Also present an oil stabilizer unit, a vapor recovery system, 15-400 barrel tanks all within containment and a gas combustor all shared with the 2H, 6H, 8H, 10H and the 12H.
2064562148 2019-03-06 Production Wells No Violations The purpose of my inspection was a status check. During my inspection the well was equipped with a plunger lift system with valves in the open position. Annular pressure monitoring was present and evaluated. The production equipment consisted of six gas production units, one triethylene glycol dehydration unit with a contact tower and reboiler, and fifteen 400-barrel tanks with vent lines plumbed to a compressor and one combustor. The identification was located on the wellhead.
227865630 2014-10-3 0:00: CS No Violations 5.00
258948207 2014-9-8 0:00:0 DD No Violations 8.00
649202824 2014-9-23 0:00: DD No Violations 2.00
75557225 2014-9-16 0:00: DD No Violations 1.50
832639259 2015-5-12 0:00: PW No Violations 1.00
893716576 2016-6-20 0:00: PW No Violations 0.50

For data sources see[10]

References