If you find this page useful and would like to be notified of changes made to this page, start by inputting your email below.
powered by ChangeDetection
Well ID: 34-059-24395 | Loading map...
{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":40.04,"lon":-81.38,"icon":""}]} |
Country: United States | |
State: Ohio | |
County: Guernsey | |
Municipality: Wills Township | |
Operator Name: UTICA RESOURCE OPERATING LLC | |
Well Pad ID: US-OH-001053 | |
Farm/Lease Name: COLE | |
License Status: Producing | |
License Date: 2014-06-23 | |
Spud Date: 2014-07-03 | |
Spud Drilling Contractor: H&P DRILLING | |
Final Drill Date: 2014-11-27 | |
Well Total Depth: | |
Configuration: Horizontal | |
Latitude: 40.040000 | |
Longitude: -81.380000 |
For data sources see[1]
Well Status | Well Status Date | Comment |
---|---|---|
APP | 2014-06-23 | Proposed Formations:POINT PLEASANT, Issued Date:6/23/2014, Expired Date:6/22/2016 12:00:00 PM, Drilling unit acres:548.419, Proposed Well Type:OG, Proposed Well Class:NWC |
Reached Total Depth | 2014-11-27 | |
Construction Permit Expires | 2016-06-22 | |
Completion Report Received | 2016-06-30 | |
Correction to Well | 2016-08-05 | updated Acrage take and target location per as drilled survey. |
Change of Owner | 2018-05-04 | Operator changed from 8595, PDC ENERGY INC to 10114, UTICA RESOURCE OPERATING LLC |
Record Last Modified | 2018-07-24 |
For data sources see[2]
Job Number | Job Start Date | Job End Date | True Vertical Depth (ft) | Total Water Volume (gal) | Total Non-Water Volume (gal) |
---|---|---|---|---|---|
1 | 03/08/2015 | 03/28/2015 | 7204 | 9,877,240.0 | 0 |
Job Number | Trade Name | Supplier | Purpose | Ingredient Name | CAS Number | Additive Percentage by Mass | Job Percentage by Mass | Mass Used (lb) |
---|---|---|---|---|---|---|---|---|
1 | ||||||||
Sand (Proppant), DAP-103, DAP-901,
DAP-925, DWP-111, DWP-125, DWP-126, DWP-614, DWP-901, DWP-905, DWP-938, BioClear 2000, DWP-NE1, Hydrochloric Acid |
CWS | Propping Agent, Iron Control, Scale Inhibitor, Acid Corrosion Inhibitor, Gel Slurry, Crosslinker, Crosslinker, Viscosifier, Breaker, Breaker, Surfactant, Biocide, Non-Emulsifier, Clean Perforations | Borate salt | Proprietary | 0 | 0 | 0 | |
Quaternary ammonium compounds,
bis(hydrogenated tallow alkyl)dimethyl, salts with bentonite |
68953-58-2 | 5 | 0.00969 | 9159.56 | ||||
Potassium hydroxide | 1310-58-3 | 10 | 0.00065 | 610.9 | ||||
Alcohols, C12-13, ethoxylated | 66455-14-9 | 1 | 0.00077 | 725.94 | ||||
Biotite | 1302-27-8 | 0.1 | 0.00264 | 2496.26 | ||||
Oxyalkylated polyamine | Proprietary | 5 | 0.00068 | 645.65 | ||||
Sodium chloride | 7647-14-5 | 1 | 0 | 2.77 | ||||
Apatite | 64476-38-6 | 0.1 | 0.00264 | 2496.26 | ||||
Polyethylene glycol mixture | 25322-68-3 | 70 | 0.01262 | 11934.2 | ||||
Ilmenite | 98072-94-7 | 0.1 | 0.00161 | 1519.96 | ||||
Fatty acids | Proprietary | 30 | 0.00009000 | 83.01 | ||||
Alcohols, C9-11, ethoxylated | 68439-46-3 | 5 | 0.00384 | 3629.7 | ||||
2-Propenoic acid, polymer with 2-propenamide, sodium salt | 25987-30-8 | 40 | 0.02072 | 19587.7 | ||||
Distillates (petroleum), hydrotreated middle | 64742-46-7 | 60 | 0.13181 | 124605 | ||||
Goethite | 1310-14-1 | 0.1 | 0.00471 | 4448.85 | ||||
Illite | 12173-60-3 | 1 | 0.00434 | 4103.89 | ||||
Diallyldimethylammonium chloride | 7398-69-8 | 5 | 0.0018 | 1704.61 | ||||
Poly(oxyethylene)nonylphenol ether | 9016-45-9 | 5 | 0.00259 | 2448.46 | ||||
Methanol | 67-56-1 | 60 | 0.03272 | 30931.9 | ||||
Organic phosphonate 1 | Proprietary | 30 | 0.0041 | 3873.87 | ||||
Isopropanol | 67-63-0 | 40 | 0.01443 | 13636.9 | ||||
Acetic acid | 64-19-7 | 1 | 0.00014 | 129.13 | ||||
Organic phosphonate 2 | Proprietary | 10 | 0.00137 | 1291.29 | ||||
2,2-Dibromo-3-Nitrilopropionamide | 10222-01-2 | 20 | 0.01262 | 11934.2 | ||||
Polyoxyalkylenes | Proprietary | 30 | 0.00009000 | 83.01 | ||||
Propargyl Alcohol | 107-19-7 | 10 | 0.00003000 | 27.67 | ||||
Amine salt | Proprietary | 5 | 0.00068 | 645.65 | ||||
Ethylene glycol | 107-21-1 | 30 | 0.00357 | 3370.79 | ||||
Formaldehyde | 50-00-0 | 0.1 | 0.00002000 | 20.94 | ||||
Calcite | 471-34-1 | 1 | 0.02169 | 20502.2 | ||||
Olefin | Proprietary | 5 | 0.00001000 | 13.84 | ||||
Guar gum | 9000-30-0 | 60 | 0.11627 | 109915 | ||||
Sodium tetraborate pentahydrate | 12179-04-3 | 40 | 0.00258 | 2443.62 | ||||
Borate salt #2 | Proprietary | 0 | 0 | 0 | ||||
Hydrochloric acid | 7647-01-0 | 37 | 0.13149 | 124308 | ||||
Ammonium Persulfate | 7727-54-0 | 100 | 0.00281 | 2661 | ||||
Oxirane, 2-methyl-, polymer with oxirane, monodecyl ether | 37251-67-5 | 1.5 | 0.00291 | 2747.87 | ||||
Ammonium chloride | 12125-02-9 | 10 | 0.00082 | 774.77 | ||||
Crystalline silica (Quartz) | 14808-60-7 | 100 | 11.904 | 11,253,500.0 | ||||
Sorbitan monooleate | 1338-43-8 | 5 | 0.00259 | 2448.46 | ||||
Dimethylcocoamine, bis(chloroethyl)
ether, diquaternary ammonium salt |
68607-28-3 | 40 | 0.01443 | 13636.9 | ||||
Citric acid | 77-92-9 | 60 | 0.00248 | 2339.88 | ||||
Modified thiourea polymer | 68527-49-1 | 30 | 0.00009000 | 83.01 | ||||
Water | Customer & CWS | Base Fluid & Mix Water | Water | 7732-18-5 | 100 | 87.5268 | 82,743,400.0 |
For data sources see[3]
Stimulation Date | Chemical Agent | Chemical Agent Concentration (%) | Fracking Fluid Volume | Mass of Proppant Used (lb) | Fracking Company | Comments |
---|---|---|---|---|---|---|
2020-03-08 | H2O | 0 | 0 | 0 | CalFrac | STAGE 1/46 |
For data sources see[4]
Period | Operator Name | Gas Quantity (mcf) | Oil Quantity (bbl) | Production Days |
---|---|---|---|---|
2015 | PDC ENERGY INC | 252454 | 76668 | 229 |
2016 | PDC ENERGY INC | 278925 | 61160 | 366 |
2017 | PDC ENERGY INC | 192269 | 27415 | 363 |
2018 | UTICA RESOURCE OPERATING LLC | 137014 | 12223 | 361 |
2019 | UTICA RESOURCE OPERATING LLC | 25525 | 2928 | 90 |
Period | Operator Name | Waste Type | Quantity (bbl) | Production Days |
---|---|---|---|---|
2015 | PDC ENERGY INC | Brine | 23586 | 229 |
2016 | PDC ENERGY INC | Brine | 12254 | 366 |
2017 | PDC ENERGY INC | Brine | 6043 | 363 |
2018 | UTICA RESOURCE OPERATING LLC | Brine | 2493 | 270 |
2019 | UTICA RESOURCE OPERATING LLC | Brine | 580 | 90 |
Inspection ID | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|
-1291830802 | 2020-1-24 0:00: | PW | No Violations | 0.10 |
-1520680408 | 2015-4-6 0:00:0 | CT | No Violations | 2.00 |
-1650802951 | 2014-7-29 0:00: | DD | No Violations | 1.00 |
-1736545188 | 2017-3-21 0:00: | PW | No Violations | 0.50 |
-1853968162 | 2014-7-30 0:00: | CS | No Violations | |
-2118068129 | 2016-12-22 0:00 | PW | No Violations | 1.00 |
-236582564 | 2019-3-4 0:00:0 | PW | No Violations | 0.20 |
-327574697 | 2015-7-16 0:00: | PW | No Violations | 0.50 |
-428770419 | 2014-11-17 0:00 | DD | No Violations | 2.50 |
-936343827 | 2016-11-9 0:00: | PW | No Violations | 0.50 |
-9732447 | 2017-3-2 0:00:0 | PW | No Violations | 0.50 |
0009732447 | 2017-03-02 | Production Wells | No Violations | On the day of my inspection following up on Complaint ID 5522, I witnessed no visible gas leak was present near the wellhead and the well was equipped with a plunger lift system and the valves were in the open position. Gauges present read 800 pounds per square inch (psi) on the casing and 400 psi on the tubing with annular pressure monitoring in place. The production equipment included 16-500 barrel tanks within containment and shared with the 1H, 3H and 4H. Also present, a GP Unit, a 2nd stage separator, a vapor recovery system, a vapor recovery system, a compressor unit and 2-combustors. |
0067892462 | 2018-05-17 | Production Wells | No Violations | The purpose of my inspection was a status check. During my inspection the well was equipped with a plunger lift system with production valves in the open position. Gauges were present reading 270 pounds per square inch on the tubing, 678 pounds per square inch on the production casing, 150 pounds per square inch on the 13.375 inch diameter intermediate, and 0 pounds per square inch on the 9.625 inch diameter second intermediate casing. The 13.375 inch diameter intermediate casing was plumbed into the same production line as the production casing and tubing. The production equipment consisted of sixteen 500 barrel tank, four vapor recovery towers, four gas production units, one gas conditioning skid, one heater treater, one compressor, one vent scrubber, two combustors, and a Triethylene Glycol dehydration system consisting of one glycol contact tower and reboiler. |
0236582564 | 2019-03-04 | Production Wells | No Violations | The purpose of my inspection was a status check. During my inspection the well was equipped with a plunger lift system with production valves in the open position. Annular pressure monitoring was present with both intermediate casing strings reading zero pounds per square inch. The production equipment consisted of sixteen 500-barrel tank, four vapor recovery towers, four gas production units, one gas conditioning skid, one heater treater, one compressor, one vent scrubber, two combustors, and a Triethylene Glycol dehydration system consisting of one glycol contact tower and reboiler. |
0327574697 | 2015-07-16 | Production Wells | No Violations | On the day of my inspection the well was equipped with production trees with valves in the open position. Gauges present read 2600psi on the casing and 1800 on the tubing. The production equipment included 16-500bbl tanks within containment and shared with the 1H, 3H and 4H. Also present a sand trap, a GP Unit, a vapor recovery system and a combustor. PDC is preparing to install a trap before the combustor which will send fluids back to the production tanks keeping condensate from reaching the combustor. Completed walk around with Well Technician Carl Caplinger revealing no violations. |
0428770419 | 2014-11-17 | Drill / Deepen / Reopen | No Violations | On the day of my inspection I witnessed that H&P Flex Rig #385 had completed running and cementing their production string on the Cole 1H and successfully skidded back to the Cole 2H. BOP stack has been moved and preparations being made to begin testing. |
0453881687 | 2016-08-23 | Production Wells | No Violations | On the day of my inspection the well was equipped with a plunger lift system and the valves were in the open position. Gauges present read 1200 pounds per square inch (psi) on the casing and 1200 psi on the tubing with annular pressure monitoring in place. The production equipment included 16-500 barrel tanks within containment and shared with the 1H, 3H and 4H. Also present a sand trap, a GP Unit, a vapor recovery system and 2-combustors. |
0789526840 | 2015-04-22 | Preliminary Restoration | No Violations | On the day of my inspection the site passed preliminary restoration according to ORC 1509.072A. |
0936343827 | 2016-11-09 | Production Wells | No Violations | On the day of my inspection the well was equipped with a plunger lift system and the valves were in the open position. Gauges present read 1080 pounds per square inch (psi) on the casing and 490 psi on the tubing with annular pressure monitoring in place. The production equipment included 16-500 barrel tanks within containment and shared with the 1H, 3H and 4H. Also present a sand trap, a GP Unit, a vapor recovery system and 2-combustors. |
1485877960 | 2017-01-31 | Production Wells | No Violations | On the day of my inspection following up on Complaint ID 5522 and accompanied by ODNR Engineering Tech Wayne Cottle, we met with landowner Mike Cole and reviewed his list of complaints. We completed walk around determining if any encroachment off of well site boundaries had occurred, observed installed discharge drains for surface water, observed sound barrier which has been installed around a new compressor unit and light bubbling coming from the cellar on the said well. The well was equipped with a plunger lift system and the valves were in the open position. Gauges present read 850 pounds per square inch on the casing and 460 pounds per square inch on the tubing with annular pressure monitoring in place. The production equipment included 16-500 barrel tanks within containment and shared with the 1H, 3H and 4H. Also present a GP Unit, a 2nd stage separator, a vapor recovery system, 2-combustors and the newly installed compressor unit. Utilizing an ODNR Honeywell PhD6 meter revealed LEL levels at 0. I placed call to PDC EHS Supervisor Maureen Kertis stating my findings, requesting that they determine where the bubbling is coming from and make necessary repairs. Ms. Kertes stated that a hospital muffler will also be installed on the compressor unit upon receipt. |
1520680408 | 2015-04-06 | Completion Testing | No Violations | On the day of my inspection accompanied by ODNR Inspector Matt Fulk, I witnessed that Mountain States Pressure Services & Well Services Rig # 168-03 was replacing rams on the BOP with drilling out the 1st kill plug set at 7080 feet to follow. The 2nd kill plug is set at 7120 feet and the 1st frac plug set at 7980 feet. |
1597510813 | 2019-9-3 0:00:0 | PW | No Violations | 0.30 |
1650802951 | 2014-07-29 | Drill / Deepen / Reopen | No Violations | On the day of my inspection accompanied by ODNR Southeast Regional Supervisor Rocky King, I met with Company Man Randall Downen and discussed upcoming surface string and cementing. First Class Drilling Rig #6 was drilling a 24 inch diameter hole on air at 103 feet with a planned td of 544 feet. |
1736545188 | 2017-03-21 | Production Wells | No Violations | On the day of my inspection following up on Complaint ID 5522, I witnessed no visible gas leak was present near the wellhead and the well was equipped with a plunger lift system and the valves were in the open position. Gauges present read 785 pounds per square inch (psi) on the casing and 430 psi on the tubing with annular pressure monitoring in place. The production equipment included 16-500 barrel tanks within containment and shared with the 1H, 3H and 4H. Also present, a GP Unit, a 2nd stage separator, a vapor recovery system, a vapor recovery system, 3-compressor units and 2-combustors. |
1779677126 | 2014-07-30 | Drill / Deepen / Reopen | No Violations | On the day of my inspection accompanied by ODNR Inspector Justin Smith, I witnessed that First Class Drilling Rig #6 had drilled a 24 inch diameter surface hole to the depth of 544 feet and ran 544 feet of 20 inch 94#/ft. casing and had to wash down the last 5 feet . Universal Well Services was on site and gained circulation with 25bbls of gel, 5bbls of fresh water and cemented casing with 706 sacks of Type 1 cement with 3% CaCl and .25#/sk. of cello flake. While dropping the plug they believed it kicked sideways so the cement was displaced with 183bbls of fresh water. Had good cement returns of 35bbls to surface and no pressure test was performed. Cement head was shut in and they were instructed to leave shut in for 8 hours and complete pressure test. |
1853968162 | 2014-07-30 | Casing String Witnessed | No Violations | I accompanied Doug Bennett on the inspection of this well today. |
1869533075 | 2020-8-24 0:00: | PW | No Violations | 1.00 |
2118068129 | 2016-12-22 | Production Wells | No Violations | On the day of my inspection meeting with PDC EHS Supervisor Tony Long and his replacement EHS Supervisor Maureen Kertis, I witnessed the well was equipped with a plunger lift system and the valves were in the open position. Gauges present read 1040 pounds per square inch (psi) on the casing and 460 psi on the tubing with annular pressure monitoring in place. The production equipment included 16-500 barrel tanks within containment and shared with the 1H, 3H and 4H. Also present, a GP Unit, a 2nd stage separator, a vapor recovery system and 2-combustors. |
2124425304 | 2016-06-08 | Production Wells | No Violations | On the day of my inspection the well was equipped with production trees with valves in the open position. Gauges present read 1250psi on the casing and 1200 on the tubing with annular pressure monitoring in place. The production equipment included 16-500bbl tanks within containment and shared with the 1H, 3H and 4H. Also present a sand trap, a GP Unit, a vapor recovery system and a combustor. |
439271721 | 2019-7-22 0:00: | PW | No Violations | 0.50 |
453881687 | 2016-8-23 0:00: | PW | No Violations | 0.50 |
67892462 | 2018-5-17 0:00: | PW | No Violations | 0.50 |
713284109 | 2020-8-25 0:00: | PW | No Violations | 1.00 |
789526840 | 2015-4-22 0:00: | PL | No Violations | 0.50 |
821160382 | 2019-7-22 0:00: | PW | No Violations | 0.30 |
For data sources see[9]