34-059-24514

Well Details

Well ID: 34-059-24514
Loading map...
Country: United States
State: Ohio
County: Guernsey
Municipality: Millwood Township
Operator Name: ECLIPSE RESOURCES I LP
Well Pad ID: US-OH-001495
Farm/Lease Name: MERCURY A
License Status: Producing
License Date: 2017-08-15
Spud Date: 2017-08-16
Spud Drilling Contractor: H&P DRILLING
Final Drill Date: 2017-09-07
Well Total Depth: 21840.00 ft
Configuration: Horizontal
Latitude: 39.980000
Longitude: -81.280000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2017-08-15 Proposed Formations:UTICA/POINT PLEASANT, Issued Date:8/15/2017, Expired Date:8/15/2019 12:00:00 PM, Drilling unit acres:607.065, Proposed Well Type:OG, Proposed Well Class:POOL
Reached Total Depth 2017-09-07
Correction to Well 2017-12-29 UPDATE TARGET/TAKE PER AS-DRILLED PLAT
Completion Report Received 2018-07-09
Record Last Modified 2018-07-13
Construction Permit Expires 2019-08-15

For data sources see[2]

Perforation Treatments

Perforation Date Interval Top (ft) Interval Base (ft) Number of Shots
2018-07-12 7960 8085 0
2018-07-12 21582 21686 0
21582 21686 0
7960 8085 0
7960 8085 0

For data sources see[3]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 02/25/2018 03/20/2018 7720 23,567,200.0 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 HP-2814 One Aqua Friction Reducer Listed Below Listed Below 0 0 0
Ingredients Listed Above Listed Above Water 7732-18-5 100 0.802951 1,773,180.0
SAND-PREMIUM-WHITE-30/50 Halliburton Proppant Litsted Below Listed Below 0 0 0
SAND-PREMIUM WHITE-40/70, BULK Halliburton Proppant Listed Below Listed Below 0 0 0
FE-2A Halliburton Additive Listed Below Listed Below 0 0 0
Ammonium Persulfate 7727-54-0 95 0.0019978 4412
Ethoxylated alcohols Proprietary 30 0.000181196 401
Propargyl alcohol 107-19-7 10 0.00006040 134
Distilates (petroleum, hydrotreated light) 64742-47-8 18 0.0119595 26411
Oxyalkylated phenolic resin Proprietary 30 0.000245507 543
Organic phosphate copolymer 71050-62-9 25 0.0031788 7020
Modified thiourea polymer Proprietary 30 0.000181196 401
Distillates (petroleum), hydrotreated light 64742-47-8 45 0.0113618 25091
Dazomet 533-74-4 24 0.00603629 13331
Hydrochloric acid 7647-01-0 60 0.480255 1,060,560.0
Ethanol 64-17-5 60 0.000368261 814
Crystalline silica, quartz 14808-60-7 100 9.89207 21,844,900.0
Citric acid 77-92-9 60 0.00252599 5579
Naphthalene 91-20-3 5 0.00003069 68
Poly(oxy-1, 2-ethanediyl), a-tridecyl-w-hydroxy, branched 69011-36-5 5 0.00126242 2788
Sodium hydroxide 1310-73-2 4 0.00100605 2222
1,2,4 Trimethylbenzene 95-63-6 1 0.00000614 14
Methanol 67-56-1 60 0.000362392 801
Ammonium chloride 12125-02-9 1.15 0.00076408 1688
Fatty acids, tall oil Proprietary 30 0.000181196 401
Poly(oxy-1,2-ethanediyl), alpha-(4-nonylphenyl)-omega-hydroxy-,

branched

127087-87-0 5 0.00003069 68
Heavy aromatic petroleum naphtha 64742-94-5 30 0.00018413 407
Olefins Proprietary 5 0.00007248 162
Fresh Water Operator Base Fluid Water 7732-18-5 100 86.9006 191,905,000.0
HP-2220 One Aqua Scale Inhibitor Listed Below Listed Below 0 0 0
OILPERM A Halliburton Non-ionic Surfactant Listed Below Listed Below 0 0 0
HP-9601 One Aqua Breaker Listed Below Listed Below 0 0 0
HYDROCHLORIC ACID Halliburton Solvent Listed Below Listed Below 0 0 0
Produced Water Operator Base Fluid Water 7732-18-5 100 2.2698 5,012,450.0
HAI-OS ACID INHIBITOR Halliburton Corrosion Inhibitor Listed Below Listed Below 0 0 0
SAND-COMMON WHITE - 100 MESH, 3307 LB BAG Halliburton Proppant Listed Below Listed Below 0 0 0
HP-2816 One Aqua Friction Reducer Listed Below Listed Below 0 0 0
MB-7530 One Aqua Biocide Listed Below Listed Below 0 0 0

For data sources see[4]

Stimulations Data

Stimulation Date Chemical Agent Chemical Agent Concentration (%) Fracking Fluid Volume Mass of Proppant Used (lb) Fracking Company Comments
2018-03-20 H2O 15 267868 Gal 274820 Halliburton STAGE 84/84

STAGES 2-83 SEE IMAGES

2018-02-25 H2O 15 288342 Gal 272440 Halliburton STAGE 1/84

STAGES 2-83 SEE IMAGES

For data sources see[5]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2018 ECLIPSE RESOURCES I LP 1636920 186377 227
2019 ECLIPSE RESOURCES I LP 467172 26770 90

For data sources see[6] [7]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2018 ECLIPSE RESOURCES I LP Brine 40038 227
2019 ECLIPSE RESOURCES I LP Brine 8316 90

For data sources see[8] [9]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1232173700 2018-10-16 0:00 PL No Violations 0.20
-1275841984 2017-8-31 0:00: DD No Violations 1.70
-1786394678 2019-3-27 0:00: PW No Violations 0.30
-245616471 2018-4-9 0:00:0 CT No Violations 1.00
-31302280 2020-7-30 0:00: PW No Violations 1.00
-4592411 2017-8-16 0:00: CS No Violations 5.00
0004592411 2017-08-16 Casing String Witnessed No Violations On the day inspection I witnessed that Precision Rathole had drilled a 30 inch diameter hole to the depth of 118 feet and ran 120 feet of 24 inch diameter 94.62 pounds per foot conductor pipe with a 2 foot stick up. Stingray Pressure Pumping was onsite and pumped 10 barrels of fresh water, performed a 400 pounds per square inch pressure test and cemented pipe with 290 sacks Class A cement with 2% CaCl and .25 pound per sack of Celluseal weighing 15.6 pounds per gallon and a yield of 1.21 cubic foot per sack. Cement was weight was verified with pressurized mud scales and displaced to 108 feet with 57.75 barrels of fresh water with good cement returns of 20 barrels to surface. Mix water was tested revealing chlorides of 46 parts per million, pH 7 and 65 degrees.
0245616471 2018-04-09 Completion Testing No Violations The purpose of my inspection was a status check on completions. During my inspection Snubbing unit 10 was currently tripping out of hole after completing drill out operations. The rig has completed drilling out the frac plugs and will install 2.375 inch diameter tubing. The tubing was evaluated on the pipe rack.
0675929409 2017-08-21 Casing String Witnessed No Violations On the day of my inspection I witnessed that H&P Flex Rig #531 had drilled a 17.5 inch diameter hole to the depth of 1356 feet. Wyoming Casing Crew ran 1308.51 feet of 13.375 inch 54.5 pound per foot J-
0727035122 2018-08-07 Preliminary Restoration No Violations The purpose of my inspection was a status check on a preliminary restoration. During my inspection the well was equipped with a production tree style wellhead with valves in the open position. Pressure gauges for all casing strings were present and in plain view with a casing identification tag. The production equipment consisted of three 400-barrel tanks on the West side of the pad, eight horizontal line heaters, eight sand traps, and eight gas production units all on the South side of the pad. The pipe line tie in was located on the North side of the pad. Three 500-barrel Frac tanks are located on the West side of the pad. Signs of erosion remain on the cut slope on the West side of the pad. I spoke with Mark Atkinson with the ODNR Engineering Section and he stated that they would investigate the situation.
1232173700 2018-10-16 Preliminary Restoration No Violations The purpose of my inspection was a status check on a preliminary restoration. During my inspection the well was equipped with a production tree style wellhead with valves in the open position. Annular pressure monitoring was present and evaluated. The production equipment consisted of three 400-barrel tanks on the West side of the pad, eight horizontal line heaters, eight sand traps, and eight gas production units all on the South side of the pad. The pipe line tie in was located on the North side of the pad. Location meets requirements for preliminary restoration.
1275841984 2017-08-31 Drill / Deepen / Reopen No Violations On the day of my inspection I witnessed that H&P Flex Rig #531 was circulating the wellbore with 11.8 pound per gallon mud at 14028 feet, changing over to 5.875 inch drill pipe and changing out their rotating head to accommodate the larger drill pipe. Upon completion H&P Flex Rig #531will continue drilling the 8.5 inch diameter wellbore to a planned total depth of 21899 feet. I met with Eclipse Consultant Jack Turner and completed walk around 5.5 inch diameter 23 pound per foot HCP-110 casing was being offloaded.
1786394678 2019-03-27 Production Wells No Violations The purpose of my inspection was a status check. During my inspection the well was equipped with a production tree style wellhead with valves in the open position. Annular pressure monitoring was present and evaluated. The production equipment consisted of three 400-barrel tanks on the West side of the pad, eight horizontal line heaters, eight sand traps, and eight gas production units all on the South side of the pad. The pipe line tie in was located on the North side of the pad. On the west side of the pad the top of the high wall on the cut slope was eroded toppling material sedimentation down near the tank battery. Mark Atkinson with ODNR Engineering was aware of the issue and he has been in contact with Eclipse Resources.
1841557419 2017-08-16 Drill / Deepen / Reopen No Violations The purpose of my inspection was a status check on drilling the conductor borehole section. During my inspection Precision Drilling was drilling a 30 inch diameter borehole at 75 feet in depth.
1900578775 2018-07-19 Preliminary Restoration No Violations The purpose of my inspection was a status check on a preliminary restoration. During my inspection the well was equipped with a production tree style wellhead with valves in the open position. Pressure gauges for all casing strings were present and in plain view with a casing identification tag. The production equipment consisted of three 400-barrel tanks on the West side of the pad, eight horizontal line heaters, eight sand traps, and eight gas production units all on the South side of the pad. The pipe line tie in was located on the North side of the pad. Eight 500-barrel Frac tanks are located on the West side of the pad. Due to signs of erosion on the cut slope on the West side of the pad the location does not meet Preliminary restoration requirements written under ORC 1509.072 (A). I will consult ODNR Engineering section and discuss the cut slope erosion.
470660907 2019-11-27 0:00 PW No Violations 0.20
675929409 2017-8-21 0:00: CS No Violations 5.00
727035122 2018-8-7 0:00:0 PL No Violations 0.20

For data sources see[10]

References