{"type":"SATELLITE","minzoom":false,"maxzoom":false,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"mappingservice":"googlemaps3","width":"100%","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"wmsoverlay":false,"copycoords":false,"static":false,"zoom":14,"layers":[],"controls":["pan","zoom","type","scale","streetview","rotate"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"resizable":false,"kmlrezoom":false,"poi":true,"markercluster":false,"clustergridsize":60,"clustermaxzoom":20,"clusterzoomonclick":true,"clusteraveragecenter":true,"clusterminsize":2,"imageoverlays":[],"kml":[],"gkml":[],"searchmarkers":"","enablefullscreen":false,"scrollwheelzoom":false,"locations":[{"text":"","title":"","link":"","lat":40.28,"lon":-81.01,"icon":""}]} |
Country: United States | |
State: Ohio | |
County: Harrison | |
Municipality: Cadiz Township | |
Operator Name: ASCENT RESOURCES UTICA LLC | |
Well Pad ID: US-OH-000890 | |
Farm/Lease Name: COBRA CDZ HR | |
License Status: Producing | |
License Date: 2014-03-12 | |
Spud Date: 2014-03-27 | |
Spud Drilling Contractor: NABORS DRILLING | |
Final Drill Date: 2015-07-14 | |
Well Total Depth: 18124.00 ft | |
Configuration: Horizontal | |
Latitude: 40.280000 | |
Longitude: -81.010000 |
For data sources see[1]
Well Status | Well Status Date | Comment |
---|---|---|
APP | 2014-03-12 | Proposed Formations:POINT PLEASANT, Issued Date:3/12/2014, Expired Date:3/11/2016 12:00:00 PM, Drilling unit acres:919.192, Proposed Well Type:OG, Proposed Well Class:EDPW |
Reached Total Depth | 2015-07-14 | |
Correction to Well | 2015-11-13 | CHANGE IN TARGET AND TAKE-POINT INFORMATION (FOOTAGES AND COORDINATES) FROM AS DRILLED SURVEY PLAT. |
Construction Permit Expires | 2016-03-11 | |
Completion Report Received | 2016-04-11 | |
Change of Owner | 2018-10-15 | Operator changed from 8870, HESS OHIO DEVELOPMENTS LLC to 9520, ASCENT RESOURCES UTICA LLC |
Correction to Well | 2018-10-19 | CHANGE IN WELL NAME AND NUMBER (PREVIOUS NAME: CADIZ C #1H-11) |
Record Last Modified | 2018-10-19 |
For data sources see[2]
Job Number | Job Start Date | Job End Date | True Vertical Depth (ft) | Total Water Volume (gal) | Total Non-Water Volume (gal) |
---|---|---|---|---|---|
1 | 11/19/2015 | 12/06/2015 | 8526 | 14,817,800.0 | 0 |
Job Number | Trade Name | Supplier | Purpose | Ingredient Name | CAS Number | Additive Percentage by Mass | Job Percentage by Mass | Mass Used (lb) |
---|---|---|---|---|---|---|---|---|
1 | AP One | U.S. Well Services, LLC | Gel Breakers | Ammonium Persulfate | 7727-54-0 | 100 | 0.00114 | 1630 |
SI-1100 | U.S. Well Services, LLC | Scale Inhibitor | hexamethylenediamine tetra (methylene phosphonic acid) | 38820-59-6 | 10 | 0.00151 | 2170.49 | |
bis (hexamethylene) tramine penta
(methylene phosphonic acid) - phosphate acid |
40623-75-4 | 10 | 0.0007 | 998.423 | ||||
2-Phosphonobutane 1,2,4 tricarboxylic salt | 37971-36-1 | 10 | 0.00117 | 1679.96 | ||||
Ethylene Glycol | 107-21-1 | 40 | 0.00342 | 4905.3 | ||||
Di Water | 7732-18-5 | 80 | 0.00967 | 13891.1 | ||||
Potassium salt of diethylene triamine
penta (methylene phosphonic acid) |
15827-60-8 | 10 | 0.00082 | 1172.06 | ||||
Copolymer of Maleic and Acrylic acid | 26677-99-6 | 10 | 0.00029 | 409.788 | ||||
HVFR-Bx3 | U.S. Well Services, LLC | Friction Reducer | Polyacrylamide | 9003-05-8 | 50 | 0.13052 | 187406 | |
Petroleum Distillate | 64742-47-8 | 50 | 0.07048 | 101199 | ||||
Suspending Agent | 14808-60-7 | 3 | 0.00835 | 11994 | ||||
Ethoxylated Alcohol Blend | Proprietary | 6 | 0.01096 | 15742.1 | ||||
AI-301 | U.S. Well Services, LLC | Acid Corrosion Inhibitors | Hydrogen Chloride | 7647-01-0 | 10 | 0.00008000 | 115.125 | |
Coco amine | 61791-14-8 | 5 | 0.00003000 | 45.6532 | ||||
Diethylene Glycol | 111-46-6 | 30 | 0.00023 | 333.169 | ||||
Methenamine | 100-97-0 | 20 | 0.00018 | 263.994 | ||||
Polyethylene polyamine | 68603-67-8 | 10 | 0.00007000 | 99.9407 | ||||
WFRA-405 | U.S. Well Services, LLC | Friction Reducer | Water | 7732-18-5 | 40 | 0.04324 | 62079.6 | |
Petroleum Distillates | 64742-47-8 | 20 | 0.0174 | 24987 | ||||
Sodium Chloride | 7647-14-5 | 20 | 0.02162 | 31039.8 | ||||
Ethoxylated alcohol blend | Proprietary | 5 | 0.0054 | 7759.95 | ||||
Anionic Polyacrylamide | Proprietary | 40 | 0.04324 | 62079.6 | ||||
Water | Hess Corporation | Base Fluid | Water | 7732-18-5 | 100 | 86.0691 | 123,580,000.0 | |
HCL Acid (3% to 7.5%) | U.S. Well Services, LLC | Bulk Acid | Water | 7732-18-5 | 97 | 0.65967 | 947176 | |
Hydrogen Chloride | 7647-01-0 | 7.5 | 0.05923 | 85038 | ||||
Sand | U.S. Well Services, LLC | Proppant | Crystalline Silica, quartz | 14808-60-7 | 100 | 12.8348 | 18,428,600.0 | |
K-BAC 1020 | U.S. Well Services, LLC | Anti-Bacterial Agent | 2,2-dibromo-3-nitrilopropionamide | 10222-01-2 | 20 | 0.00421 | 6038.37 | |
Deionized Water | 7732-18-5 | 28 | 0.0024 | 3449.09 |
For data sources see[3]
Period | Operator Name | Gas Quantity (mcf) | Oil Quantity (bbl) | Production Days |
---|---|---|---|---|
2016 | HESS OHIO DEVELOPMENTS LLC | 1700695 | 21967 | 273 |
2017 | HESS OHIO DEVELOPMENTS LLC | 1815840 | 6614 | 364 |
2018 | ASCENT RESOURCES UTICA LLC | 989088 | 2904 | 335 |
2019 | ASCENT RESOURCES UTICA LLC | 226802 | 77 | 90 |
Period | Operator Name | Waste Type | Quantity (bbl) | Production Days |
---|---|---|---|---|
2016 | HESS OHIO DEVELOPMENTS LLC | Brine | 13289 | 273 |
2017 | HESS OHIO DEVELOPMENTS LLC | Brine | 7498 | 364 |
2018 | ASCENT RESOURCES UTICA LLC | Brine | 3320 | 335 |
2019 | ASCENT RESOURCES UTICA LLC | Brine | 831 | 90 |
Inspection ID | Inspection Date | Inspection Type | Inspection Result | Inspection Comments |
---|---|---|---|---|
-1140267102 | 2014-12-4 0:00: | CS | No Violations | |
-1605476952 | 2015-4-29 0:00: | DD | No Violations | 1.50 |
-1702274693 | 2016-5-6 0:00:0 | PW | No Violations | 1.00 |
-1720324864 | 2016-3-22 0:00: | PW | No Violations | 2.00 |
-1856087694 | 2018-11-7 0:00: | PW | No Violations | 1.00 |
-654070210 | 2015-4-22 0:00: | DD | No Violations | 1.00 |
0253292323 | 2015-08-03 | Drill / Deepen / Reopen | No Violations | Nabors Drilling Rig # 36 is done with this well and is moving to the Cadiz C 3-H - They advised that they should be ready to drill this evening. |
0568875471 | 2014-04-28 | Drill / Deepen / Reopen | No Violations | I am on site today to witness the running of the 30 inch diameter casing string. The rig has shut down due to mechanical problems and another rig is now scheduled to move on in its place. They have casing at 68 ft and now will need to reduce the casing size and set 24 inch casing. |
0654070210 | 2015-04-22 | Drill / Deepen / Reopen | No Violations | While conducting inspections in the area I noticed that there were two small drilling units on the well pad. I checked the area and there was nobody on site. I contacted Ron Trivisonno and he advised that they plan to drill and prepare the site to meet the new footprint of the larger rig scheduled to drill the wells on this pad. He advised that Jason Simmerman was going to check on the unit to make sure the new footprint meets the needed requirements. |
0666432122 | 2014-06-25 | Drill / Deepen / Reopen | No Violations | On the date of inspection I accompanied ODNR Inspector Randy Akins and ODNR District Supervisor Brent Bear to witness the current drilling status of the well. Refer to Randy Akins report for further details. |
0921374768 | 2016-02-09 | Drill / Deepen / Reopen | No Violations | On the day of my inspection accompanied by inspector Mark Moreland, I was informed by the security guard that all fracking operations have been completed and now a crew is working on installing the production equipment. She also stated that the well should be in production by the end of April. After talking to the security guard a visual inspection was conducted on site, were there were no indications of spills or contamination. |
1140267102 | 2014-12-04 | Casing String Witnessed | No Violations | On the day of my inspection I found that HAD Drilling rig 249 had drilled a 22 hole to 681. They did not encounter a mine. They drilled from 681 to 1934 with a 17.5 bit. They ran new 13.375 casing equipped with cement baskets at 590 and 565. Halliburton cemented the casing to surface with 1380 sacks of HalCem cement blend. Good circulation was maintained throughout the job with approximately 50 barrels of cement returns. |
1345697406 | 2020-3-3 0:00:0 | PW | No Violations | 1.00 |
1396354639 | 2014-03-27 | Drill / Deepen / Reopen | No Violations | HAD Drilling Rig # 680 is on site drilling a 30 inch diameter conductor hole and setting 30 inch diameter casing. The permit requirements are for 100ft of casing and no cementing is required using the concentric drilling method. |
1399302949 | 2014-05-05 | Drill / Deepen / Reopen | No Violations | I am checking the drilling status of HAD Drilling and found that they are no longer on site. The conductor casing appeats to be set. I was advised that they would set 200 ft but nobody on site to confirm that. |
1400092117 | 2014-05-12 | Drill / Deepen / Reopen | No Violations | H &P Drilling Rig # 287 is moving from the Athens B pad to this well. They are not very far along and will be several days before drilling begins. |
1400680137 | 2014-05-20 | Drill / Deepen / Reopen | No Violations | Met Ron Trivisonno on site along with Beth Pratt and Hess Company Man R.L. went over the site stability information and why H & P Drilling Rig # 287 had to rig down and move off the site. Review my concerns on the conductor angular stability. If the section of the pad and toe of the bottom fill move will it move the conductor as well. I need to contact Hess Ohio to find out who is to take over the updates needed to repair the site. |
1404139024 | 2014-06-30 | Casing String Witnessed | No Violations | On the date of inspection I accompanied ODNR Inspector Chris Grimm to witness a surface cement string. Refer to Chris Grimms report for further details. |
1404233807 | 2014-06-30 | Casing String Witnessed | No Violations | On the day of my inspection I found that HAD Drilling ran new 24 casing to a depth of 310. Halliburton cemented the casing to surface with 570 sacks of class A cement. Good circulation was maintained throughout the job with 15 barrels of cement returns. |
1429102258 | 2015-04-14 | Drill / Deepen / Reopen | No Violations | After several days of rain I am checking this site for stability and drilling status. This site has had a stability issue since it was constructed. I am on site today to monitor the area near the road entrance and on the left side of the pad. I did not see any evidence that the slip has moved or is unstable at this time. There is no equipment on site at this time, the casing has night caps on them and pipe cages. |
1438910873 | 2015-07-27 | Drill / Deepen / Reopen | No Violations | Nabors Drilling Rig # 36 is drilling a 8.5 inch diameter hole at 13,646 on oil base drilling fluid. I conducted an inspection of the solids area and found that area to be very neat and clean. No leaks or containment problems are visible at this inspection. |
1499198283 | 2015-04-24 | Drill / Deepen / Reopen | No Violations | I received a call from Jason Simmerman that drilling would continue on this site so that the footprint would match the new drilling rig. There are two small drill units on site today but there is nobody on site during this inspection. |
1506093408 | 2017-09-22 | Preliminary Restoration | No Violations | On the day of my inspection I found the Cadiz C pad to contain five properly labeled wellheads. Wells are equipped with chritmas tree wellheads. Gauges show no surface or intermediate casing pressures. Production equipment on the pad includes five gas production units, one horizontal seperator, one compressor, four 400 barrel steel condensate tanks, and a flare. Tanks are in their own steel containment. Production records current in RBDMS. Site passes preliminary restoration according to ORC 1509.072A. |
1557220194 | 2019-9-5 0:00:0 | PW | No Violations | 1.00 |
1605476952 | 2015-04-29 | Drill / Deepen / Reopen | No Violations | I am on site today because Beaver Construction has two small drill units operating on this well pad today. They are drilling to 85 ft. They plan to set and cement sets of steel pillar posts to match the footprint of the larger rig which they intend to move on to drill the deep section of the well. The footprint which was in place matched that of the H & P 284 Drilling rig which was released. Drilling continues with only one unit drilling today. This operation is to take 8 weeks to complete. |
1666888425 | 2014-03-25 | Drill / Deepen / Reopen | No Violations | HAD Drilling is on site moving equipment in place to drill the conductor hole. They are not drilling at this time. |
1702274693 | 2016-05-06 | Production Wells | No Violations | I arrived on location, were I witnessed the lease road gate was locked and the lease road in adequate condition. The pad is fenced and all man doors were locked. The permitted well is producing off of natural reservoir pressure. RBDMS production records indicate that the well is in producing order.
The production equipment on the pad consists of the following: 4 400 bbl. Production tanks 4 Producing wells 4 Sand separators 1 Combustor 1 Compressor |
1720324864 | 2016-03-22 | Production Wells | No Violations | On the day of my inspection accompanied by Inspector Mark Moreland, I witnessed Hess Ohio is in the process of putting the well into production. At the time of my inspection Hess was flaring off two wells at a time. Production equipment was placed on site and crews were in the process of plumbing all equipment in. Hess plans to have the well in full operation within a week. |
1856087694 | 2018-11-07 | Production Wells | No Violations | On the day of my inspection I found this pad to contain five properly labeled wellheads. Wells are equipped with chritmas tree wellheads. Gauges show no surface or intermediate casing pressure. Production equipment on the pad includes five gas production units, one horizontal seperator, one compressor, four 400 barrel steel condensate tanks, and a flare. Tanks are in their own steel containment. Production records current in RBDMS. Pad is now owned by Ascent resources and named has changed to Ace. |
1891795248 | 2015-05-04 | Drill / Deepen / Reopen | No Violations | Beaver Excavating has two small drilling units drilling and setting 9-5/8 inch diameter casing to 85 ft. They are setting the casing to match the footprint of the larger drilling unit which they intend to move in to drill these wells. Both units are working today and setting casing across the location toward the hill. |
253292323 | 2015-8-3 0:00:0 | DD | No Violations | 1.50 |
568875471 | 2014-4-28 0:00: | DD | No Violations | 1.50 |
666432122 | 2014-6-25 0:00: | DD | No Violations | 2.00 |
921374768 | 2016-2-9 0:00:0 | DD | No Violations | 2.50 |