34-067-21311

Well Details

Well ID: 34-067-21311
Loading map...
Country: United States
State: Ohio
County: Harrison
Municipality: Cadiz Township
Operator Name: ASCENT RESOURCES UTICA LLC
Well Pad ID: US-OH-000890
Farm/Lease Name: COBRA CDZ HR
License Status: Producing
License Date: 2014-03-12
Spud Date: 2014-11-20
Spud Drilling Contractor: NABORS DRILLING
Final Drill Date: 2015-08-02
Well Total Depth: 17675.00 ft
Configuration: Horizontal
Latitude: 40.280000
Longitude: -81.010000

For data sources see[1]

Well History

Well Status Well Status Date Comment
APP 2014-03-12 Proposed Formations:POINT PLEASANT, Issued Date:3/12/2014, Expired Date:3/11/2016 12:00:00 PM, Drilling unit acres:919.192, Proposed Well Type:OG, Proposed Well Class:EDPW
Reached Total Depth 2015-08-02
Correction to Well 2015-11-13 CHANGE IN TARGET AND TAKE-POINT INFORMATION (FOOTAGES AND COORDINATES) FROM AS DRILLED SURVEY PLAT.
Construction Permit Expires 2016-03-11
Completion Report Received 2016-04-11
Change of Owner 2018-10-15 Operator changed from 8870, HESS OHIO DEVELOPMENTS LLC to 9520, ASCENT RESOURCES UTICA LLC
Correction to Well 2018-10-19 CHANGE IN WELL NAME AND NUMBER (PREVIOUS NAME: CADIZ C #2H-11)
Record Last Modified 2018-10-19

For data sources see[2]

Fracking Activities

Fracking Jobs

Job Number Job Start Date Job End Date True Vertical Depth (ft) Total Water Volume (gal) Total Non-Water Volume (gal)
1 11/15/2015 12/06/2015 8524 14,069,600.0 0

Fluid Composition Data

Job Number Trade Name Supplier Purpose Ingredient Name CAS Number Additive Percentage by Mass Job Percentage by Mass Mass Used (lb)
1 HVFR-Bx3 U.S. Well Services, LLC Friction Reducer Ethoxylated Alcohol Blend Proprietary 6 0.01077 14741.7
Suspending Agent 14808-60-7 3 0.00821 11231.8
Polyacrylamide 9003-05-8 50 0.12822 175497
Petroleum Distillate 64742-47-8 50 0.06924 94768.1
AI-301 U.S. Well Services, LLC Acid Corrosion Inhibitors Polyethylene polyamine 68603-67-8 10 0.00006000 88.183
Diethylene Glycol 111-46-6 30 0.00021 293.972
Methenamine 100-97-0 20 0.00017 232.936
Hydrogen Chloride 7647-01-0 10 0.00007000 101.581
Coco amine 61791-14-8 5 0.00003000 40.2822
Water Hess Corporation Base Fluid Water 7732-18-5 100 85.73 117,341,000.0
SI-1100 U.S. Well Services, LLC Scale Inhibitor bis (hexamethylene) tramine penta

(methylene phosphonic acid) - phosphate acid

40623-75-4 10 0.00065 895.32
Di Water 7732-18-5 80 0.0091 12456.6
Copolymer of Maleic and Acrylic acid 26677-99-6 10 0.00027 367.47
Potassium salt of diethylene triamine

penta (methylene phosphonic acid)

15827-60-8 10 0.00077 1051.03
Ethylene Glycol 107-21-1 40 0.00321 4398.75
hexamethylenediamine tetra (methylene phosphonic acid) 38820-59-6 10 0.00142 1946.35
2-Phosphonobutane 1,2,4 tricarboxylic salt 37971-36-1 10 0.0011 1506.47
HCL Acid (3% to 7.5%) U.S. Well Services, LLC Bulk Acid Hydrogen Chloride 7647-01-0 7.5 0.05725 78362.6
Water 7732-18-5 97 0.63769 872825
K-BAC 1020 U.S. Well Services, LLC Anti-Bacterial Agent Deionized Water 7732-18-5 28 0.00245 3351.01
2,2-dibromo-3-nitrilopropionamide 10222-01-2 20 0.00429 5866.66
AP One U.S. Well Services, LLC Gel Breakers Ammonium Persulfate 7727-54-0 100 0.00112 1528
WFRA-405 U.S. Well Services, LLC Friction Reducer Sodium Chloride 7647-14-5 20 0.02048 28034.1
Ethoxylated alcohol blend Proprietary 5 0.00512 7008.52
Water 7732-18-5 40 0.04096 56068.2
Anionic Polyacrylamide Proprietary 40 0.04096 56068.2
Petroleum Distillates 64742-47-8 20 0.01649 22567.4
Sand U.S. Well Services, LLC Proppant Crystalline Silica, quartz 14808-60-7 100 13.2097 18,080,500.0

For data sources see[3]

Production Data

Period Operator Name Gas Quantity (mcf) Oil Quantity (bbl) Production Days
2016 HESS OHIO DEVELOPMENTS LLC 1682904 20325 278
2017 HESS OHIO DEVELOPMENTS LLC 1484173 5464 364
2018 ASCENT RESOURCES UTICA LLC 694119 1298 333
2019 ASCENT RESOURCES UTICA LLC 160888 51 90

For data sources see[4] [5]

Waste Data

Period Operator Name Waste Type Quantity (bbl) Production Days
2016 HESS OHIO DEVELOPMENTS LLC Brine 11021 278
2017 HESS OHIO DEVELOPMENTS LLC Brine 6129 364
2018 ASCENT RESOURCES UTICA LLC Brine 2787 333
2019 ASCENT RESOURCES UTICA LLC Brine 586 90

For data sources see[6] [7]

Inspection Data

Inspections Performed

Inspection ID Inspection Date Inspection Type Inspection Result Inspection Comments
-1512372850 2019-9-5 0:00:0 PW No Violations 1.00
-1927270320 2014-11-18 0:00 DD No Violations 1.00
-493179028 2017-9-22 0:00: PL No Violations 1.00
-578425131 2018-11-7 0:00: PW No Violations 1.00
0493179028 2017-09-22 Preliminary Restoration No Violations On the day of my inspection I found the Cadiz C pad to contain five properly labeled wellheads. Wells are equipped with chritmas tree wellheads. Gauges show no surface or intermediate casing pressures. Production equipment on the pad includes five gas production units, one horizontal seperator, one compressor, four 400 barrel steel condensate tanks, and a flare. Tanks are in their own steel containment. Production records current in RBDMS. Site passes preliminary restoration according to ORC 1509.072A.
0578425131 2018-11-07 Production Wells No Violations On the day of my inspection I found this pad to contain five properly labeled wellheads. Wells are equipped with chritmas tree wellheads. Gauges show no surface or intermediate casing pressure. Production equipment on the pad includes five gas production units, one horizontal seperator, one compressor, four 400 barrel steel condensate tanks, and a flare. Tanks are in their own steel containment. Production records current in RBDMS. Pad is now owned by Ascent resources and named has changed to Ace.
1416410705 2014-11-19 Drill / Deepen / Reopen No Violations On the date of inspection I met with Hess consultants Kevin Toothman and Mike Roberts. They informed me that during the previous day the HAD 245 rig had drilled a 22 inch diameter hole to a depth of 574 feet. They switched to a 17.5 inch diameter hole from 574 feet to the Top of Mine at 613 feet. The rig tagged the Bottom of Mine at 621 feet. As the rig drilled through the Top of Mine they ran into coal bed methane. They shut off the air and the methane was diverted to the flare stack. The flare has been burning since 15:45 11-18-14 through the time of my arrival at 10:00 11-19-14. Mike Roberts estimated the flare to be as high as 20-30 feet the previous night. The flare has diminished overnight to approximately 10-15 feet. Mike and Kevin plan to load the drill pipe and mine void with 1000-1500bbl of fresh water in an attempt to hold back the gas. I was forced to leave the site for another job after they had pumped 570bbl of fresh water through the drill pipe. The flare had diminished to approximately 1-2 feet. Kevin and Mike will follow up with ODNR Inspector Mark Moreland when the gas pressure dies down.
1416621911 2014-11-21 Casing String Witnessed No Violations On the day of my inspection I found HAD Drilling preparing to run 13 3/8 inch casing, this covering the mine string . The mine shaft was at 613 to 624 feet, and drilled to 668 feet. The cement baskets are set at the top being 566 feet and the other at 586 feet. Halliburton will doing the cementing. The casing would not go to bottom. They had tight hole conditions. The casing was removed from the wellbore and the hole was reamed.
1416783725 2014-11-23 Casing String Witnessed No Violations On the day of my inspection I found that HAD Drilling Had reamed the wellbore and reinstalled the casing the original Depth of 668 feet. The cement baskets were installed at 570 fee and at 590 feet 620 sacks of cement was pumped in the bottom. There was no circulation or returns to surface. 63 feet of 1 inch tubing was run on the outside of the 18 5/8 inch casing to grout the pipe to surface. They pumped 570 sacks with no returns to surface. They shut down and order more cement to attempt again to cement to surface.
1416930574 2014-11-24 Casing String Witnessed No Violations HAD Drilling Rig # 249 set 690 ft. Of 18-5/8 inch diameter casing c/w 620 sacks of class A cement on the bottom 50 ft. section below the Mine. Next they cemented the annulus with 1 inch tubing from the basket set at 542 ft. to surface . The basket did not deploy for the original job and a second job was done that did circulate cement to surface. 805 sacks total with 295 sacks used for the last job.
1437402994 2015-07-20 Drill / Deepen / Reopen No Violations Upon arrival on location I found the crew drilling ahead at 6840 feet. There are no issues at this time.
1927270320 2014-11-18 Drill / Deepen / Reopen No Violations I received a call from Company Man Kevin Toothman that HAD Rig # 249 drilled into a Mine at 600 ft. and that they blew out. Drilling has stopped and it is being diverted to the flare stack at this time. There is no uncontrolled fluid flow just a gas blow out. The plan now is to go back in and drill the 50 ft. section to land the Mine String casing after the gas blows down.
82200615 2020-3-3 0:00:0 PW No Violations 1.00

For data sources see[8]